Skip to main content
NTMWD Logo
File #: 25-6153    Version: 1
Type: Administrative Memorandum Status: Agenda Ready
File created: 6/9/2025 In control: Board of Directors
On agenda: 6/26/2025 Final action:
Title: South Mesquite Creek Regional Wastewater Treatment Plant Peak Flow Management and Expansion, Project No. 301-0525-18; Amendment No. 8; and Buffalo Creek Parallel Force Main, Project No. 507-0640-24; Partial GMP No. 1
Sponsors: Wastewater Committee - Committee Action
Indexes: .RWWS - South Mesquite WWTP, Amendment to CMAR Agreement - Partial Guranteed Maximum Price, Amendment to Contract
Code sections: 301-0525-18 - S Mesquite Ck WWTP Peak Flow Management, 507-0640-24 - Buffalo Ck Parallel Force Main
Attachments: 1. Attachment A - Total Contract Price Summary, 2. Attachment B - Contract Amendment Summary, 3. Attachment C - Project Cost and Schedule, 4. Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Regional Wastewater System

Buffalo Creek Interceptor System

 

title

South Mesquite Creek Regional Wastewater Treatment Plant Peak Flow Management and Expansion, Project No. 301-0525-18; Amendment No. 8; and Buffalo Creek Parallel Force Main, Project No. 507-0640-24; Partial GMP No. 1

end

 

SUBJECT

 

recommendation

Authorize funding to Archer Western Construction, LLC in the amount of $936,308 for Amendment No. 8 to the Construction Manager At-Risk (CMAR) Agreement for work related to partial Guaranteed Maximum Price (GMP) No. 1 for the Buffalo Creek Parallel Force Main (BCPFM).  

end

 

PURPOSE

 

The CMAR has submitted a partial Guaranteed Maximum Price (GMP) No. 1 for an early plug valve procurement work package for the Buffalo Creek Parallel Force Main project. Future amendments will be presented to the Board as the remaining work packages are developed, procured, and evaluated.

 

RECOMMENDATION

 

The Executive Director and NTMWD staff recommend the Board of Directors authorize the Executive Director to execute Amendment No. 8 to the Construction Manager At-Risk as follows:

 

CMAR:

Archer Western Construction, LLC (Archer Western)

 

 

Scope: 

Construction, Buffalo Creek Parallel Force Main Partial GMP No. 1

 

 

Project:

No. 507-0640-24, Buffalo Creek Parallel Force Main

 

 

Amount:

$936,308 for Construction

 

 

Committee:

This item will be an item on the June 25, 2025, Wastewater Committee meeting agenda

 

 

 

 

DRIVER(S) FOR THIS PROJECT

 

Strategic Objective:

1.1 High Quality Services                                                                                              1.4 Reliable and Resilient Systems

 

 

Regulatory Compliance

Asset Condition

Capacity

Redundancy/Resiliency

Relocation or External Requests

Operational Efficiency

Safety

Administrative

Policy

Other _____________

 

 

BACKGROUND

 

PROJECT PURPOSE

                     Flow monitoring studies show the South Mesquite Creek Regional Wastewater Treatment Plant (RWWTP) has influent flows higher than its rated wet weather capacity of 82.5 MGD (million gallons per day).  The South Mesquite Creek RWWTP Peak Flow Management preliminary design report determined that onsite storage facilities need to be provided to store peak flows in excess of the wet weather capacity with a phased approach that will provide early peak flow relief for the facility.

                     The Capacity Assessment Study of the southern service area shows that the South Mesquite Creek RWWTP needs to expand from 33 MGD to 41 MGD average daily flow by 2026 to meet the growth projections through 2033.

                     Provide condition assessment and criticality assessment to determine which critical items need to be repaired or replaced in the expansion project, and which items to be included as part of the master plan.

                     A 2023 Feasibility Analysis for Conveyance Alternatives Report recommended a new Buffalo Creek Lift Station No. 2 and Buffalo Creek Parallel Force Main to convey flows from the Buffalo Creek Interceptor System to the new headworks at the South Mesquite Creek RWWTP.   

                     Divert Buffalo Creek Parallel Force Main and Buffalo Creek Force Main flows to a new Headworks at South Mesquite to improve peak flow management at South Mesquite Creek RWWTP and increase wastewater conveyance capacity in the Buffalo Creek Interceptor System to accommodate growth in Forney, Heath, and Rockwall.

 

PROJECT COMPONENTS

                     Early peak flow relief includes upgrades to existing influent pump station no. 1, force main, and re-purposing an existing basin for peak flow storage basin no. 3.

                     Peak flow management includes new parallel 42-inch force mains, new headworks facility no. 2, new peak flow storage basin no. 1 and supporting facilities. 

                     Expansion of the RWWTP to 41 MGD includes a primary clarifier, aeration basins, blower building, secondary sludge pump station, tertiary filters, disinfection, effluent metering, plant water pump station, solids handling, and supporting facilities.

                     Approximately 10,400-feet of 42-inch force main will parallel the existing 36-inch force main from Buffalo Creek Lift Station No. 2 (BCLS2) to the South Mesquite Creek Regional Wastewater Treatment Plant. The 60% CMAR estimated construction cost for the force main is $19,334,700 including estimated CMAR fees.

 

BCPFM PARTIAL GUARANTEED MAXIMUM PRICE (GMP) NO. 1

                     Bid Package 11 - Early Plug Valve Procurement

o                     5 - 42-inch

o                     2 - 36-inch

o                     1 - 24-inch

                     Allowance for 10% tariffs

 

The total 60% CMAR estimate for the solicitation set included herein totaled $1.7 million

 

To determine the Partial GMP No. 1 associated with this Amendment No. 8, the following table details the costs of the bid work package, general conditions, CMAR contingency, and the CMAR fee.

 

Major Scope of Work Description -                      Lump Sum Amount

BCPFM Partial GMP No. 1

 

                     

Bid Package 11 - BCPFM Valve Procurement                     $726,393

Allowances for 10% Tariffs                     $72,640

Total Construction Cost                     $799,033

General Conditions                      $67,918                     

(@8.5% of the Estimated Construction Costs)                     

Total Cost of Work                     $866,951

CMAR Fees (@6.5% of the Cost of Work)                     $56,352

CMAR Contingency (@1.5% of the Cost of Work)                     $13,005

BCPFM Partial Guaranteed Maximum Price No. 1                      $936,308

(Sum of Total Cost of Work and CMAR Fees)                     

 

The following tables are included as attachments:

Attachment A - Total Contract Price Summary

Attachment B - Contract Amendment Summary

Attachment C - Project Cost and Schedule

 

FUNDING

 

Funding for Project No. 507-0640-24 in the amount of $936,308.00 to Archer Western Construction, LLC, is to be made available from the Buffalo Creek Interceptor System Construction Funds.