File #: 24-6081    Version: 1
Type: Administrative Memorandum Status: Agenda Ready
File created: 11/7/2024 In control: Board of Directors
On agenda: 11/21/2024 Final action:
Title: Texoma Raw Water Pipeline to Leonard WTP Pipeline Project No. 101-0642-24; Resolution No. 24-49; Right of Way Acquisition Program
Sponsors: Real Estate Committee - Committee Action
Indexes: Right-of-Way Acquisition Program
Code sections: 101-0642-24 - Texoma Raw Water Pipeline to Leonard WTP Pipeline
Attachments: 1. Resolution, 2. Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Regional Water System

 

title

Texoma Raw Water Pipeline to Leonard WTP Pipeline

Project No. 101-0642-24; Resolution No. 24-49; Right of Way Acquisition Program

end

 

 

SUBJECT

 

recommendation

Authorize funding in the amount of $8,400,000 and adoption of Resolution No. 24-49 to acquire permanent and temporary easements for the Texoma Raw Water Pipeline to Leonard WTP Pipeline project.  

end

 

 

PURPOSE

 

Acquire easements to allow construction of a pipeline to divert 70 million gallons per day (MGD) of raw water from Lake Texoma to the Leonard WTP to increase available raw water for treatment for the Phase III expansion of Leonard WTP to 210 MGD by 2030.

 

 

RECOMMENDATION

 

The Executive Director and NTMWD staff recommend the Board of Directors:

 

1)                     Authorize the Executive Director to execute a right-of-way acquisition program for the Texoma Raw Water Pipeline to Leonard WTP Pipeline, Project No. 101-0642-24, with a budget of $8,400,000; and,

 

2)                     Adopt Resolution No. 24-49, “A Resolution Authorizing the Use of Eminent Domain to Acquire Right-of-Way for the Texoma Raw Water Pipeline to Leonard WTP Pipeline, Project No. 101-0642-24, and Delegating Authority to Initiate Condemnation Proceedings to the NTMWD Executive Director.”

 

Consultant:

N/A

 

 

Scope: 

Right-of-way acquisition and the necessary support services to facilitate the purchase of easements for the project.

 

 

Project:

No. 101-0642-24, Texoma Raw Water Pipeline to Leonard WTP Pipeline

 

 

Amount:

$8,400,000

 

 

Committee:

This will be an item on the November 20, 2024, Real Estate Committee meeting agenda

 

 

DRIVER(S) FOR THIS PROJECT

 

Strategic Objective:

1.2 Successfully Deliver Capital Program

 

 

Regulatory Compliance

Asset Condition

Capacity

Redundancy/Resiliency

Relocation or External Requests

Operational Efficiency

Safety

Administrative

Policy

Other _____________

 

 

BACKGROUND

 

PROJECT PURPOSE

                     To meet projected demand growth, the Leonard Water Treatment Plant (WTP) will require a treatment capacity of 210 MGD before 2030 .

                     Available raw water supply from Bois d’Arc Lake is insufficient to meet future demand at ultimate plant capacity of 280 MGD.

                     Additional 70 MGD of raw water can be supplied from Lake Texoma by constructing an 84-inch pipeline from the Texoma raw water pipeline to the Leonard WTP.

                     The operational flexibility of Texoma Raw Water System will be improved by allowing raw water to be conveyed to both the Wylie WTP and the Leonard WTP.

                     The Leonard WTP’s reliability will also be improved with this second raw water source.

                     Construction is projected to begin early 2026 and completed in 2029.

                     Permanent and Temporary easements are required; and will be located along the general route shown on the accompanying map.

 

SUPPORT SERVICES

                     The firm of Saunders, Walsh & Beard, Attorneys & Counselors will serve as counsel on the acquisition of the properties.

                     An appraiser will provide appropriate reports.

                     Professional services related to certain property ownership issues will be provided by a title company.

 

 

                     Survey services  will perform title survey for purchase & acquisition and verify property lines and potential easement locations, when necessary.

                     Based on ongoing projects and the goal of commencing construction on this project by February 2026, contracted land agents or acquisition company(s) will be employed to assist in easement acquisition.

 

 

FUNDING

 

Funding in the amount of $8,400,000 for Right-Of-Way Acquisition Services is to be made available in the Regional Water System Capital Improvement.