Skip to main content
NTMWD Logo
File #: 24-6000    Version: 1
Type: Administrative Memorandum Status: Agenda Ready
File created: 3/13/2024 In control: Board of Directors
On agenda: 3/28/2024 Final action:
Title: Leonard Water Treatment Plant Phase II; Project Number 101-0600-21 Tabulation of Bids and Award of Contract
Sponsors: Water Committee - Committee Action
Indexes: .RWS, .RWS - Leonard Water Treatment Plant, Tabulation of Bids and Award of Contract
Code sections: 101-0600-21 - Leonard Water Treatment Plant, Phase II
Attachments: 1. Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Regional Water System

 

title

Leonard Water Treatment Plant Phase II; Project Number 101-0600-21

Tabulation of Bids and Award of Contract

 

end

SUBJECT

 

recommendation

Authorize award of a construction contract for the Leonard Water Treatment Plant Phase II Expansion Project.

 

end

 

PURPOSE

 

Award a construction contract for an additional 70 Million Gallons per Day (MGD) water treatment capacity at Leonard Water Treatment Plant (Leonard WTP) making additional use of the Bois d’Arc Lake water supply.  Additional capacity from the Bois d’Arc Lake system is consistent with NTMWD’s plans and efforts to continuously supply safe potable water to its growing service area.

 

RECOMMENDATION

 

The Executive Director, NTMWD staff and Jacobs Engineering Group, Inc. recommend the Board of Directors authorize the award of a contract as follows:

 

Consultant:

Thalle Construction Co., Inc.

 

 

Scope: 

Construction

 

 

Project:

No. 101-0600-21, Leonard Water Treatment Plant Phase II

 

 

Amount:

Construction Contract Amount: $290,955,000

 

 

Strategic Objective:

1.2 Successfully Deliver Capital Program  1.4 Reliable and Resilient System Capacity 

 

 

Committee:

This will be an item on the March 27, 2024, Water Committee meeting agenda.

 

 

 

 

 

 

 

DRIVER(S) FOR THIS PROJECT

 

Regulatory Compliance

Asset Condition

Capacity

Redundancy/Resiliency

Relocation or External Requests

Operational Efficiency

Safety

Administrative

Policy

Other _____________

 

 

 

BACKGROUND

 

PROJECT PURPOSE 

                     Construct Phase II of the Leonard WTP

                     This second phase of the Leonard WTP will include facilities and equipment to treat an additional 70 million gallons per day for a total treatment capacity of 140 MGD.

                     Construction is estimated to take four years with Start-up and Commissioning expected by December of 2027.

                     Planning level construction cost for Phase II is $267,000,000.00. 

                     Master Planning for future expansions of the Leonard WTP includes an ultimate capacity of 280 MGD. 

  

 

PROJECT COMPONENTS 

                     New treatment facilities included in Phase II to increase the capacity:

o                     Pre-Treatment (flocculation and sedimentation) basin

o                     Filter complex

o                     Liquid oxygen unloading facilities 

o                     East and West Chemical Buildings

o                     Chlorine Contact basin and Clearwell

                     Improvements and additional equipment to existing facilities:

o                     Influent Pump Station - additional pumps

o                     Additional ozone generators and process equipment

                     Electrical equipment

                     Supervisory Control and Data Acquisition (SCADA) instrumentation and controls programming

                     Site and yard piping

 

 

 

 

 

 

 

TABULATION OF BIDS

 

Sealed bids for construction of Leonard WTP Phase II were received at 2:00 p.m. on Wednesday, February 14, 2024, as tabulated below:

 

Bidder                                                                                                          Total Bid                                           Recommendation

Archer Western Construction, LLC                      $294,074,000

Thalle Construction Co., Inc.                                           $290,955,000                     Lowest Responsible Bidder

ENGINEER’S OPINION OF                                           $267,000,000

PROBABLE COST

 

LOWEST RESPONSIBLE BIDDER HISTORY

 

Thalle Construction Co., Inc. has successfully completed or is currently in construction on several similar projects for the NTMWD and for other entities:

 

                     NTMWD Project No. 101-0344-13 TSR under CMAR No. 1, Leonard WTP Terminal Water Storage Reservoir (Completed 2021); subcontractor to Archer Western Construction

                     Brushy Creek Wastewater Treatment Plant, Round Rock, TX

                     Sam’s Branch Water Reclamation Facility, Clayton, NC

                     Trinity River Authority Regional Wastewater, Phase IIIB, Grand Prairie, TX

                     Trinity River Authority Red Oak Peak Flow Storage & Flood, Red Oak, TX

                     Paris Wastewater Treatment Plant Improvements, Phase I, Paris, TX

                     NACA Wastewater Treatment Plant, Bentonville, AR

 

Based on their standing as lowest responsible bidder, the information provided, and reports by the supplied references, the NTMWD staff and Jacobs Engineering Group, Inc. recommend award of the contract to Thalle Construction Co., Inc.

 

 

 

 

FUNDING

 

Funding in the amount of $290,955,000 to Thalle Construction Company Inc is to be made available in the Regional Water System SWIFT Construction Funds contingent upon Texas Water Development Board approval of the contract and release of funding.