File #: 24C-12    Version: 1
Type: Consent Agenda Item Status: Agenda Ready
File created: 3/11/2024 In control: Board of Directors
On agenda: 3/28/2024 Final action:
Title: Wylie Water Treatment Plant Backup Power Improvements - Authorization for Alternate Project Delivery Method; Project No. 101-0564-20; Resolution No. 24-12
Sponsors: Water Committee - Committee Action
Indexes: .RWS - Transmission Systems, Construction Manager At-Risk
Code sections: 101-0564-20 - Wylie WTP Backup Power Improvements
Attachments: 1. Resolution, 2. Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Regional Water System

 

title

Wylie Water Treatment Plant Backup Power Improvements - Authorization for Alternate Project Delivery Method; Project No. 101-0564-20; Resolution No. 24-12

end

 

SUBJECT

 

recommendation

Authorize the use of Construction Manager At-Risk (CMAR) project delivery method for the Wylie Water Treatment Plant (WTP) Backup Power Improvements project.

end

 

PURPOSE

 

CMAR project delivery approach provides a distinct advantage for early identification and procurement of major equipment and systems that have traditional long lead times for configuration approvals, fabrication and delivery to the project site.  Such equipment specific to this project includes large diesel generators, transformers and electrical switch gear.  The CMAR delivery approach allows the procurement process to progress concurrent with the detailed design, which helps compress project schedule. 

 

RECOMMENDATION

 

The Executive Director and NTMWD staff recommend the Board of Directors adopt Resolution No. 24-12, A Resolution authorizing the use of this alternative delivery approach in accordance with Texas Administrative Code Chapter 2269, Contracting and Delivery Procedures for Construction Projects.

 

 

Project:

No. 101-0564-20, Wylie Water Treatment Plant Backup Power Improvements

 

 

Amount:

N/A

 

 

Strategic Objective:

1.1 High Quality Services

 

1.4 Reliable and Resilient System Capacity

 

 

Committee:

This will be an item on the March 27, 2024, Water Committee meeting agenda

 

 

 

 

DRIVER(S) FOR THIS PROJECT

 

Regulatory Compliance

Asset Condition

Capacity

Redundancy/Resiliency

Relocation or External Requests

Operational Efficiency

Safety

Administrative

Policy

Other

 

BACKGROUND

 

PROJECT PURPOSE

                     This project will enable the NTMWD to continuously monitor Oncor’s 138 kilovolt electrical service to the Wylie WTP and to transfer loads to the emergency backup generator system in the event of an Oncor power outage.

                     In October 2023, the Board approved Administrative Memorandum No. TMP-23-31 authorizing final design of the Wylie WTP Backup Power Improvements.  These improvements are based on the recommendations developed during the preliminary engineering phase as the most viable path forward for a dependable emergency backup power system.

                     This action seeks the Board’s authorization for use of the alternative delivery approach.

                     Future actions dealing with selection of a CMAR and Authorization of CMAR Preconstruction and Procurement Services will be brought at a later time.  Other subsequent recommendations dealing with construction Work Packages will also be brought at a later time.    

 

PROJECT COMPONENTS 

                     Centralized generator yard located just west of the north electrical substation;

                     Generators will be sized to support 460 million gallons per day (MGD) of WTP treatment capacity;

                     Design will meet requirements of Texas Senate Bill No. 3; and

                     Supervisory Control and Data Acquisition (SCADA) system interface to assist control room operators.

 

 

FUNDING

 

None required at this time.