Title: Request to Declare Certain NTMWD Property Salvage or Surplus and Authorization to Enter into a Contract to Facilitate the Trade of Such Assets; Bois d'Arc Lake Boat Ramps; Project No. 101-0436-16
Sponsors: Water - NC
Indexes: .RWS - Bois d'Arc Lake
Code sections: 101-0436-16 - LBCR Reservoir Boat Ramps
Related files: 25C-33, 25C-6, 24C-26
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Regional Water System

 

title

Request to Declare Certain NTMWD Property Salvage or Surplus and Authorization to Enter into a Contract to Facilitate the Trade of Such Assets;

Bois d’Arc Lake Boat Ramps; Project No. 101-0436-16

end

 

 

SUBJECT

 

recommendation

Declare certain NTMWD property salvage or surplus and authorize the Executive Director or their designee to enter into a contract to facilitate the trade of such assets for new equipment.

end

 

 

PURPOSE

 

Request the Board of Directors declare the John Deere 1590 No-Till-Drill (Asset No. 1658) salvage or surplus in order to replace the asset with new equipment.

 

 

RECOMMENDATION

 

The Executive Director and NTMWD staff recommend the Board of Directors declare the asset listed below as salvage or surplus and authorize the Executive Director or their designee to enter into a contract with United Ag & Turf for the trade of such assets for new operational equipment as follows:

 

Vendor:

United Ag & Turf

 

 

Scope: 

Trade of NTMWD Property Declared Salvage or Surplus

 

 

Project:

Bois d’Arc Lake Boat Ramps, Procurement of Equipment for Bois d’Arc Lake Operations; Project No. 101-0436-16

 

 

Amount:

$40,000 Trade-In Credit (Asset No. 1658)

 

 

Strategic Objective:

1.4 Reliant and Resilient Systems

 

 

Committee:

N/A

 

 

DRIVER(S) FOR THIS PROJECT

 

Regulatory Compliance

Asset Condition

Capacity

Redundancy/Resiliency

Relocation or External Requests

Operational Efficiency

Safety

Administrative

Policy

Other _____________

 

 

BACKGROUND

 

                     Maintaining vegetative cover on the Bois d’Arc Lake dam is critical to helping prevent erosion and maintain the embankment.

                     Vegetative maintenance on the embankment requires periodic reseeding to ensure healthy, consistent vegetative cover.

                     The No-Till Drill originally acquired is not conducive to the type of seed used to establish vegetation during the construction of the Bois d’Arc Lake dam and is difficult to operate on steep slopes.

                     Declaring this item salvage or surplus will facilitate a trade credit that will be used to purchase the following equipment:

o                     Landoll Icon Pull Type Grader

o                     Agspray 1000 Gallon Water Trailer

o                     Agspray UTV-Mounted Sprayer

o                     Turbo Turf Hydroseeder

o                     Blue Diamond Sod Roll Roller Attachment

                     This equipment will better support vegetation maintenance and erosion control activities by Bois d’Arc Lake Operations staff

                     With the trade-in credit of $40,000, this transaction will result in a balance due of $3,610.

                     All actions taken on the disposition of these assets are in accordance with NTMWD practices, state law, the NTMWD Personnel Policies Manual and Board Policies Manual.

 

 

FUNDING

 

Funding for the remaining balance of $3,610 has been authorized by Administrative Memorandum No. 5703 for the Procurement of Equipment for Bois d’Arc Lake Operations. No additional funding needed.