File #: 24-6001    Version: 1
Type: Administrative Memorandum Status: Agenda Ready
File created: 3/18/2024 In control: Board of Directors
On agenda: 3/28/2024 Final action:
Title: Leonard Water Treatment Plant Phase II; Project No. 101-0600-21 Leonard WTP Terminal Storage Reservoir Phase II; Project No. 101-0601-21 Bois d'Arc Lake Raw Water Pump Station Phase II; Project No. 101-0602-21 Leonard WTP High Service Pump Station Phase II; Project No. 101-0603-22 Additional Services for Construction Management and Inspection - Construction Phase
Sponsors: Water Committee - Committee Action
Indexes: .RWS, .RWS - Bois d'Arc Lake, Construction Management Services Agreement - Additional Services, Construction Management Services Agreement - Inspection Services
Code sections: 101-0600-21 - Leonard Water Treatment Plant, Phase II, 101-0601-21 - Leonard WTP Terminal Storage Reservoir, Phase II, 101-0602-21 - Bois D'arc Lake Raw Water Pump Station, Phase II, 101-0603-22 - Leonard WTP HSPS South
Attachments: 1. Attachment - Additonal Construction Managment and Inspection Services Fee
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Regional Water System

 

title

Leonard Water Treatment Plant Phase II; Project No. 101-0600-21

Leonard WTP Terminal Storage Reservoir Phase II; Project No. 101-0601-21

Bois d’Arc Lake Raw Water Pump Station Phase II; Project No. 101-0602-21

Leonard WTP High Service Pump Station Phase II; Project No. 101-0603-22

 

Additional Services for Construction Management and Inspection - Construction Phase

 

end

SUBJECT

 

recommendation

Recommend Board authorization for additional construction management and inspection services, and Internal Inspection Services for the construction of four projects that comprise the Bois d’Arc Lake System Phase II Program.

 

end

 

PURPOSE

 

This agreement will provide outsourced technical and administrative resources for the daily activities related with the oversight, construction management, and quality assurance, and supplemental inspection support of the NTMWD internal Inspectors during the construction across the four projects of the Bois d’Arc Lake System Phase II Program. This is a subsequent phase of the Construction Management Services Agreement to Black & Veatch, which was previously authorized by Administrative Memorandum No. 5923 in July 2023.

 

RECOMMENDATION

 

The Executive Director and NTMWD staff recommend the Board of Directors authorize additional services as follows:

 

Consultant:

Black and Veatch Corporation (Black & Veatch)

 

 

Scope: 

Construction Management and Inspection Services for   Bois d’Arc Lake System Phase II Program 

 

 

Project:

Leonard Water Treatment Plant Phase II (Leonard WTP), Project No. 101-0600-21  Leonard WTP Terminal Storage Reservoir (TSR) Phase II,  Project No. 101-0601-21  Bois d’Arc Lake Raw Water Pump Station (BDL RWPS) Phase II, Project No. 101-0602-21  Leonard WTP High Service Pump Station (HSPS) Phase II, Project No. 101-0603-22 

 

 

Amount:

Construction Management and Inspection Amount: $15,956,446 Internal Inspection Services Amount: $1,962,000 

 

 

Strategic Objective:

1.4 - Reliable and Resilient System capacity

 

1.2 - Successfully deliver capital program

 

 

Committee:

This will be an item on the March 27, 2024, Water Committee meeting agenda 

 

DRIVER(S) FOR THIS PROJECT

 

Regulatory Compliance

Asset Condition

Capacity

Redundancy/Resiliency

Relocation or External Requests

Operational Efficiency

Safety

Administrative

Policy

Other _____________

 

BACKGROUND

 

PROJECT PURPOSE

                     Provide outsourced construction management services prior to the construction contract bid to represent the District’s interest in coordinating the bid documents and in providing review and comment pertaining to potential risks associated with the scheduling or sequencing of the separate projects.

                     Once construction has commenced, maintain documentation and reporting to the District staff of issues and status relating to the construction progress

                     Provide inspection support, in coordination with assigned District Inspection personnel, of the multiple construction projects for quality assurance and adherence to the contract documents. 

 

CONSTRUCTION MANAGEMENT SERVICES

                     Administer and manage the day-to-day requirements of the Projects in regular coordination with the District Program Manager (PM) and In-house Inspectors.

                     Serve as primary contact with the General Contractor with primary responsibility for construction contract administration.

                     Provide direction and manage the efforts of inspectors.

                     Coordinate with the District PM on issues that impact ongoing operations.

                     Monitor construction activities for conformance with contract, schedule, and quality assurance.

 

 

SUPPLEMENTAL INSPECTION SERVICES

                     Provide third-party inspectors to supplement NTMWD Inspectors.

                     Work alongside and in coordination with NTMWD Inspectors to enforce the Contract documents during construction activity.

                     Provide daily status of schedule and field issues by preparing Daily Field Reports and photos and participate in ongoing communications with the Contractor.

                     Coordinate with project team in processing requests for information, submittals, clarification of the plans, and processing of claims.

 

The initial term of these services is two years.  At that point the services and ongoing needs of the District will be reassessed for possible extension. Attached is the table summarizing the third-party additional construction management and inspection services fee.

 

 

INTERNAL INSPECTION SERVICES

 

NTMWD’s North System Construction Inspection Staff (one Senior Inspector and two Construction Inspectors) will be assigned to provide inspection services for this project.

 

 

Attached is the table summarizing the additional construction management and inspection services fee.

 

 

 

 

FUNDING

 

Funding in the amount $15,956,446 to Black & Veatch, and $1,962,000 for NTMWD Internal Inspection Services is to be made available in the Regional Water System SWIFT Construction Funds contingent upon Texas Water Development Board approval of the contract and release of funding.