Skip to main content
NTMWD Logo
File #: 25C-31    Version: 1
Type: Consent Agenda Item Status: Agenda Ready
File created: 6/9/2025 In control: Board of Directors
On agenda: 6/26/2025 Final action:
Title: Wylie Complex Reclaim System Improvements; Project No. 101-0666-25; Engineering Services Agreement, Preliminary Engineering
Sponsors: Water Committee - Committee Action
Indexes: .RWS - Regional Water System, Engineering Services Agreement - Preliminary Engineering Design
Code sections: 101-0666-25 - Wylie Complex Reclaim System Improvements
Attachments: 1. Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Regional Water System

 

 

title

Wylie Complex Reclaim System Improvements; Project No. 101-0666-25; Engineering Services Agreement, Preliminary Engineering

 

end

SUBJECT

 

recommendation

Authorize funding in the amount of $487,000 for an engineering services agreement with HDR Engineering, Inc. for preliminary design of the proposed Wylie Complex Reclaim System Improvements project.

 

end

PURPOSE

 

The Engineer will evaluate the hydraulics of the WTP I and WTP II reclaim system , propose modifications , evaluate the capacity of WTP I and WTP II reclaim basins, and develop a matrix of options based on different operational conditions.  A Preliminary Design Report will be provided  incorporating the results of hydraulic evaluations, pipeline changes and additional reclaim volume options, system modifications, and recommendations.

 

RECOMMENDATION

 

The Executive Director and NTMWD staff recommend the Board of Directors authorize the Executive Director to execute an engineering services agreement (ESA) as follows:

 

Consultant:

HDR Engineering, Inc.

 

 

Scope:

Preliminary Engineering Design

 

 

Project:

101-0666-25, Wylie Complex Reclaim System Improvements

 

 

Amount:

$487,000

 

 

Committee:

This will be a Champion Update at the June 25, 2025, Water Committee meeting

 

 

 

 

DRIVER(S) FOR THIS PROJECT

 

Strategic Objective:

1.1 High Quality Services

 

Regulatory Compliance

Asset Condition

Capacity

Redundancy/Resiliency

Relocation or External Requests

Operational Efficiency

Safety

Administrative

Policy

Other _____________

 

BACKGROUND

 

Historically, reclaim return flows at all water treatment plants were returned to the treatment process as raw water enters each plant, downstream of chlorine dioxide addition and mixing boxes. These reclaim return flows contain constituents that affect water chemistry as they are mixed, and the eventual overall finished water quality.

 

In particular, WTP I reclaim can become overloaded during normal operating conditions, particularly when WTP II is offline, resulting in impacts to WTP I’s water quality and filter capacity.

 

Similar challenges exist at Plants III and IV. Upgrades to the reclaim return at WTP III are currently under construction, and upgrades at WTP IV are included under a current design effort.  Redirecting the reclaim flows to each water treatment plant’s mixing box will provide an opportunity for chemical dosing to facilitate the sedimentation process.

 

 

PROJECT PURPOSE

Improve finished water quality following conversion to biologically active filtration (BAF)

 

PROJECT COMPONENTS

 

                     Evaluate the hydraulics and operations of the WTP I and WTP II reclaim system from the filters to the reclaim basins

                     Propose modifications to pipelines

                     Evaluate the capacity of WTP I and WTP II reclaim basins and develop a matrix of options to consider based on different operational conditions such as plant flow, frequency of backwash, and backwash parameters.

                     Determine if any modifications to chlorine dioxide feed facilities at the WTP I and WTP II mixing structure are required, and any changes to other assets that are part of the WTP I and WTP II reclaim system.

                     Provide a Preliminary Design Report incorporating results of hydraulic evaluations, pipeline changes, reclaim volume options, system modifications, and other recommendations.

 

 

 

 

BASIC SERVICES

 

                     Preliminary and General Items

                     Project Set-up and Administration

                     Review System Performance Limiting Factors

                     Evaluate Performance Limiting Factors

                     Identify and Evaluate Alternatives

                     Final Recommendations

 

SPECIAL SERVICES

                     Subsurface Utility Exploration

 

CONSULTANT SELECTION PROCESS

 

                     A total of 3 engineering firms, Freese and Nichols, Inc., HDR Engineering, Inc., and Garver, LLC. were interviewed and HDR Engineering, Inc. was deemed as the most highly qualified firm for this project.

 

ENGINEERING SERVICES FEE

Description                     Amount

Basic Services                     $ 453,000

Special Services                     $ 34,000

Requested Amount                     $ 487,000

 

FUNDING

 

Funding in the amount of $487,000 to HDR Engineering, Inc. is to be made available utilizing the Regional Water System Extendable Commercial Paper (ECP) Program as the appropriation source; issuance of ECP notes will occur as cash needs arise.