Title: A Resolution Expressing Official Intent to Reimburse Costs of Regional Water System Bois d'Arc Lake / Leonard Water Treatment Plant - Phase III; Resolution No. 26-28
Indexes: .RWS
Attachments: 1. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Regional Water System

 

title

A Resolution Expressing Official Intent to Reimburse Costs of Regional Water System Bois d’Arc Lake / Leonard Water Treatment Plant - Phase III; Resolution No. 26-28

 

end

SUBJECT

 

recommendation

Adopt Resolution No. 26-28 authorizing the reimbursement of the Regional Water System, Bois d’Arc Lake (BDL) / Leonard Water Treatment Plant (LWTP) - Phase III costs with the Texas Water Development Board’s (TWDB’s) State Water Implementation Fund for Texas (SWIFT) Program Funding.

 

 

end

PURPOSE

 

This bond issue finances various components of the BDL / LWTP Phase III - Leonard Treated Water Pipeline No. 2 (LTWPL No. 2) project. The Reimbursement Resolution allows the District to reimburse itself with bond proceeds for capital expenditures incurred 60 days prior to adoption of the resolution and for future expenditures, if necessary.

 

RECOMMENDATION

 

The Executive Director, NTMWD staff, McCall, Parkhurst and Horton, LLP, NTMWD Bond Counsel, and Hilltop Securities, Inc., NTMWD Financial Advisor, recommend the Board of Directors adopt Resolution No. 26-28, “A Resolution Expressing Official Intent to Reimburse Costs of Regional Water System Bois D’Arc Lake/Leonard Water Treatment Plant - Phase III”.

 

 

Consultant:

N/A

 

 

Scope: 

N/A

 

 

Project:

BDL/LWTP Phase III - Leonard Treated Water Pipeline No. 2

 

 

Amount:

N/A

 

 

Committee:

This item was reviewed with the Finance Committee on April 8, 2026. 

 

 

DRIVER(S) FOR THIS PROJECT

 

Strategic Objective:

2.3 Rigorous Financial Management

 

Regulatory Compliance

Asset Condition

Capacity

Redundancy/Resiliency

Relocation or External Requests

Operational Efficiency

Safety

Administrative

Policy

Other _____________

 

 

BACKGROUND

 

                     Resolution No. 26-28 will provide NTMWD with the option to be reimbursed for expenditures incurred 60 days prior to August 27, 2026, and all future expenditures on or after August 27, 2026, in an amount not to exceed $354,475,000 for the cost of planning, procuring, construction, expanding and improving the BDL/LWTP - Phase III in the Regional Water System.

                     Resolution No. 26-28 is necessary to satisfy certain federal tax law requirements relating to such reimbursement and has been reviewed by McCall, Parkhurst and Horton, bond counsel for NTMWD.

 

FUNDING

 

No funding is requested.