Legislation Details

File #: 26-6267    Version: 1
Type: Administrative Memorandum Status: Agenda Ready
File created: 5/12/2026 In control: Board of Directors
On agenda: 5/28/2026 Final action:
Title: Wylie Water Treatment Plant Complex Valve Improvements; Project No. 101-0672-25; Tabulation of Bids and Award of Contract
Indexes: .RWS - Wylie Plant Complex, Tabulation of Bids and Award of Contract
Code sections: 101-0672-25 - Wylie WTP Complex Valve Improvements
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Regional Water System

 

title

Wylie Water Treatment Plant Complex Valve Improvements; Project No. 101-0672-25; Tabulation of Bids and Award of Contract

end

 

SUBJECT

 

recommendation

Authorize funding in the amount of $556,042 to VAG, USA, LLC for a contract to procure valves for the Wylie WTP Complex Valve Improvements project.

end

 

PURPOSE

 

Due to the long lead time for large valves (estimated 42 weeks), NTMWD recommended beginning the procurement and manufacture of the 60-inch and 72-inch butterfly valves before bidding and selecting a general contractor for this project.  This will allow NTMWD to have the valves delivered to the project site during the next shutdown season, allowing the contractor to perform the installation when water demands are lower.

 

RECOMMENDATION

 

The Executive Director, NTMWD staff and Pape-Dawson Consulting Engineers, LLC recommend the Board of Directors authorize the award of a contract as follows:

 

Contractor:

VAG, USA, LLC

 

 

Scope: 

Procurement and Manufacture of three (3) 60-inch double offset butterfly valves and two (2) 72-inch double offset butterfly valves

 

 

Project:

No. 101-0672-25, Wylie WTP Complex Valve Improvements

 

 

Amount:

$556,042

 

 

Committee:

This will be an item on the May 27, 2026, Water Committee meeting agenda

 

 

 

 

 

 

DRIVER(S) FOR THIS PROJECT

 

Strategic Objective:

1.3 Proactive Asset and Maintenance Management                                                                                              1.4 Reliable and Resilient Systems

 

 

Regulatory Compliance

Asset Condition

Capacity

Redundancy/Resiliency

Relocation or External Requests

Operational Efficiency

Safety

Administrative

Policy

Other _____________

 

 

BACKGROUND

 

The Wylie WTP Complex has insufficient pipeline isolation capabilities, which limit the ability to shut down facilities for proper maintenance.  NTMWD staff have identified valves that need to be immediately repaired or replaced in support of upcoming projects and future isolation needs for maintenance activities. Valve failures can significantly impact plant operations and treatment capacity, thereby posing a risk to NTMWD’s ability to meet customers’ demands. 

 

PROJECT PURPOSE

                     Project No. 101-0528-19, the High Service Pump Stations 2-2 and 2-3 Control Valve Improvements, cannot proceed due to the identified leaking valves and insufficient isolation capabilities.

                     On September 25, 2025, the Board of Directors approved Administrative Memorandum No. 25-6184 to authorize an engineering services agreement with Pape-Dawson Consulting Engineers, LLC for the design of this project.

 

PROJECT COMPONENTS

                     Removal of 60-inch butterfly valve ISO-011 and its interconnection pipe between the North Garland Pipeline No. 2 Phase I pipeline and High Service Pump Station 2-1 discharge pipeline

                     Replacement of a 72-inch butterfly valve (ISO-112) in a more suitable location and the addition of a new 72-inch butterfly valve on the North Garland Pipeline No. 2 Phase I pipeline

                     Replacement of the 60-inch butterfly valve ISO-002 and the addition of a new 60-inch butterfly valve on the North Garland Pipeline

                     Replacement of the 60-inch butterfly valve ISO-003 on the interconnect between the North Garland Pipeline and the North Garland Pipeline No. 2 Phase I pipeline

TABULATION OF BIDS

 

Sealed bids for procurement of the valves were received at 2:00 p.m. on Thursday April 23, 2026, as tabulated below:

 

Bidder                     Total Bid                     Recommendation

The Valve Agency, Inc.                     $471,931                     Non-responsive bid

VAG USA, LLC                     $556,042                     Lowest responsible bid Recommended for Award

Municipal Valve & Equipment Co.                     $719,811                     

Core & Main                     $779,700                     Non-responsive bid

                                          

ENGINEER’S OPINION OF                      $605,000

PROBABLE COST                                          

 

 

LOWEST RESPONSIBLE BIDDER HISTORY

 

One VAG valve is currently in service in the NTMWD conveyance system, and additional VAG valves have been purchased for future installation by NTMWD Facilities Services.  Pape-Dawson Consulting Engineers, LLC recommends VAG valves, which meet the specified requirements.

 

Based on their standing as the lowest responsible bidder, the information provided, and reports by the supplied references, the NTMWD staff and Pape-Dawson Consulting Engineers, LLC recommend award of the contract to VAG, USA, LLC.

 

 

INTERNAL INSPECTION SERVICES

 

NTMWD will authorize inspection services with the upcoming general contractor contract Administrative Memorandum.  No inspections are expected to be needed before that time.

 

 

FUNDING

 

Funding to VAG USA LLC in the amount of $556,042 is to be made available in the Regional Water System Capital Improvement Fund.