File #: 26-6245    Version: 1
Type: Administrative Memorandum Status: Agenda Ready
File created: 3/11/2026 In control: Board of Directors
On agenda: 3/26/2026 Final action:
Title: Leonard Water Treatment Plant Phase III; Project No. 101-0653-24; Engineering Services Agreement - Preliminary Engineering
Indexes: .RWS - Regional Water System, Engineering Services Agreement, Engineering Services Agreement - Preliminary Engineering Design, Preliminary Engineering - Engineering Services Agreement
Code sections: 101-0653-24 - Leonard WTP Phase III
Attachments: 1. Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Regional Water System

 

title

Leonard Water Treatment Plant Phase III; Project No. 101-0653-24; Engineering Services Agreement - Preliminary Engineering

 

end

SUBJECT

 

recommendation

Authorize funding in the amount of $4,564,900 to Carollo Engineers, Inc. for an engineering services agreement for preliminary design development of the proposed Phase III expansion of the Leonard Water Treatment Plant (WTP).

 

end

PURPOSE

 

The purpose of this preliminary design service is to develop the design of the Leonard Water Treatment Plant (WTP) Phase III expansion project from the conceptual level up to the 30% design phase. Leonard WTP is part of the Bois d’Arc Lake Regional Water System. The phase III expansion will increase the treatment capacity of the Leonard WTP to 210 million gallons per day (MGD). Also, this preliminary design effort will produce engineering reports needed to support the Texas Water Development Board State Water Implementation Fund for Texas (SWIFT) funding application for final design and construction of the project.

 

RECOMMENDATION

 

The Executive Director and NTMWD staff recommend the Board of Directors authorize the Executive Director to execute an engineering services agreement (ESA) as follows:

 

 

Consultant:

Carollo Engineers, Inc.

 

 

Scope: 

Preliminary Engineering

 

 

Project:

No. 101-0653-24, Leonard Water Treatment Plant Phase III 

 

 

Amount:

$4,564,900 

 

 

Committee:

This will be an item on the March 25, 2026, Water Committee meeting agenda

 

 

 

DRIVER(S) FOR THIS PROJECT

 

Strategic Objective:

1.2 Successfully Deliver Capital Program                                                                                              1.4 Reliable and Resilient Systems

 

Regulatory Compliance

Asset Condition

Capacity

Redundancy/Resiliency

Relocation or External Requests

Operational Efficiency

Safety

Administrative

Policy

Other _____________

 

BACKGROUND

 

The Leonard Water Treatment Plant (WTP) treats raw water from Bois d’Arc Lake.  Plans are currently underway to provide additional raw water from Lake Texoma to supplement the water rights at Bois d'Arc Lake. The initial Phase I Leonard WTP development, completed in 2023, provided a capacity of 70 million gallon per day (MGD). Following a re-rating approval by the Texas Commission on Environmental Quality (TCEQ) in 2025, the Leonard WTP Phase I now has a production capacity of 81 MGD. Phase II, currently under construction, will increase the production capacity of the plant to 150 MGD. Phase III will increase the treatment capacity of Leonard WTP to 210 MGD. In August 2024, Administrative Memorandum No. 24-6047 awarded conceptual design services for the Leonard WTP Phase III expansion. The conceptual design is now completed, and NTMWD is ready to proceed with the preliminary design.

 

PROJECT PURPOSE

 

                     The ultimate planned capacity of Leonard WTP is 280 MGD.

                     The projected demand growth in the service area of Leonard WTP calls for Leonard WTP to have an available treatment capacity of 210 MGD no later than Spring 2031.

                     This effort will evaluate the existing Phase I and Phase II processes to identify opportunities for optimal use of existing facilities. 

                     Take the design from the conceptual level to 30% design to achieve a production capacity of 210 MGD.

                     The conceptual design level estimated construction cost to achieve 210 MGD production capacity is $508,521,000.

 

PROJECT COMPONENTS

 

                     Develop preliminary design documents to 30% for Leonard WTP expansion facilities to achieve 210 MGD production capacity. Documents will include a design criteria sheet with updated hydraulic profile, general site and grading plans, process flow diagrams, basic architectural, structural and mechanical plan views, building mechanical air flow schematics, electrical diagrams and site plan, generator sizing, preliminary process and instrumentation diagrams, network architecture diagrams, major equipment lists, and equipment specifications.

                     Design connection of the Phase III process units to existing Phase I and Phase II infrastructure.

                     This service agreement will enable master planning of the remaining process facilities needed to achieve the ultimate production capacity of 280 MGD. 

                     Develop and review documents for Construction Manager At-Risk (CMAR) procurement, including Request for Qualifications and Request for Proposals.

                     Produce environmental assessment report and engineering feasibility report to support Texas Water Development Board SWIFT funding application for final engineering design and construction.

                     Conduct review of current and potential drinking water regulations to ensure that design is compliant with treatment standards and meets targets.

                     Perform a study to optimize existing processes, identify opportunities/hydraulic or process bottlenecks in Phase I and Phase II.

                     Determine 30% level opinion of probable construction cost.

 

BASIC SERVICES

 

                     Site master planning and conceptual design refinement

                     Evaluation of Phase III connection to Phases I and II at the Leonard WTP

                     Basis of design development

                     Hydraulic profile development

                     Electrical, Instrumentation and Controls development

                     Preliminary design development and report

                     CMAR procurement services

                     Texas Commission on Environmental Quality (TCEQ) coordination

 

SPECIAL SERVICES

 

                     Site surveying

                     Geotechnical investigation

                     Tracer Study Evaluation

                     Environmental Services

                     Chemical Optimization Study for corrosion control, manganese removal, total organic carbon removal and ammonia removal.

 

 

 

 

 

 

 

 

 

 

 

ENGINEERING SERVICES FEE

 

Description                     Amount

Basic Services                     $4,726,400

Special Services                     $638,500

Reallocate Funds from unused services                      ($800,000)

that are Available from Conceptual Design

(Administrative Memorandum No. 24-6047)                     

Requested Amount                     $4,564,900

 

FUNDING

 

Funding in the amount of $4,564,900 to Carollo Engineers Inc is to be made available from the Regional Water System Construction Funds.