Skip to main content
NTMWD Logo
File #: 25-6201    Version: 1
Type: Administrative Memorandum Status: Agenda Ready
File created: 10/7/2025 In control: Board of Directors
On agenda: 10/23/2025 Final action:
Title: Wilson Creek Regional Wastewater Treatment Plant Primary Clarifiers, UV and Centrifuge Improvements, Project No. 301-0606-22; Engineering Services Agreement, Outsourced Inspection Agreement, and Internal Inspection Services
Indexes: .RWWS - Wilson Creek WWTP, Engineering Services Agreement, Internal Inspection Services, Outsourced Inspection Services
Code sections: 301-0606-22 - Wilson Ck WWTP Clarifier, UV and Centrifuge Improvements
Attachments: 1. Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Regional Wastewater System

 

title

Wilson Creek Regional Wastewater Treatment Plant Primary Clarifiers, UV and Centrifuge Improvements, Project No. 301-0606-22; Engineering Services Agreement, Outsourced Inspection Agreement, and Internal Inspection Services

end

 

SUBJECT

 

recommendation

Authorize award of an engineering services agreement in the amount of $484,113 to Brown and Caldwell, Inc. for construction phase engineering services, an outsourced inspection contract to Mbroh Engineering, Inc., in the amount of $646,800, and authorize internal inspection services in the amount of $404,400.

end

 

PURPOSE

 

The Wilson Creek Master Plan outlined condition and reliability improvement projects, which are prioritized over the next five years and split into two construction projects. The higher priority project includes replacement of three UV light disinfection trains and additional centrifuge solids processing capacity.

 

RECOMMENDATION

 

The Executive Director and NTMWD staff recommend the Board of Directors authorize the award of a contract and services as follows:

 

Consultant:

Brown and Caldwell, Inc

 

 

Outsourced Inspection:

Mbroh Engineering, Inc.

 

 

Scope: 

Engineering Services During Construction, Outsourced and Internal Inspection Services

 

 

Project:

No. 301-0606-22; Wilson Creek Regional Wastewater Treatment Plant (RWWTP) Primary Clarifiers, UV and Centrifuge Improvements.

 

 

Amount:

Engineering Services During Construction $484,113 Outsourced Inspection Services: $646,800 Internal Inspection Services: $404,400

 

 

Committee:

This was an item on the September 24, 2025, Wastewater   Committee meeting agenda

 

DRIVER(S) FOR THIS PROJECT

 

Strategic Objective:

1.1 High Quality Services                                                                                               1.4 Reliable and Resilient Systems

 

 

Regulatory Compliance

Asset Condition

Capacity

Redundancy/Resiliency

Relocation or External Requests

Operational Efficiency

Safety

Administrative

Policy

Other _____________

 

 

BACKGROUND

 

PROJECT PURPOSE

                     The Wilson Creek Master Plan identified condition and reliability improvements, which are prioritized for construction over the next five years.  Items included are improvements to the Plant 1 primary clarifiers, the Plant 1 primary sludge pump station, an additional dewatering centrifuge, three Plant 1 aeration basin structural deficiencies, UV improvements and process air and blower development.

                     The preliminary design evaluated the recommended improvements and determined additional dewatering centrifuge and UV improvements as high-priority improvements to be constructed first.

                     The Wilson Creek RWWTP Primary Clarifier, UV, and Centrifuge Improvements project will be split into two projects, and the high-priority improvements will be completed first.

                     Engineering services during construction and inspection services to support the construction are currently being negotiated and will be recommended to the board for consideration in October 2025. 

 

PROJECT COMPONENTS

                     Disinfection facility and canopy improvements for UV 601, 602, and 603.

                     Addition of one new centrifuge feed pump, sludge grinder, polymer system, and mixing system for bulk polymer storage tanks.

                     Replacement of drains from the primary sludge pump station nos. 1 and 2 to the plant drain manholes.

                     Electrical and supervisory control and data acquisition (SCADA) improvements for scoped facilities.

 

ENGINEERING SERVICES AGREEMENT

 

Engineering services during construction for the Wilson Creek RWWTP Primary Clarifiers, UV and Centrifuge Improvements project are based on a 24-month construction duration in the amount of $484,113.  These services include:

                     Monthly project management and coordination

                     Review of shop drawing submittals, requests for information, proposed change orders and operation and maintenance manuals

                     Review of contractor’s monthly progress payment requests

                     Site visits and construction meetings

                     Startup assistance and substantial and final completion inspections

                     Development of record drawings and updated equipment lists

                     Updates to the plant operation and maintenance manual

 

OUTSOURCED INSPECTION SERVICES

 

                     Act as the on-site Owner’s Representative, performing daily construction observations, quality assurance (QA) inspections, and ensuring contractor adherence to plans and specifications.

                     Attend and facilitate project meetings, maintain communications with all stakeholders, and coordinate activities, including testing, connections, and facility interruptions.

                     Document and review project records, such as daily reports, requests for information (RFIs), change orders, submittals, and as-built drawings, ensuring accuracy and compliance.

                     Participate in substantial and final completion inspections, prepare and verify punch lists, and assist with equipment training, startup, and project closeout.

                     Review contractor schedules, pay estimates, and project changes, providing feedback and ensuring proper documentation and testing coordination.

                     The outsourced inspection services will focus on inspection of electrical and instrumentation components of the project.

 

The initial term of these services is 24 months at a cost of $646,800. At that point, the services and ongoing needs of the District will be reassessed for possible extension.

 

INTERNAL INSPECTION SERVICES

 

NTMWD will provide one civil inspector and one senior inspector to supervise external inspection services. The cost to NTMWD related to this internal inspection coverage is estimated at $404,400.

 

FUNDING

 

Funding in the amount of $484,113 to Brown and Caldwell, Inc. for engineering services during construction, $646,800 to Mbroh Engineering, Inc. for outsourced inspection services and funding in the amount of $404,400 for NTMWD internal inspection services will be provided utilizing the Regional Wastewater System Extendable Commercial Paper (ECP) Program as the appropriation source; issuance of ECP notes will occur as cash needs arise.