Skip to main content
NTMWD Logo
File #: 26-6236    Version: 1
Type: Administrative Memorandum Status: Agenda Ready
File created: 2/3/2026 In control: Board of Directors
On agenda: 2/26/2026 Final action:
Title: Leonard to Princeton Pipeline; Project No. 101-0686-26; Preliminary Engineering Services Agreement
Indexes: .RWS - Regional Water System, Preliminary Engineering - Engineering Services Agreement
Code sections: 101-0686-26 - Leonard to Princeton Pipeline
Attachments: 1. Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Regional Water System

 

title

Leonard to Princeton Pipeline; Project No. 101-0686-26; Preliminary Engineering Services Agreement

 

end

SUBJECT

 

recommendation

Authorize funding in the amount of $2,737,600 to AECOM Technical Services, Inc. for an engineering services agreement (ESA) for preliminary design of the Leonard to Princeton Pipeline project.

 

end

PURPOSE

 

Projected growth in the North System is expected to challenge the current capacity to deliver water efficiently and reliably from the Wylie Water Treatment Plant to the City of Princeton. The purpose of this project is to provide a reliable second source of treated water into the North System from the Leonard Water Treatment Plant to meet the projected demands.

 

RECOMMENDATION

 

The Executive Director and NTMWD staff recommend the Board of Directors authorize the Executive Director to execute an engineering services agreement (ESA) as follows:

 

Consultant:

AECOM Technical Services, Inc.

 

 

Scope: 

Preliminary Engineering Services Agreement

 

 

Project:

No. 101-0686-26, Leonard to Princeton Pipeline

 

 

Amount:

$2,737,600

 

 

Committee:

This will be an item on the February 25, 2026, Water Committee meeting agenda 

 

 

 

 

 

 

 

 

DRIVER(S) FOR THIS PROJECT

 

Strategic Objective:

1.1 High Quality Services                                                                                              1.4 Reliable and Resilient Systems

 

Regulatory Compliance

Asset Condition

Capacity

Redundancy/Resiliency

Relocation or External Requests

Operational Efficiency

Safety

Administrative

Policy

Other _____________

 

BACKGROUND

 

The current and forecasted growth within the North and East Systems increases the demand and necessitates additional capacity be supplied by the Leonard Water Treatment Plant (WTP) to supplement Wylie WTP in the near-term demands.

 

PROJECT PURPOSE

 

                     This project was identified in the 2021 Water Transmission System CIP Update as demand projections for the City of Princeton (City) are expected to double by 2030 and continue to steadily increase by 2050 to the Princeton Delivery Point No. 2A. To meet these forecast demands, an additional pipeline is needed beyond the existing 14-inch and 24-inch pipelines originating from the Wylie Water Treatment Plant currently serving the City.

                     Enhance resiliency and redundancy in the North system by secondary supply from the Leonard Water Treatment Plant.

                     The pipeline is planned to be completed and in service by 2031.

                     The planning level estimated construction cost from the 2021 report is approximately $28,480,000. The Engineer will review and provide an updated estimate during the preliminary engineering phase.

 

PROJECT COMPONENTS

 

                     Design approximately 28,000 linear feet of 48-inch diameter pipeline from a new connection on the existing Leonard Treated Water Pipeline (TWPL) No.1 to a tie-in location near the Princeton Delivery Point No. 2A.

                     Alignment study to develop viable routes and recommend a final alignment for the pipeline.

                     Preliminary engineering design of the pipeline, including material, sizing, and appurtenance design, tie-in location on the existing 84-inch pipeline, and future connection to the parallel Leonard TWPL No. 2.

                     Hydraulic analysis, including transient modeling and water age analysis

                     Recommendation for cathodic protection system

                     Recommendation for Supervisory Control and Data Acquisition (SCADA) updates.

                     Land Acquisition services and preparation of easement documents (Right-of-Entry (ROE), field notes, appraisals, offer letters, condemnation hearings) for the pipeline corridor.

 

BASIC SERVICES

 

                     Project Startup, Coordination, Meetings, and Project Administration

                     Alignment Study

                     Preliminary Design Report and 30% Plans with development of a preliminary Opinion of Probable Construction Costs (OPCC)

                     Electrical and Instrumentation and Controls (I&C)

 

SPECIAL SERVICES

 

                     Topographic and Boundary Survey Services

                     Environmental Evaluation Services

                     Cultural Resources / Archaeological Evaluation Services

                     Right-of-Way (ROW) and Easement Acquisition Support Services

 

CONSULTANT SELECTION PROCESS

 

                     A total of five engineering firms were interviewed for the Leonard Treated Water Pipeline Segments D and E and this project.  AECOM Technical Services, Inc., was deemed as the most highly qualified firm for this project.

 

 

ENGINEERING SERVICES FEE

 

Description                     Amount

Basic Services                     $913,100

Special Services                     $808,600

ROW Services                     $1,015,900

Requested Amount                     $2,737,600

 

FUNDING

 

Funding the AECOM Technical Services, Inc. for Preliminary Engineering services in the amount of $2,737,600 is to be made available from the Regional Water System Capital Improvement Fund.