Title: Leonard Water Treatment Plant High Service Pump Station - South; Project No. 101-0603A-22; Tabulation of Proposals And Award of Contract; and Additional Engineering Services
Indexes: .RWS - Regional Water System, Additional Engineering Services, Tabulation of Bids and Award of Contract, Tabulation of Proposals and Award of Agreement
Code sections: 101-0603A-22 - Leonard WTP High Service Pump Station - South
Attachments: 1. Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Regional Water System

 

title

Leonard Water Treatment Plant High Service Pump Station - South; Project No. 101-0603A-22; Tabulation of Proposals And Award of Contract; and Additional Engineering Services

 

end

SUBJECT

 

recommendation

Authorize award of a construction contract in the amount of $136,220,000 with Garney Companies, Inc. and Additional Engineering Services to Carollo Engineers, Inc., in the amount of $3,524,030 for the Leonard Water Treatment Plant High Service Pump Station - South

 

end

PURPOSE

 

Planned expansions of the Leonard Water Treatment Plant (WTP) will require an additional High Service Pump Station (HSPS) to add 175 million gallons per day (MGD), for a total of 350 MGD in treated water pumping capacity. The additional pumping capacity from the Bois d’Arc Lake system is consistent with NTMWD’s plans and efforts to continuously supply safe potable water to its growing service area.

 

RECOMMENDATION

 

The Executive Director and NTMWD staff recommend the Board of Directors authorize the award of a contract as follows:

 

 

Contractor:                

Garney Companies, Inc.

 

 

Consultant:

Carollo Engineers, Inc.

 

 

Scope: 

Construction Contract; and Additional Engineering Services during construction

 

 

Project:

No. 101-0603A-22, Leonard Water Treatment Plant High Service Pump Station - South

 

 

Amount:

Construction Contract Amount: $136,220,000                                                                                         Engineering Services:                $3,524,030

 

 

 

DRIVER(S) FOR THIS PROJECT

 

Strategic Objective:

1.2 Successfully Deliver Capital Program                                                                                                1.4 Reliable and Resilient Systems

 

Regulatory Compliance

Asset Condition

Capacity

Redundancy/Resiliency

Relocation or External Requests

Operational Efficiency

Safety

Administrative

Policy

Other _____________

 

BACKGROUND

 

PROJECT PURPOSE

 

                     Add treated water pumping capacity of 175 MGD to the Leonard WTP, consisting of a second HSPS, very similar in design and scope to the existing HSPS North.

                     Construction of a building to include pump level and electrical component levels that will create HSPS South.

                     Improvements to the existing HSPS North facility include the installation of one high-flow/high-head horizontal split-case pump (45 MGD) with motor and ancillary equipment, replacement of manual gate valve actuators with electric actuators, and modifications to the existing Heating Ventilation and Cooling (HVAC) ductwork.

                     The Engineer’s Opinion of Probable Construction Cost for Leonard WTP HSPS South is $174,694,126.

                     This project will bring the total high service pumping capacity for the Leonard WTP site to 350 MGD.

 

PROJECT COMPONENTS

 

                     HSPS building structure complete with mechanical, electrical, plumbing, drainage, and site work components.

                     Installation of four high-flow/high-head horizontal split-case pumps (45 MGD each) with associated motors, air-cooled adjustable frequency drives (AFDs) and ancillary equipment.

                     Installation of three high-flow/low-head (45 MGD each) horizontal split-case pumps with associated motors, air-cooled AFDs and ancillary equipment in the new HSPS South.

                     Two submersible dewatering pumps, and associated mechanical, electrical, instrumentation, and control (EI&C) equipment and components.

                     Removal and relocation of a 25 MGD horizontal split-case pump and motor, including ancillary equipment from the existing HSPS North to HSPS South.

                     Modifications to the existing HSPS North HVAC ductwork.

 

 

 

Summary of new equipment                                           HSPS-South                      HSPS-North

(under this contract)                                                               (HSPS-S)                                          (HSPS-N)

                                                                                                                                                                                                                                                            

High flow/High head 45 MGD pumps                     4                     1

High flow/ Low head 45 MGD pumps                     3                     

Low flow/ low head 25 MGD pumps                     1                     (1) (existing pump to be                                                                                                                                                                                                                         relocated to HSPS-S)                     

Spare pump place                     1                     

AFDs                     8                     1

 

Total pumps - to date                     7                     8 (7 existing + 1 new)

 

 

BEST VALUE PROPOSAL

 

NTMWD used the Competitive Sealed Proposal Method in accordance with Section 2269 of the Texas Administrative Code, “Contracting and Delivery Procedures for Construction Projects,” to procure a contractor for this project.  This method involves evaluating and scoring proposals based on key criteria, including project approach, experience with similar projects, key personnel, safety record, and price. Four proposals were received on Tuesday, February 10, 2026.

 

NTMWD staff evaluated the four responsive proposals in accordance with the published rating criteria. Additionally, NTMWD consultants Carollo Engineers, Inc. (Carollo), and Black and Veatch Corporation (Black and Veatch) checked company and individual team member references. NTMWD staff scored the Garney Companies, Inc. proposal as the best value for NTMWD.

 

 

TABULATION OF PROPOSALS

 

Proposals for construction of the Leonard WTP HSPS - South were received at 2:00 P.M. on Tuesday, February 10, 2026, as tabulated below:

 

Proposer                     Total Bid                     Recommendation

Garney Companies, Inc. (Garney)                     $136,220,000.00                     Best Value Proposer

Archer Western Construction, LLC                     $155,795,930.00                     

Zachry Construction Corporation                     $180,306,402.57                     

Thalle Construction Company, Inc.                     $187,500,000.00                     

ENGINEER’S OPINION OF                      $174,694,126.00

PROBABLE COST                                          

 

 

 

 

 

LOWEST RESPONSIBLE PROPOSER HISTORY

 

Garney Companies, Inc., either as a Construction Manager at-Risk (CMAR) or a General Contractor (GC), has successfully completed several similar projects for NTMWD. Garney has successfully completed the following projects for NTMWD:

 

                     Project No. 101-0268-11, Lake Texoma Outfall to Wylie WTP Raw Water Pipeline (CMAR and Work package Contractor - completed September 2015)

                     Project No. 101-0269-11, Trinity River Main Stem Pump Station and Raw Water Pipeline (CMAR - completed November 2021)

                     Project No. 101-0358-14, Bois d'Arc Lake Raw Water Pump Station (CMAR - completed November 2024)

                     Project No. 101-0384-15, Bois d'Arc Lake Leonard Water Treatment Plant (CMAR - completed November 2024)

                     Project No. 101-0428-16, Bois d'Arc Lake Leonard WTP High Service Pump Station (CMAR and Mechanical Work package contractor - completed November 2024)

                     Project No. 101-0261-11, High Service Pump Stations 2-2 and 2-3 Mechanical Improvements (GC - completed January 2017)

                     Project No. 101-0388-15, Chapman Pipeline Repair at Hunt County Road and South Sulphur River, Phases 1, 2 and 3 (GC - completed November 2020)

 

Based on their standing as the best value proposer, the information provided in the submitted proposals, reports from the references supplied, and their history with NTMWD, the NTMWD staff and Carollo Engineers, Inc. recommend award of the contract to Garney Companies, Inc.

 

ENGINEERING SERVICES AGREEMENT

 

Additional engineering services are needed during the construction phase for the Leonard WTP HSPS - South in the amount of $3,524,030. These services include the standard construction phase services the engineer of record performs, such as:

 

                     General project management

                     Review of submittals, schedules, pay applications, proposed change orders, and requests for information

                     Monthly progress and other meetings

                     Site visits and specific observations

                     Major equipment witness testing

                     Start-up, testing, and commissioning oversight

                     Record drawings, handover support, and other construction related services

 

 

 

 

 

Description                     Amount

Original ESA                     $8,480,000

Proposed Additional Services                     $3,524,030

Construction Phase Engineering Services for HSPS-S Project                     $3,524,030

Revised ESA Amount                     $12,004,030

 

INSPECTION SERVICES AGREEMENT

 

The engineering department normally provides inspections services for NTMWD projects.  Due to the current project workload, the NTMWD staff recommended that Black and Veatch Corporation (Black and Veatch) be retained to augment and supplement NTMWD construction management and inspection staff with full-service inspection services for the Leonard WTP HSPS - South.  A request for authorization of Black and Veatch’s construction management and inspection fee for services related to Bois d’Arc Lake Phase II projects was presented and approved during the March 28, 2024, Board meeting. A recommendation to augment these services will be presented in a separate Administrative Memorandum at this same Board meeting, March 26, 2026.

 

FUNDING

 

Funding in the amount of $136,220,000 to Garney Companies Inc. and additional funding in the amount of $3,524,030 to Carollo Engineers Inc is to be made available in the Regional Water System SWIFT Construction Funds contingent upon Texas Water Development Board approval of the contract and release of funding.