Skip to main content
NTMWD Logo
File #: 25-6099    Version: 1
Type: Administrative Memorandum Status: Agenda Ready
File created: 1/8/2025 In control: Board of Directors
On agenda: 1/23/2025 Final action:
Title: South Mesquite Creek Regional Wastewater Treatment Plant Peak Flow Management and Expansion, Project No. 301-0525-18; Amendment No. 7, Partial GMP No. 6, and Engineering Services During Construction
Sponsors: Wastewater Committee - Committee Action
Indexes: .RWWS - South Mesquite WWTP, Amendment to CMAR Agreement - Partial Guranteed Maximum Price, Amendment to Contract, Engineering Services During Construction
Code sections: 301-0525-18 - S Mesquite Ck WWTP Peak Flow Management
Attachments: 1. Attachment A - Major Scope of Work Description, 2. Attachment B - Total Contract Price Summary-Contract Amendment Summary, 3. Attachment C - Project Cost and Schedule, 4. Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Regional Wastewater System

 

title

South Mesquite Creek Regional Wastewater Treatment Plant Peak Flow Management and Expansion, Project No. 301-0525-18; Amendment No. 7, Partial GMP No. 6, and Engineering Services During Construction

end

 

SUBJECT

 

recommendation

Authorize funding to Archer Western Construction, LLC in the amount of $49,650,787 for Amendment No. 7 to the Construction Manager At-Risk (CMAR) Agreement and authorize funding to Carollo Engineers, Inc. in the amount of $1,308,300 for Engineering Services During Construction of the work related to Guaranteed Maximum Price (GMP) No. 6, for the South Mesquite Creek Regional Wastewater Treatment Plant (RWWTP) Peak Flow and Expansion project.

end

 

PURPOSE

 

The CMAR has submitted a partial GMP No. 6 for the continuation of the 42-inch parallel force mains, ultraviolet disinfection (UV), tertiary filter, and non-potable water pump station construction and the procurement of dewatering, UV, and filter equipment.  Future amendments will be presented and recommended to the Board as remaining work packages are developed, procured, and evaluated.

 

RECOMMENDATION

 

The Executive Director and NTMWD staff recommend the Board of Directors authorize the Executive Director to execute Amendment No. 7 to the Construction Manager At-Risk and an Engineering Services Agreement as follows:

 

CMAR:

Archer Western Construction, LLC (Archer Western)

 

 

Consultant:

Carollo Engineers, Inc. (Carollo)

 

 

Scope: 

Construction, Partial GMP No. 6                                                                                        Engineering Services During Construction for GMP No. 6

 

 

Project:

No. 301-0525-18, South Mesquite Creek Regional Wastewater Treatment Plant Peak Flow Management and Expansion

 

 

Amount:

$49,650,787 for Construction,                                                                                        $1,308,300 for Engineering Services During Construction

 

 

Committee:

This will be an item on the January 22, 2025, Wastewater Committee meeting agenda.

 

 

DRIVER(S) FOR THIS PROJECT

 

Strategic Objective:

1.1 High Quality Services                                                                                              1.4 Reliable and Resilient Systems

 

 

Regulatory Compliance

Asset Condition

Capacity

Redundancy/Resiliency

Relocation or External Requests

Operational Efficiency

Safety

Administrative

Policy

Other _____________

 

 

BACKGROUND

 

PROJECT PURPOSE

                     Flow monitoring studies show the South Mesquite Creek RWWTP to have influent flows higher than its rated wet weather capacity of 82.5 MGD (million gallons per day).  The South Mesquite Creek RWWTP Peak Flow Management preliminary design report recommended that onsite storage facilities need to be provided to store peak flows in excess of the wet weather capacity with a phased approach that will provide early peak flow relief for the facility.

                     The Capacity Assessment Study of the southern service area shows the South Mesquite Creek RWWTP needs to expand from 33 MGD to 41 MGD average daily flow by 2028 to meet the growth projections through 2033.

                     Provide condition assessment and criticality assessment to determine which items need to be repaired or replaced in the expansion project and which should be included in the master plan.

                     A 2023 Feasibility Analysis for Conveyance Alternatives Report recommended a new Buffalo Creek Lift Station No. 2 and Buffalo Creek Parallel Force Main to convey flows from the Buffalo Creek Interceptor System to the new headworks at the South Mesquite Creek RWWTP.   

                     Divert Buffalo Creek Parallel Force Main and Buffalo Creek Force Main flows to a new Headworks at South Mesquite Creek RWWTP to improve peak flow management and increase wastewater conveyance capacity in the Buffalo Creek Interceptor System to accommodate growth in Forney, Heath, and Rockwall.

 

 

 

 

 

 

PROJECT COMPONENTS

                     Early peak flow relief includes upgrades to existing influent pump station no. 1, force main, and re-purposing an existing basin for peak flow storage basin no. 3.

                     Peak flow management includes new parallel 42-inch force mains, new headworks facility no. 2, new peak flow storage basin no. 1, and supporting facilities. 

                     Expansion of the RWWTP to 41 MGD includes a primary clarifier, aeration basins, blower building, secondary sludge pump station, tertiary filters, disinfection, effluent metering, plant water pump station, solids handling, and supporting facilities.

                     Approximately 10,400 feet of 42-inch force main paralleling the existing 36-inch force main from Buffalo Creek Lift Station No. 2 (BCLS2) to the South Mesquite Creek RWWTP.

 

PARTIAL GUARANTEED MAXIMUM PRICE (GMP) NO. 6

                     Bid Package 8 - 42-inch parallel force mains downstream section

                     Bid Package 9 - UV, tertiary filter, NPW pump station construction

                     Bid Package 10 - dewatering, UV, and filter equipment procurement

                     Allowances for 90% to 100% design progression changes, bid exclusions, miscellaneous concrete repair and crack injection, distributions structure filter complex no. 2 modifications, additional pavement and road replacement at headworks no. 1, reprogramming of existing equipment, procurement and installation of valves and or fittings in dewatering facility, and equipment, appurtenances and materials for early incorporation of the peak wet weather flow storage basin no. 1

 

The total 90% CMAR estimate for the solicitation set included herein totaled $52.99 million.

 

Attachment A details the costs of the bid work package, general conditions, CMAR contingency, and CMAR fee to determine the Partial GMP No. 6 associated with Amendment No. 7.

 

ENGINEERING SERVICES AGREEMENT (ESA)

 

The ESA with Carollo Engineers, Inc. is for engineering services during construction for work related to GMP No.6 for the South Mesquite RWWTP Peak Flow Management and Expansion.

 

The services will consist of:

                     Monthly project management and coordination

                     Pre-construction and bi-weekly construction progress meetings

                     Review of shop drawing submittals, requests for information, proposed change orders, payment requests, and operation and maintenance (O&M) manuals

                     Site visits and structural engineer inspections

                     Agency coordination, such as with City of Mesquite and the Texas Commission on Environmental Quality (TCEQ)

                     Development of demolition closure plans, record drawings and update existing plant operations and maintenance (O&M) Manual

                     Factory Witness Testing of the programmable logic control (PLC) hardware and software

                     Start-up and commissioning support

 

The total contract price summary and the contract amendment summary are included as Attachment B, and project cost and schedule are included as Attachment C.

 

FUNDING

 

Funding to Archer Western Construction, LLC in the amount of $49,650,787 and to Carollo Engineers, Inc. in the amount of $1,308,300 is to be made available utilizing the Regional Wastewater System Extendable Commercial Paper (ECP) Program as the appropriation source; issuance of ECP notes will occur as cash needs arise.