Skip to main content
NTMWD Logo
File #: 25-6219    Version: 1
Type: Administrative Memorandum Status: Agenda Ready
File created: 12/2/2025 In control: Board of Directors
On agenda: 12/18/2025 Final action:
Title: Buffalo Creek Lift Station No. 2; Project No. 507-0639-24; Tabulation of Bids, Award of Contract, and Inspection Services
Indexes: .Inter Sys - Buffalo Creek Interceptor, Tabulation of Bids - Award of Contract and Inspection Services
Code sections: 507-0639-24 - Buffalo Ck Lift Station No 2
Attachments: 1. Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Buffalo Creek Interceptor System

 

title

Buffalo Creek Lift Station No. 2; Project No. 507-0639-24; Tabulation of Bids, Award of Contract, and Inspection Services

end

 

SUBJECT

 

recommendation

Authorize award of a construction contract to Urban Infraconstruction, LLC in the amount of $32,219,360 and authorize internal inspection services in the amount of $805,560 for Buffalo Creek Lift Station No. 2 project.

end

 

PURPOSE

 

The purpose of this project is to increase wastewater conveyance capacity in the Buffalo Creek Interceptor System to accommodate growth in Forney, Heath, and Rockwall.

 

RECOMMENDATION

 

The Executive Director, NTMWD staff and Carollo Engineers, Inc recommend the Board of Directors authorize the award of a contract as follows:

 

Contractor:

Urban Infraconstruction, LLC

 

 

Scope: 

Construction Contract and Internal Inspection Services

 

 

Project:

No. 507-0639-24, Buffalo Creek Lift Station No. 2

 

 

Amount:

Construction Contract:           $32,219,360                                                                                              Internal Inspection Services:  $     805,560

 

 

Committee:

This will be an item on the December 17, 2025, Wastewater Committee meeting agenda

 

 

 

 

 

 

 

DRIVER(S) FOR THIS PROJECT

 

Strategic Objective:

1.2 Successfully Deliver Capital Program                                                                                              1.4 Reliable and Resilient Systems

 

 

Regulatory Compliance

Asset Condition

Capacity

Redundancy/Resiliency

Relocation or External Requests

Operational Efficiency

Safety

Administrative

Policy

Other _____________

 

 

BACKGROUND

 

PROJECT PURPOSE

                     The 2021 Buffalo Creek Interceptor System Capacity Assessment & Assurance report identified the need for additional capacity in the Buffalo Creek System to meet projected demand growth in the cities of Forney, Heath and Rockwall.

                     A 2023 Feasibility Analysis for Conveyance Alternatives Report recommends a new Buffalo Creek Lift Station No. 2 to convey flows from the Buffalo Creek Interceptor System to the new headworks at the South Mesquite Creek Regional Wastewater Treatment Plant (RWWTP). To meet projected growth demands, the new lift station would need to be in service by the end of 2027.

                     In February 2024 (Administrative Memorandum No. 24-5993), the Board authorized the preliminary and final engineering services for the design of a new 32 million gallon per day (MGD) Buffalo Creek Lift Station No. 2 to convey projected flows to the South Mesquite Creek RWWTP.  Electrical equipment on the market currently has long lead times. Both  the specified generator and switchboard have an estimated delivery lead time of nearly 2 years.

                     In July 2025 (Administrative Memorandum No. 25-6159), the Board authorized the early electrical equipment procurement package in advance of this main construction package of the lift station. The purpose was to procure the electrical equipment months prior to the main construction package award to support the project's substantial completion by November 2027.

 

 

PROJECT COMPONENTS

                     New generator and switchboard

                     New 32 MGD capacity lift station on the existing Buffalo Creek Lift Station site

 

 

 

 

 

 

 

TABULATION OF BIDS

 

Sealed bids for construction were received at 2:00 p.m. on Thursday, November 13th, 2025, as tabulated below:

 

Bidder                     Total Bid                     Recommendation

Urban Infraconstruction, LLC                                          $32,219,360                     Lowest responsible bid

                                                               Recommended for Award

Archer Western Construction, LLC                     $34,857,718                     

BAR Constructors, Inc.                     $38,560,438                     

Crescent Constructors, Inc.                     $49,584,959                     

Thalle Construction Co., Inc.                     $60,772,500

ENGINEER’S OPINION OF                     $41,772,742

PROBABLE COST                     

 

 

LOWEST RESPONSIBLE BIDDER HISTORY

 

Urban Infraconstruction, LLC has successfully completed projects for the NTMWD:

                     Project No. 501-0658-25, Lower Rowlett Creek Lift Station Structural Repairs (completed September 2025)

 

Urban Infraconstruction, LLC is currently in progress on the following projects for the NTMWD:

                     Project No. 501-0616-22, Beck Branch, Prairie Creek and Renner Road Lift Stations Improvements

                     Project No. 301-0606-22, Wilson Creek Regional Wastewater Treatment Plant Primary Clarifiers, UV and Centrifuge Improvements

 

Urban Infraconstruction, LLC has been a subcontractor to general contractors working on the following past NTMWD projects:

 

                     Project No. 301-0328-13, Rowlett Creek Regional Wastewater Treatment Plant Peak Flow Management Improvements, Phase I, subcontractor to Pepper Lawson Waterworks, LLC (completed June 2023)

                     Project No. 101-0375-14, Wylie Water Treatment Plant I Rapid Mix and Sedimentation Improvements, subcontractor to Eagle Contracting, L.P. (completed March 2021)

                     Project No. 310-0450-17, Muddy Creek Wastewater Treatment Plant Aeration Basin, Odor Control, and Backup Improvements, subcontractor to Eagle Contracting, L.P. (completed January 2021)

 

 

 

 

 

Urban Infraconstruction, LLC has also done construction for other utility companies located within the state of Texas:

 

                     City of Bells Wastewater Treatment Plant

                     City of Kemp Water Treatment System Improvements

                     City of Midland Water Pollution Control Plant, Secondary Treatment Upgrades

 

Based on their standing as the lowest responsible bidder, the information provided, and reports by the supplied references, the NTMWD staff and Carollo Engineers, Inc. recommend award of the contract to Urban Infraconstruction, LLC.

 

INTERNAL INSPECTION SERVICES

 

NTMWD will utilize its own inspection staff to cover all inspection tasks.  The cost to the NTMWD related to this internal inspection coverage is approximately $805,560.

 

FUNDING

 

Funding in the amount of $32,219,360 to Urban Infraconstruction LLC is to be made available in the Buffalo Creek Interceptor System Clean Water State Revolving Fund Program contingent upon Texas Water Development Board approval of the contract and release of funding.

 

Funding in the amount of $805,560 for NTMWD Internal Inspection Services is to be made available from the Buffalo Creek Interceptor System Construction Funds.