File #: 25-6100    Version: 1
Type: Administrative Memorandum Status: Agenda Ready
File created: 1/8/2025 In control: Board of Directors
On agenda: 1/23/2025 Final action:
Title: 121 Force Main Improvements; Project No. 501-0491-18; Tabulation of Bids and Award of Contract, Internal Inspection Services, and Engineering Services Agreement
Sponsors: Wastewater Committee - Committee Action
Indexes: .UEFIS - Upper East Fork Interceptor System, Engineering Services Agreement, Tabulation of Bids - Award of Contract and Internal Inspection Services
Code sections: 501-0491-18 - 121 Force Main Improvements, Phase 1
Attachments: 1. Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Upper East Fork Interceptor System

 

title

121 Force Main Improvements; Project No. 501-0491-18; Tabulation of Bids and Award of Contract, Internal Inspection Services, and Engineering Services Agreement

end

 

SUBJECT

 

recommendation

Award a construction contract to Belt Construction of Texas, LLC in the amount of $10,794,721, authorize internal inspection services in the amount of $472,860, and authorize an engineering service agreement with Kimley-Horn and Associates in the amount of $326,000 for construction phase services for the 121 Force Main Improvements project.

end

 

PURPOSE

 

Authorize construction contract for replacement of a segment of the existing 121 Force Main that has reliability issues and ongoing hydraulic constraints.

 

RECOMMENDATION

 

The Executive Director and NTMWD staff recommend the Board of Directors authorize the award of contract as follows:

 

Contractor:

Belt Construction of Texas, LLC

 

 

Consultant:

Kimley-Horn and Associates, Inc.

 

 

Scope: 

Construction Contract, Engineering Services During Construction, and Internal Inspection Services

 

 

Project:

No. 501-0491-18, 121 Force Main Improvements

 

 

Amount:

Construction Contract:  $10,794,721                                                                                              Inspection Services (Internal):  $472,860                                                                                        Engineering Services during Construction:  $326,000

 

 

Committee:

This will be an item on the January 22, 2025, Wastewater Committee meeting agenda

 

 

 

 

DRIVER(S) FOR THIS PROJECT

 

Strategic Objective:

1.2 Successfully Deliver Capital Program                                                                                              1.4 Reliable and Resilient System

 

 

Regulatory Compliance

Asset Condition

Capacity

Redundancy/Resiliency

Relocation or External Requests

Operational Efficiency

Safety

Administrative

Policy

Other _____________

 

 

BACKGROUND

 

PROJECT PURPOSE

 

                     Replace a segment of the existing 121 Force Main and increase conveyance capacity in the 121 Force Main from the Preston Road Lift Station to a point on the existing 121 Force Main located approximately 1,500 linear feet west of Coit Road.

 

PROJECT COMPONENTS

 

                     Construction of approximately 12,500 linear feet of 36-inch force main and associated appurtenances.

                     Grouting and abandonment of approximately 9,600 linear feet of 30-inch force main and removal of approximately 3,200 linear feet of 30-inch force main.

 

TABULATION OF BIDS

 

Sealed bids for construction of the 121 Force Main Improvements were received at 2:00 p.m. on Thursday, December 12, 2024, as tabulated below:

 

Bidder

Total Bid

Recommendation

Belt Construction of Texas, LLC

$10,794,721.00

Lowest responsible bid Recommended for Award

Mountain Cascade of Texas, LLC

$11,220,041.00

 

Wilson Contractor Services, LLC

$11,753,379.95

 

BRCT, LLC dBA Black Rock Construction

$16,229,844.75

 

Western Municipal Construction of Texas, LLC

$17,766,857.00

 

Thalle Construction Co., Inc.

$18,006,881.00

 

Canary Construction, Inc.

$18,901,045.00

 

ENGINEER’S OPINION OF PROBABLE CONSTRUCTION COST (OPCC)

$18,160,000.00

 

 

The  cost difference between the low bid and the OPCC was primarily due to the more aggressive production rate for the pipe and tunnel installation, a manhole for the plug valves that was removed late in design, and a 15% contingency carried in the final OPCC.

 

LOWEST RESPONSIBLE BIDDER HISTORY

 

Belt Construction of Texas, LLC has successfully completed several or is currently in construction on several projects for NTMWD and other utilities:

 

                     NTMWD Project No. 101-607B-22, Waterline Relocations along State Highways in Dallas, Rockwall and Kaufman Counties (currently in construction)

                     NTMWD Project No. 301-508A-18, Wilson Creek Regional Wastewater Treatment Plant (RWWTP Plant Drain Improvements (completed October 2023)

                     NTMWD Project No. 501-0439-16, Beck Branch Parallel Interceptor (completed May 2021)

                     NTMWD Project No. 401-0438-16, 121 Regional Disposal Facility (121 RDF) Gravity Sewer, Leachate Pump Station and Force Main (completed March 2018)

                     NTMWD Project No. 101-0262-11, Replacement Section of the North Plano Pipeline (completed May 2015)

                     City of Pflugerville, Secondary Colorado River Raw Water Line Package 4

                     City of Frisco, Pather Creek Interceptor Improvements

                     City of Fort Worth, Lake Arlington 42-Inch Force Main Part 1 and Part 2

                     City of Midland, Northeast Sewer Line

                     Texarkana Water Utilities, Nix Creek Sewer Improvements

                     City of Crossett, East Crossett Sewer Improvements

                     City of Hutchins, Southern Force Main

                     City of Frisco, Upper Reuse 24-Inch Pipeline Phase 2

                     Northwest Arkansas Conservation Authority, Little Osage Creek Sewer Improvements, Bentonville, AR

 

Based on their standing as the lowest responsible bidder, the information provided, and reports by the supplied references, the NTMWD staff and Kimley-Horn and Associates, Inc. recommend the award of the contract to Belt Construction of Texas, LLC.

 

ENGINEERING SERVICES AGREEMENT

 

Engineering services during construction for the 121 Force Main Improvements project are based on a planned 20-month construction duration in the amount of $326,000.

 

                     Monthly project management and coordination

                     Review of shop drawing submittals, request for information, proposed change orders, and operation and maintenance (O&M) manuals

                     Review contractor’s monthly progress payment requests

                     Site visits and construction meetings

                     Startup assistance and substantial and final completion inspection

                     Development of record drawings and updated equipment list

 

INTERNAL INSPECTION SERVICES

 

NTMWD will utilize its own inspection staff to cover all inspection tasks.  The cost to the NTMWD related to this internal inspection coverage is approximately $472,860.

 

FUNDING

 

Funding to Belt Construction of Texas, LLC in the amount of $10,794,721, Kimley-Horn and Associates, Inc in the amount of $326,000 and NTMWD internal inspection services in the amount of $472,860 is to be made available utilizing the Upper East Fork Interceptor System Extendable Commercial Paper (ECP) Program as the appropriation source; issuance of ECP notes will occur as cash needs arise.