Legislation Details

File #: 26-6285    Version: 1
Type: Administrative Memorandum Status: Agenda Ready
File created: 8/12/2026 In control: Board of Directors
On agenda: 8/27/2026 Final action:
Title: McKinney Delivery Point No. 3 to McKinney Delivery Point No. 4 Pipeline; Project No. 101-0505-18; Change Order No. 7
Indexes: .RWS - Regional Water System, Change Order
Code sections: 101-0505-18 - McKinney DP #3 to McKinney DP #4 Pipeline
Attachments: 1. Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Regional Water System

 

 

title

McKinney Delivery Point No. 3 to McKinney Delivery Point No. 4 Pipeline; Project No. 101-0505-18; Change Order No. 7

 

end

SUBJECT

 

recommendation

Authorization to process a construction project change order with Oscar Renda Contracting, Inc. and provide additional funding in the amount of $2,438,820.

 

end

PURPOSE

 

This Change Order No. 7 authorizes the contractor to increase the depth of excavation and tunnel installation across Bloomdale Lake and modify adjacent lengths of piping tying into the tunnel portion. The change order also captures a sewer relocation scope deletion and credit. Additional contractual time is to be added.

 

RECOMMENDATION

 

The Executive Director, NTMWD staff, and HDR Engineering, Inc. recommend the Board of Directors authorize a construction change order as follows:

 

 

Contractor:

Oscar Renda Contracting, Inc.

 

 

Scope: 

Construction Contract Change Order No. 7

 

 

Project:

No. 101-0505-18, McKinney Delivery Point No. 3 to McKinney Delivery Point No.4 Pipeline

 

 

Amount:

$2,438,820

 

 

Committee:

This will be an item on the August 26, 2026, Water Committee meeting agenda

 

 

 

 

 

 

 

DRIVER(S) FOR THIS PROJECT

 

Strategic Objective:

1.4 Reliable and Resilient System Capacity

 

Regulatory Compliance

Asset Condition

Capacity

Redundancy/Resiliency

Relocation or External Requests

Operational Efficiency

Safety

Administrative

Policy

Other _____________

 

BACKGROUND

 

PROJECT PURPOSE

                     In order to adequately meet future demand, improve system pressures, and improve the transfer of treated water from the Leonard Water Treatment Plant (WTP) into the western area of NTMWD’s transmission system, the addition of a 72-inch water transmission pipeline from the McKinney Delivery Point No. 4 to the McKinney’s Delivery Point No. 3 is required.

                     The new pipeline will provide a major loop in the north transmission system and enhance the movement and reliability of water to the remote parts of the western system currently experiencing increased demands due to growth.

 

PROJECT COMPONENTS

                     Construction of 40,000 linear feet (LF) of 72-inch diameter water transmission steel pipeline, including all fittings, valves, and appurtenances.

                     Installation of approximately 6,800 LF of 72-inch diameter tunnel pipe by trenchless methods under roadways and waterways.

 

PROPOSED CHANGE ORDER

                     To address deeper than expected underground rock strata and provide adequate safe cover over the contractor’s tunneling activities, the tunnel under Bloomdale Lake will be approximately 12-feet deeper. To increase constructability of the portions of pipeline within the tunneled section, modification to the open-cut portion of pipeline is also required. 

                     Current substantial completion date shall be extended 60 days, and final completion date shall be extended 90 days.

                     Due to the extension of the piping tunnel, relocation of an existing sewer line is no longer needed and subsequent credit is due.

 

 

 

 

 

 

CHANGE ORDER NO. 7

 

Description                     Amount                     Days

Original Contract Amount                     $102,886,839                     880

Prior Change Order(s) Total                            $499,062                     90

Proposed Change Order No. 7                                          

PCO 17 - Bloomdale Lake piping modifications                         $2,505,986                     60

PCO 18 - City of McKinney sewer relocation                            ($67,166)                     0

Proposed Change Order No. 7 Increase                         $2,438,820                     90

Revised Contract Amounts                     $105,818,735                     1,060

 

 

FUNDING

 

Funding in the amount of $2,438,820 for Change Order No. 7 to Oscar Renda Contracting, Inc., is available from the Regional Water System Construction Funds.