Skip to main content
NTMWD Logo
File #: 25C-32    Version: 1
Type: Consent Agenda Item Status: Agenda Ready
File created: 6/9/2025 In control: Board of Directors
On agenda: 6/26/2025 Final action:
Title: Wylie Water Treatment Plant (WTP) II East System Interconnection; Project No. 101-0652-24; Tabulation of Bids and Award of Contract for Valve Procurement
Sponsors: Water Committee - Champion Update
Indexes: .RWS - Regional Water System, Bid Tab and Award
Code sections: 101-0652-24 - Wylie WTP II East System Interconnection
Attachments: 1. Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Regional Water System

 

title

Wylie Water Treatment Plant (WTP) II East System Interconnection; Project No. 101-0652-24; Tabulation of Bids and Award of Contract for Valve Procurement

 

end

SUBJECT

 

recommendation

Award valve procurement contract to Municipal Valve and Equipment Company, Inc. for the Wylie WTP II East System Interconnection project in the amount of $432,907.

 

end

PURPOSE

 

Due to the long lead times associated with manufacturing valves, this action enables the District to procure these items prior to awarding the construction contract. Having timely possession of the valves helps mitigate future construction delays.

 

 

RECOMMENDATION

 

The Executive Director, NTMWD staff and Kennedy Jenks recommend the Board of Directors authorize the award of a contract as follows:

 

Supplier:

Municipal Valve and Equipment Company, Inc.

 

 

Scope: 

Procurement of two 36-inch butterfly valves and one sleeve valve with 30-inch flanges

 

 

Project:

No. 101-0652-24, Wylie WTP II East System Interconnection

 

 

Amount:

$432,907

 

 

Committee:

This will be a Champion Update at the June 25, 2025, Water Committee meeting

 

 

 

 

 

 

 

DRIVER(S) FOR THIS PROJECT

 

Strategic Objective:

1.4   Reliable and Resilient Systems

 

 

Regulatory Compliance

Asset Condition

Capacity

Redundancy/Resiliency

Relocation or External Requests

Operational Efficiency

Safety

Administrative

Policy

Other _____________

 

BACKGROUND

 

PROJECT PURPOSE

                     The objective for the project is to provide additional capacity from Wylie WTP II to the East System by June 2026. This will be accomplished by constructing an interconnect pipeline between the High Service Pump Station (HSPS) 2-2/2-3 discharge and the 36-inch Wylie Rockwall Farmersville pipeline.

                     To accomplish this task, tie-ins during the shutdown season need to be completed. Therefore, the isolation butterfly valves need to be procured to ensure they are available for installation by the contractor during the shutdown season.

                     Similarly, a control sleeve valve required for the project has an estimated lead time of 40 weeks. Early procurement of the valve is also needed to ensure the project completion in June 2026.

 

PROJECT COMPONENTS

                     Procure two 36-inch butterfly valves and one sleeve valve with 30-inch flanges.

                     Valve procurement includes the engineer’s review of submittals and placing an order to proceed with fabrication.

                     Payment for the valves will be due upon shipment and will be assigned by contract in the project construction award.

 

TABULATION OF BIDS

 

Sealed bids for valve procurement were received at 2:00 p.m. on Wednesday, May 21, 2025, as tabulated below:

 

Bidder                     Total Bid                                          Recommendation

Municipal Valve and Equipment                                           $432,907                                          Lowest responsible bid

Company, Inc.                                                                                                                                                   Recommended for Award

                                          

ENGINEER’S OPINION OF

PROBABLE COST (OPCC)                     $351,975                     

 

All indications are that the received bid price is fair and reasonable in the current construction marketplace.

 

LOWEST RESPONSIBLE BIDDER HISTORY

 

Municipal Valve and Equipment Company, Inc. started in 1991 and is a leading manufacturers’ representative firm that sells and services water and wastewater treatment equipment, valves, and actuators. They have a history working with NTMWD, with the meter vault standardization projects as recent examples. Being located in Dallas, Texas, they also have a history of supplying equipment, including butterfly and sleeve valves, to the City of Dallas at facilities such as the Eastside WTP, Bachman HSPS, and Walcrest Pump Station. NTMWD’s water conveyance system professional engineer, who previously worked for the City of Dallas, reported a positive experience after having worked with them for over 15 years.

 

Based on their standing as the lowest responsible bidder, the information provided, and reports by the supplied references, the NTMWD staff and Kennedy Jenks recommend award of the contract to Municipal Valve and Equipment Company, Inc. This procurement contract will be assigned to a construction contractor selected through the bidding process in July 2025.

 

FUNDING

 

Funding in the amount of $432,907 to Municipal Valve and Equipment Company Inc. is to be made available utilizing the Regional Water System Extendable Commercial Paper (ECP) Program as the appropriation source; issuance of ECP notes will occur as cash needs arise.