Skip to main content
NTMWD Logo
File #: 25-6199    Version: 1
Type: Administrative Memorandum Status: Agenda Ready
File created: 10/9/2025 In control: Board of Directors
On agenda: 10/23/2025 Final action:
Title: Wylie Water Treatment Plant Raw Water Pump Station No. 4; Project No. 101-0647-24; Additional Engineering Services Agreement
Indexes: .RWS - Regional Water System, Additional Engineering Services, Engineering Services Agreement, Engineering Services Agreement - Additional Services, Engineering Services Agreement - Preliminary Engineering Design
Code sections: 101-0647-24 - Wylie WTP Raw Water Pump Station No. 4
Attachments: 1. Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Regional Water System

 

title

Wylie Water Treatment Plant Raw Water Pump Station No. 4; Project No. 101-0647-24; Additional Engineering Services Agreement

end

 

SUBJECT

 

recommendation

Authorize funding in the amount of $4,873,800 to Arcadis U.S., Inc. for additional engineering services for preliminary design of the Wylie Water Treatment Plant (WTP) Raw Water Pump Station No. 4.

 

end

PURPOSE

 

The purpose of this project is the preliminary design of a new 350 million gallons per day (MGD) raw water pump station on a site along the Lavon Lake shoreline, as recommended in the feasibility study report. The pump station shall access supply water down to an elevation of 451 feet (ft) mean sea level (MSL), which is below the dead pool elevation of 453 ft MSL, ensuring full access to the conservation storage at Lavon Lake.

 

RECOMMENDATION

 

The Executive Director and NTMWD staff recommend the Board of Directors authorize the Executive Director to execute an engineering services agreement (ESA) as follows:

 

Consultant:

Arcadis U.S., Inc.

 

 

Scope: 

Additional Engineering Services - Preliminary Engineering Design

 

 

Project:

No. 101-0647-24; Wylie Water Treatment Plant Raw Water Pump Station No. 4

 

 

Amount:

$4,873,800

 

 

Committee:

This will be an item on the October 22, 2025, Water Committee meeting agenda

 

 

 

 

 

 

DRIVER(S) FOR THIS PROJECT

 

Strategic Objective:

1.2: Successfully Deliver Capital Program,                                                                                              1.4: Reliable and Resilient Systems

 

Regulatory Compliance

Asset Condition

Capacity

Redundancy/Resiliency

Relocation or External Requests

Operational Efficiency

Safety

Administrative

Policy

Other _____________

 

BACKGROUND

 

PROJECT PURPOSE

 

Lavon Lake is the original source of water supply  for the Wylie Water Treatment Plant (WTP) complex. Currently, three raw water pump stations draw from the Lavon Lake and serve the Wylie WTP complex. The current pump stations do not optimize NTMWD’s full water rights in Lavon Lake. Previous studies, the NTMWD Water Supply Resiliency Plan Phase II in 2021 and the Long Range Water Supply Plan in 2023, had reviewed the potential for a fourth Raw Water Pump Station (RWPS) at Lake Lavon. As a result, a feasibility study and conceptual design was initiated in early 2024 under Administrative Memorandum No. 24-6014.

 

Based on recommendations from the study, a new raw water pump station with a rated firm capacity of 350 MGD and retaining existing Raw Water Pump Station No. 2 would provide the operational flexibility and meet the goal of long-term reliability and drought resiliency. Raw Water Pump Station No. 1 will be decommissioned as part of a separate project upon completion of RWPS No. 4.

 

PROJECT COMPONENTS

                     Provide preliminary design of a 350 MGD intake and pump station with the ability to intake at a depth of 451 ft MSL elevation from Lavon Lake below the dead pool elevation of 453 ft MSL.

                     Provide preliminary design of 17,000 linear feet of 96-inch and 60-inch transmission mains to convey flow north and south mixing area in the Wylie WTP complex.

                     Connection to existing transmission mains for operational flexibility.

                     The Engineer’s current opinion of probable construction cost (OPCC) is $453,000,000.

 

BASIC SERVICES

                     Project management

                     Pump station preliminary design

                     Transmission main preliminary design

                     Preliminary (30%) design drawings and OPCC

                     Permitting and regulatory support and coordination related to:

o                     Section 404 and 408 pre-application meeting with the United States Army Corp of Engineers (USACE)

o                     Swift funding application

 

SPECIAL SERVICES

                     Geotechnical (preliminary and final)

                     Marine geophysical

                     Land surveying

                     Geophysical

                     Subsurface utility engineering (SUE)

                     Assistance with procurement of Construction Manager at Risk (CMAR)

 

CONSULTANT SELECTION PROCESS

                     Arcadis US, Inc. is the current consultant engineer for the project. After evaluation and justification, NTMWD’s team recommends continuing to work with Arcadis, US Inc., as they are the most highly qualified firm for this project.

 

ENGINEERING SERVICES FEE

 

Description                     Amount

Basic Services                     $3,604,600

Reallocate unused services from Feasibility

and conceptual study as authorized by

Administrative Memorandum No. 24-6014                     ($1,300,000)

Revised Basic Services                      $2,304,600

Special Services                     $2,569,200

Requested Amount (Basic and Special Services)                     $4,873,800

 

Arcadis U.S., Inc. has provided a total fee in the amount of $6,173,800 for these services. NTMWD staff recommend reallocating $1,300,000 of unused fee under Feasibility and Conceptual Study as authorized by Administrative Memorandum No. 24-6014 towards basic services to reduce the total fee to $4,873,800.

 

FUNDING

 

Funding in the amount of $4,873,800 to Arcadis U.S. Inc is to be made available from the Regional Water System Construction Funds.