File #: 25-6200    Version: 1
Type: Administrative Memorandum Status: Agenda Ready
File created: 10/9/2025 In control: Board of Directors
On agenda: 10/23/2025 Final action:
Title: Buffalo Creek Parallel Interceptor Phase II; Project No. 507-0636-24; Engineering Services Agreement - Final Engineering
Indexes: .Inter Sys - Buffalo Creek Interceptor, Engineering Services Agreement - Final Engineering
Code sections: 507-0636-24 - Buffalo Ck Parallel Interceptor Phase II
Attachments: 1. Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Buffalo Creek Interceptor System

 

title

Buffalo Creek Parallel Interceptor Phase II; Project No. 507-0636-24; Engineering Services Agreement - Final Engineering

end

 

 

SUBJECT

 

recommendation

Authorize funding in the amount of $2,157,011 to HDR Engineering, Inc. for an engineering services agreement for the final design of the Buffalo Creek Parallel Interceptor Phase II project.

end

 

 

PURPOSE

 

This project will allow for  increased wastewater conveyance capacity in the Buffalo Creek Interceptor System by constructing the second phase of a parallel interceptor system along Buffalo Creek from Farm-to-Market Road (F.M.) 740 to the Buffalo Creek Lift Station to accommodate growth in the cities of Forney, Heath, and Rockwall.

 

 

RECOMMENDATION

 

The Executive Director and NTMWD staff recommend the Board of Directors authorize the Executive Director to execute an engineering services agreement (ESA) as follows:

 

Consultant:

HDR Engineering, Inc.

 

 

Scope:

Final Engineering Design

 

 

Project:

No. 507-0636-24, Buffalo Creek Parallel Interceptor Phase II

 

 

Amount:

$2,157,011

 

 

Committee:

This was an item on the September 24, 2025, Wastewater Committee meeting agenda

 

 

 

 

DRIVER(S) FOR THIS PROJECT

 

Strategic Objective:

1.2: Successfully Deliver Capital Program                                                                                             1.4: Reliable and Resilient Systems

 

Regulatory Compliance

Asset Condition

Capacity

Redundancy/Resiliency

Relocation or External Requests

Operational Efficiency

Safety

Administrative

Policy

Other _____________

 

BACKGROUND

 

The 2021 Buffalo Creek Interceptor System Capacity Assessment and Assurance report recommends a new parallel interceptor to meet flow projections due to population growth in the cities of Forney, Heath, and Rockwall. Phase I (NTMWD Project No. 507-0484-17) extended from the Buffalo Creek Wastewater Treatment Plant to just north of F.M. 740, and the pipeline was placed in service in 2023.

 

PROJECT PURPOSE

                     Final design of a parallel interceptor from north of F.M. 740 to Buffalo Creek Lift Station to increase conveyance capacity, reduce existing surcharges, and provide redundancy and resiliency within the wastewater system as recommended by the capacity assurance report.

                     Completion of this project is needed to decommission the Buffalo Creek Wastewater Treatment Plant.

                     The planning level estimated construction cost for the project is $68,380,000.

 

PROJECT COMPONENTS

                     Approximately 32,000 linear feet of 60-inch parallel interceptor, including tunneling, traffic control, and odor control.

                     One permanent billing flow meter parallel to the existing Heath 740 Meter Station.

                     Manhole rehabilitation of approximately 83 manholes on the existing Buffalo Creek Interceptor.

                     Access improvements across existing drainages to facilitate maintenance along the interceptor system.

 

BASIC SERVICES

                     Final Design Services

                     Bid Phase Services

 

SPECIAL SERVICES

                     Geotechnical Engineering

                     Survey

                     Cultural & Archaeological Services

                     Permitting

 

ENGINEERING SERVICES FEE

 

Description                     Amount

Basic Services                     $1,825,160

Special Services                     $331,851

Requested Amount                     $2,157,011

 

 

 

FUNDING

 

Funding to HDR Engineering Inc. in the amount of $2,157,011 is to be made available from the Buffalo Creek Interceptor System Construction Funds.