Title: Wylie Water Treatment Plant (WTP) Complex Valve Improvements; Project No. 101-0672-25; Tabulation of Proposals and Award of Contract, Authorize Additional Engineering Services, and Authorize Internal Inspection Services
Indexes: .RWS - Regional Water System, Authorize Inspection Services, Engineering Services Agreement, Tabulation of Bids and Award of Contract
Code sections: 101-0672-25 - Wylie WTP Complex Valve Improvements
Attachments: 1. Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Regional Water System

 

 

title

Wylie Water Treatment Plant (WTP) Complex Valve Improvements; Project No.  101-0672-25; Tabulation of Proposals and Award of Contract, Authorize Additional Engineering Services, and Authorize Internal Inspection Services

 

end

SUBJECT

 

recommendation

Authorize award of a Construction Contract to Felix Construction Company in the amount of $12,194,000 and authorize additional services to Pape-Dawson Consulting Engineers, LLC (PD) in the amount of $537,000 for Engineering Services During Construction (ESDC) and authorize internal inspection services in the amount of $245,250 for the Wylie WTP Complex Valve Improvements project.

 

end

PURPOSE

 

The Contractor will remove, replace, or install the six (6) identified critical valves on the North Garland 60-inch pipeline and the North Garland Pipeline No. 2 Phase I 72-inch pipeline.  These valves improve the isolation capability, operational flexibility, and resilience of the two pipelines.

 

RECOMMENDATION

 

The Executive Director and NTMWD staff recommend the Board of Directors authorize the award of a contract as follows:

 

Contractor:

Felix Construction Company (Felix)

 

 

Consultant:

Pape-Dawson Consulting Engineers, LLC (PD)

 

 

Scope: 

Construction Contract, Engineering Services During Construction, and Internal Inspection Services

 

 

Project:

No. 101-0672-25, Wylie WTP Complex Valve Improvements

 

 

Amount:

Construction Contract: $12,194,000 (Felix)                                                                                            Engineering Services During Construction: $537,000 (PD)                                                                                               Internal Inspection Services $245,250 (NTMWD)

 

 

Committee:

This will be an item on the October 21, 2026, Water Committee meeting agenda

 

 

DRIVER(S) FOR THIS PROJECT

 

Strategic Objective:

1.3 Proactive Asset and Maintenance Management                                                                                               1.4 Reliable and Resilient Systems

 

☐ Regulatory Compliance

☒ Asset Condition

☐ Capacity

☒ Redundancy/Resiliency

☐ Relocation or External Requests

☒ Operational Efficiency

☐ Safety

☐ Administrative

☐ Policy

☐ Other _____________

 

BACKGROUND

 

The Wylie Water Treatment Plant Complex has many valves of varying age and condition.  Leaking valves and insufficient isolation capabilities limit the ability to shut down basins or processes while maintaining service.  Valve failures have the potential to greatly impact plant operations and treatment capacity.  NTMWD staff have identified valves that need to be immediately repaired or replaced in support of upcoming projects. These valves will improve the isolation capability of High Service Pump Station (HSPS) 2-2 & 2-3 and the immediate segments of the North Garland 60-inch pipeline and the North Garland Pipeline No. 2 Phase I 72-inch pipeline.  This project will also allow maintenance of service to the North Garland System with HSPS 2-2 & 2-3 out of service, which will improve the ability to maintain the pump stations.

 

On May 28, 2026, the Board of Directors authorized funding in the amount of $556,042 to VAG, USA, LLC for a contract to procure the large-diameter valves for this project.  (Administrative Memorandum No. 26-6267) This contract will be assigned to Felix Construction Company.

 

PROJECT PURPOSE

•                     Enable the isolation of HSPS 2-1, 2-2, & 2-3, the North Garland 60-inch and North Garland 72-inch pipelines to facilitate future maintenance and construction projects.

•                     The Valve Condition Assessment and Asset Management Plan are critical to maintaining the reliability and resiliency of the Wylie Water Treatment Plant Complex.

 

PROJECT COMPONENTS

•                     Perform the removal of valve ISO-011 and closure of pipe segments.

•                     Disable valve ISO-112 and install a new valve further downstream to enable future access for maintenance.

•                     Replace valves ISO-002 and ISO-003.

 

 

 

 

•                     Install a new 60-inch valve on the North Garland 60-inch pipeline downstream of the interconnect.

•                     Install a new 72-inch valve on the North Garland Pipeline No. 2 Phase I 72-inch pipeline downstream of the interconnect. 

•                     Install necessary Blow-Off valves and Combined Air/Vacuum valves

 

TABULATION OF PROPOSALS

 

Seven (7) Competitive Sealed Proposals for construction were received at 2:00 p.m. on Thursday, September 24, 2026. A team of evaluators from Engineering, Maintenance and Operations reviewed the Qualifications and scored them according to procurement process criteria. Results deemed Felix Construction as the Best Value proposer.

 

Proposer​

Total Bid​

Recommendation​

Evans & Associates Utility Services, Inc.​

$12,150,788​

​

Felix Construction Company​

$12,194,000​

Best Value Proposer​ Recommended for Award

Belt Construction of Texas, LLC​

$12,240,000​

​

Canary Construction, Inc.​

$14,100,000​

​

RP Constructors, LLC​

$16,112,149​

​

CLW Water Group, LLC​

$16,435,958​

 ​

Crescent Constructors, Inc.​

$17,153,390​

 ​

 

 

 

ENGINEER'S OPINION OF PROBABLE COST

$12,719,000​

​

 

 

LOWEST RESPONSIBLE PROPOSER HISTORY

 

Felix Construction Company has successfully completed or is currently in construction on the following projects for NTMWD and other entities:

•                     Project No. 101-0572-20 North Garland Ground Storage Tank (currently in construction)

•                     Project No. 101-0338-13 Meter Vault Standardization, Set Point Control Phase III, Work Package C (completed May 2025)

•                     Northgate Pump Station Ground Storage Tank No. 2 (City of Irving) (completed February 2023)

•                     Project No. 101-0338D-13 Meter Vault Standardization, Set Point Control Phase IV, Work Package D2, Richardson No. 2 Delivery Point via an Inter-Local Agreement with the City of Richardson and through their Construction Manager At-Risk efforts on a wider City project (currently in construction)

•                     Project No. 101-0422-16 Wylie Water Treatment Plant (WTP) IV Filter Complex Wall Repairs - Felix Construction Company was the Construction Manager At-Risk (completed June 2024)

 

 

 

Based on the evaluation of their proposal and the information provided in the submitted proposals, reports from supplied references, and their project history with NTMWD, the NTMWD staff and Pape-Dawson Consulting Engineers, LLC recommend award of the contract to Felix Construction Company.

 

ENGINEERING SERVICES AGREEMENT

 

Engineering services are required during the construction phase (ESDC’s) of the Wylie WTP Complex Valve Improvements in the amount of $537,000. These services include:

 

•                     Project management and administration

•                     Meetings and site visits

•                     Review and respond to requests for information (RFI’s), submittals, operation and maintenance (O&M) manuals, test reports, proposed change orders, and payment applications.

•                     Perform substantial completion walk-through

•                     Perform final completion walk-through

•                     Review As-Builts from the Contractor and create record drawings.

 

ENGINEERING SERVICES FEE

 

Description                     Amount

Phase 1 - Identified Valves Package                     

Basic Services                     $725,109

Special Services                     $150,700

Original Contract Amount                     $875,809

Amendment No. 1 - Valve Vault Design and

ISO-112 Additional Services                     $53,415

Amendment No. 2 - Phase 2 - Valve Reliability

Centered Maintenance Program                     $1,304,410

Amendment No. 3 - Engineering Services During

Construction (Current Request)                     

Additional Services                     $537,000

Total Current Request                     $537,000

New Total Contract Amount                     $2,770,634

 

INTERNAL INSPECTION SERVICES

 

NTMWD will utilize its own inspection staff to cover all inspection tasks. The costs to the NTMWD related to this internal inspection coverage are estimated at $245,250.

 

 

 

FUNDING

 

Funding to Felix Construction Company in the amount of $12,194,000, $537,000 to Pape-Dawson Consulting Engineers, LLC, and $245,250 for NTMWD Internal Inspection services is to be made available from the Regional Water System Construction Funds.