Skip to main content
NTMWD Logo
File #: 24C-18    Version: 1
Type: Consent Agenda Item Status: Agenda Ready
File created: 4/10/2024 In control: Board of Directors
On agenda: 4/25/2024 Final action:
Title: Princeton Lift Station Expansion; Project No. 501-0617-22 Engineering Services Agreement
Sponsors: Wastewater Committee - Champion Update
Indexes: .UEFIS - Upper East Fork Interceptor System, Engineering Services Agreement
Code sections: 501-0617-22 - Princeton Lift Station Improvements
Attachments: 1. Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Upper East Fork Interceptor System

 

title

Princeton Lift Station Expansion; Project No. 501-0617-22

Engineering Services Agreement

end

 

SUBJECT

 

recommendation

Authorize funding for engineering services for final design of the Princeton Lift Station Expansion project.

end

 

PURPOSE

 

The purpose of this project is to increase wastewater conveyance capacity serving growth in Princeton and to replace the lift station’s roof due to condition.

 

RECOMMENDATION

 

The Executive Director and NTMWD staff recommend the Board of Directors authorize the Executive Director to execute an engineering services agreement (ESA) as follows:

 

Consultant:

AECOM Technical Services, Inc. (AECOM)

 

 

Scope:

Final Engineering Design

 

 

Project:

No. 501-0617-22, Princeton Lift Station Expansion

 

 

Amount:

$292,000

 

 

Strategic Objective:

1.2: Successfully Deliver Capital Program  1.4: Reliable and Resilient Systems

 

 

Committee:

This will be an item at the April 24, 2024, Wastewater Committee meeting agenda

 

 

 

 

 

 

DRIVER(S) FOR THIS PROJECT

 

Regulatory Compliance

Asset Condition

Capacity

Redundancy/Resiliency

Relocation or External Requests

Operational Efficiency

Safety

Administrative

Policy

Other _____________

 

BACKGROUND

 

PROJECT PURPOSE

                     Increase the capacity of the Princeton Lift Station No. 2 from 12 million gallons per day (MGD) to approximately 14.7 MGD by increasing the size of the existing pump impellers as recommended in the Princeton Conceptual Design Report, by AECOM dated February 2024.  

                     Replace the existing lift station roof as recommended by the Princeton Lift Station Condition Assessment Report, by HDR, Inc., dated August 2023.

                     The planning level estimated construction cost is $2,314,000.

 

PROJECT COMPONENTS 

                     Replace and upsize pump impellers

                     Replace badly deteriorated roof

 

BASIC SERVICES

                     Project management

                     Final design engineering services

                     Bid phase services

 

SPECIAL SERVICES

                     None

 

ENGINEERING SERVICES FEE

 

Description                                                                                                          Amount

Basic Services                                                                                     $292,000

Special Services                                                                                     $0.00

Requested Amount                                                                $292,000

 

 

 

FUNDING

 

Funding in the amount of $292,000 to AECOM Technical Services, Inc. is to be made available utilizing the Upper East Fork Interceptor System Extendable Commercial Paper (ECP) Program as the appropriation source; actual issuance of ECP notes will occur as cash needs arise.