File #: 24-6015    Version: 1
Type: Administrative Memorandum Status: Agenda Ready
File created: 4/10/2024 In control: Board of Directors
On agenda: 4/25/2024 Final action:
Title: Muddy Creek Wastewater Treatment Plant Expansion to 12.5 MGD and Operations Building Improvements; Project Nos. 310-0592-21 and 310-0535-19; Tabulation of Bids and Award of Contract, Engineering Services Agreement, and Internal Inspection Services
Sponsors: Wastewater Committee - Committee Action
Indexes: .Small Systems-310-Muddy Crk WWTP, .WWTP - Muddy Creek WWTP, Engineering Services Agreement, Internal Inspection Services, Tabulation of Bids and Award of Contract
Code sections: 310-0535-19 - Muddy Ck WWTP Operations Building Improvements, 310-0592-21 - Muddy Ck WWTP Peak Flow Storage & Expansion
Attachments: 1. Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

title

Muddy Creek Wastewater Treatment Plant Expansion to 12.5 MGD and Operations Building Improvements; Project Nos. 310-0592-21 and 310-0535-19; 

Tabulation of Bids and Award of Contract, Engineering Services Agreement, and Internal Inspection Services

 

end

SUBJECT

 

recommendation

Authorize award of a construction contract, engineering services agreement, and internal inspection services for the Wastewater Treatment Plant (WWTP) Expansion to 12.5 million gallons per day (MGD) and Operations Building Improvements projects.

end

 

PURPOSE

 

Address constraints in the existing facilities to improve the reliability of the existing WWTP and expand the WWTP capacity to meet the growth projections consistent with the 2021 Master Plan and 2022 Preliminary Engineering Report, which will reduce the risk of permit exceedances from peak wet weather events and expand the treatment capacity to meet the needs of the customers in the Cities of Wylie and Murphy.

 

RECOMMENDATION

 

The Executive Director and  NTMWD staff recommend the Board of Directors authorize the award of a contract as follows:

 

Contractor:

Eagle Contracting, LLC

 

 

Consultant:

Garver, LLC

 

 

Scope: 

Construction Contract, Engineering Services during Construction, and Internal Inspection Services

 

 

Project:

No. 310-0592-21 and 310-0535-21, Muddy Creek Wastewater Treatment Plant (WWTP) Expansion to 12.5 MGD and Operations Building Improvements

 

 

Amount:

$72,918,084 for construction contract  $2,883,566 for engineering services agreement  $2,164,980 for internal inspection services

 

 

Strategic Objective:

1.4 Reliable and Resilient Systems

 

 

Committee:

This will be an item on the April 24, 2024, Wastewater Committee meeting agenda

 

DRIVER(S) FOR THIS PROJECT

 

Regulatory Compliance (pre-emptive)

Asset Condition

Capacity

Redundancy/Resiliency

Relocation or External Requests

Operational Efficiency

Safety

Administrative

Policy

Other _____________

 

BACKGROUND

 

PROJECT PURPOSE

                     Address hydraulic constraints within the existing treatment plant to improve its reliability.

                     Expand the plant capacity to 12.5 million gallons per day (MGD) to meet the growth projections in the 2021 Master Plan and 2022 Preliminary Engineering Report

                     Supervisory Control and Data Acquisition (SCADA) improvements identified as high priority in the 2021 Wastewater SCADA Master Plan.

                     The construction of Project No. 310-0535-19, Muddy Creek WWTP Operations Building Improvements (designed by Huitt-Zollars, Inc.) is combined with Project No. 310-0592-21 for efficiencies and to avoid multiple contractors on the site.

 

PROJECT COMPONENTS

                     Flow meter vaults for the 54-inch and 48-inch influent flow gravity lines 

                     Modifications to the existing Influent Pump Station (IPS) and 42-inch parallel force main 

                     Modifications to existing primary clarifier splitter box

                     Primary clarifier and primary sludge pump station

                     Two aeration basins, splitter structure and additional blowers within the existing blower building

                     Secondary clarifier and splitter structure. Modifications to existing secondary clarifiers and additional sludge pumping

                     Replacement of existing belt filter press with screw presses and associated equipment  

                     Tertiary filtration facility with cloth media filters 

                     Retrofitting existing ultraviolet (UV) disinfection channels with new UV equipment

                     Civil and yard piping improvements 

                     Electrical, instrumentation and controls

                     New 1,700 square foot operations building addition

                     Renovate 600 square feet of the existing operations building

 

 

 

 

 

TABULATION OF BIDS

 

Sealed bids for construction of Muddy Creek Wastewater Treatment Plant Expansion to 12.5 MGD and Operations Building Improvements were received at 3:00 p.m. on Wednesday, March 13, 2024, as tabulated below:

 

 

LOWEST RESPONSIBLE BIDDER HISTORY

 

Bidder                                                                                                         Total Bid                                          Recommendation

 

Eagle Contracting                                                                                    $72,918,084                                          Lowest responsible bid

                                                                                                                                                                                             Recommended for Award

 

Archer Western Construction, LLC                     $82,995,000                     

 

Thalle Construction Company, Inc.                      $89,950,000                     

 

ENGINEER’S OPINION OF

PROBABLE COST                                                                                    $81,676,000

 

 

Eagle Contracting, LLC has successfully completed or is currently in construction on several similar projects for NTMWD:

                     Project No. MCRCF 03-1, Muddy Creek Wastewater Treatment Plant, (completed September 2006)

                     Project No. MCRCF 05-1(062), Muddy Creek Wastewater Treatment Plant Expansion No. 1 (completed February 2008)

                     Project No. 116, Panther Creek Wastewater Treatment Plant Expansion (completed March 2011)

                     Project No. 101-0375-14, Wylie Water Treatment Plant I Rapid Mix and Sedimentation Improvements (completed March 2021)

                     Project No. 310-0450-17, Muddy Creek Wastewater Treatment Plant Aeration Basin, Odor Control, and Backup Power Improvements (completed January 2021)

                     Project No. 301-0432-16, Floyd Branch Regional Wastewater Treatment Plant Process Optimization Improvements (completed February 2023)

                     Project No. 308-0576-20, Sabine Creek Wastewater Treatment Plant Expansion to 7 MGD (currently under construction)

 

Based on their standing as lowest responsible bidder, the information provided, and reports by the supplied references, the NTMWD staff and Garver, LLC recommend award of the contract to Eagle Contracting, LLC.

 

 

 

 

 

ENGINEERING SERVICES AGREEMENT (ESA)

 

This ESA with Garver, LLC is for construction services needed for the Muddy Creek WWTP Expansion to 12.5 MGD.

 

The services will consist of:

                     Monthly project management and coordination

                     Review of shop drawing submittals, requests for information, proposed change orders, and operation and maintenance (O&M) manuals

                     Site visits by structural and geotechnical engineer

                     Development of record drawings and update existing plant O&M manual

                     Survey for metes and bounds Oncor easement

 

NTMWD will utilize Garver, LLC for engineering construction services for the 44-month period. The cost to NTMWD related to the Engineering Construction Services is $2,883,566.00.

 

INTERNAL INSPECTION SERVICES

 

NTMWD will use internal inspection staff to cover all inspection disciplines.  The costs to the NTMWD related to this internal inspection coverage is approximately $2,164,980.00.

 

TOTAL PROJECT COSTS 

 

Project Name                                           Engineering                                          Construction                     Inspection

                                                                                         Cost                                                       Cost                                               Cost

 

Muddy Creek WWTP                     $2,883,566                                           $71,271,874                                           $2,035,080

Expansion to 12.5 MGD

Project No. 310-0592-21

 

Muddy Creek WWTP                      $0.00                                                                $1,646,210                                           $129,900                                           

Operations Building

Improvements

Project No. 310-0535-19

 

Total                                                                                     $2,883,566                                          $72,918,084                                          $2,164,980

 

 

FUNDING

 

Funding to Eagle Contracting LLC in the amount of $72,918,084, $2,883,566 to Garver LLC, and $2,164,980 for NTMWD Internal Inspection is to be made available from the issuance of the Muddy Creek Wastewater System 2024 Bonds planned for April 25, 2024.