File #: 24-6010    Version: 1
Type: Administrative Memorandum Status: Agenda Ready
File created: 4/11/2024 In control: Board of Directors
On agenda: 4/25/2024 Final action:
Title: McKinney Delivery Point No. 3 to McKinney Delivery Point No. 4 Pipeline; Project No. 101-0505-18, Tabulation Of Bids And Award of Contract, and Inspection Services
Sponsors: Water Committee - Committee Action
Indexes: .RWS, .RWS - McKinney DP #3 to McKinney DP #4 Pipeline, Tabulation of Bids - Award of Contract and Inspection Services
Code sections: 101-0505-18 - McKinney DP #3 to McKinney DP #4 Pipeline
Attachments: 1. Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Regional Water System

 

title

McKinney Delivery Point No. 3 to McKinney Delivery Point No. 4 Pipeline;

Project No. 101-0505-18, Tabulation Of Bids And Award of Contract, and Inspection Services

end

 

SUBJECT

 

recommendation

Authorize award of a construction contract and internal inspection services.

end

 

PURPOSE

 

The project is for the construction of a new water pipeline that will provide additional capacity to the Frisco-McKinney area of the NTMWD water transmission system.

 

RECOMMENDATION

 

The Executive Director, NTMWD staff and HDR, Inc. recommend the Board of Directors authorize the award of a contract as follows:

 

Contractor:

Oscar Renda Contracting, Inc.

 

 

Scope:

Construction Contract and Internal Inspection Services

 

 

Project:

No. 101-0505-18 McKinney Delivery Point No. 3 to McKinney Delivery Point No. 4 Pipeline

 

 

Amount:

$102,886,839 for construction contract; and $180,000 for NTMWD Inspection Services

 

 

Strategic Objective:

Objective 1.4 - Reliable and Resilient System Capacity

 

 

Committee:

This will be an item on the April 24, 2024, Water Committee meeting agenda

 

 

 

 

 

 

 

DRIVER(S) FOR THIS PROJECT

 

Regulatory Compliance

Asset Condition

Capacity

Redundancy/Resiliency

Relocation or External Requests

Operational Efficiency

Safety

Administrative

Policy

Other _____________

 

BACKGROUND

 

                     The transfer of treated water from the Leonard Water Treatment Plant (WTP) into the existing NTMWD north transmission system will require the addition of a 72-inch water transmission pipeline from the site of the McKinney Delivery Point No. 4 to the site of McKinney’s Delivery Point No. 3.

                     The new pipeline will serve to close a major loop in the north transmission system and enhance the movement and reliability of water to the remote parts of the system currently experiencing increased demands due to growth.

                     In June 2018, the Board approved Administrative Memorandum No. 5189 authorizing Preliminary Engineering design. Subsequent administrative memoranda were approved in February 2019 (No. 5351) and August 2019 (No. 5458) for expedited routing design and real estate acquisition.

                     In June 2021, the Board approved Administrative Memorandum No. 5734 authorizing Final Engineering Design services to advance the pipeline design to 60% level.

                     In November 2021 the Board approved Consent Agenda Item No. 21-11-02 authorizing additional services for Adjustment No. 2 on the pipeline project for the cultural resources services, as required by the Texas Historic Commission.

                     In September 2022 the Board approved Administrative Memorandum No. 5861 authorizing additional services to advance the pipeline Final Engineering Design from 60% level through construction.

                     In February 2024 the Board approved Administrative Memorandum No. 24-5990 authorizing the construction management and supplemental inspection services for the pipeline project. 

 

 

PROJECT COMPONENTS 

                     Construction of 40,000 linear feet (LF) of 72-inch diameter water transmission steel pipeline including all fittings, valves, and appurtenances.

                     Installation of approximately 6,800 LF of 96-inch diameter steel casing pipe or tunnel liner plate and 72-inch diameter tunnel pipe by trenchless methods under roadways and waterways.   

 

 

 

 

 

 

 

 

 

TABULATION OF BIDS 

Sealed bids for construction of McKinney Delivery Point No. 3 to McKinney Delivery Point No. 4 Pipeline were received at 2:00 p.m. on Wednesday, March 20, 2024, as tabulated below:

 

Bidder                                                                                                          Total Bid                                           Recommendation

 

Harper Brothers Construction, LLC                      $111,281,569

Mountain Cascade of Texas, LLC                      $105,907,184

Oscar Renda Contracting, Inc.                                           $102,886,839                     Lowest responsible bid

                                                                                                                                                                                             Recommended for Award

ENGINEER’S OPINION OF

PROBABLE COST                                                                                     $97,080,000

 

 

LOWEST RESPONSIBLE BIDDER HISTORY

 

Oscar Renda Contracting, Inc. has successfully completed several similar projects for the NTMWD:

 

                     NTMWD Project No. 101-0424-16, Bois d’Arc Lake Raw Water Pipeline Section C, 10 miles of 90-inch steel water line 

                     NTMWD Project No. 101-0425-16, Bois d’Arc Treated Water Pipeline - East Fork Trinity River Tunnel - Segment E; 2,532 linear feet of 118-inch tunnel

                     Tarrant Regional Water District (TRWD)- Integrated Pipeline (IPL) Section 19 TxDOT Tunnel Project, 1 mile 84-inch waterline and 2,175 linear feet of tunnel

                     TRWD IPL Section 17 Trinity River Tunnel Crossing; 11,800 linear feet of 108-inch tunnel. 

                     TRWD IPL Section 10/11; 12.7 miles of 84-inch waterline

                     City of Dallas Water Utilities, Elm Fork 72-inch Water Main; 1.6 miles of 72-inch steel water main

                     Oklahoma City Water Utilities, Atoka Raw Water Pipeline; 13 miles of 72-inch steel water main and 1,027 linear feet of tunnel

                     Garrison Diversion Conservancy District, North Dakota, Red River Valley Water Supply Segment 5c; 8 miles of 72-inch waterline

 

Based on their standing as lowest responsible bidder, the information provided, and reports by the supplied references, the NTMWD staff and HDR, Inc. recommend award of the contract to Oscar Renda Contracting, Inc.

 

 

 

 

 

 

 

INTERNAL INSPECTION SERVICES

 

NTMWD will utilize Construction Inspection Supervisory staff to provide oversight of inspection services in conjunction with the Construction Manager. Construction Management services to AECOM Technical Services were approved in the February 2024 Board meeting. The costs to the NTMWD related to this internal inspection coverage is approximately $180,000.00.

 

 

FUNDING

 

Funding in the amount of $102,886,839 to Oscar Renda Contracting, Inc and funding for NTMWD Internal Inspection Services in the amount of $180,000 is to be made available utilizing the Regional Water System Extendable Commercial Paper (ECP) Program as the appropriation source; actual issuance of ECP notes will occur as cash needs arise.