Skip to main content
NTMWD Logo
File #: 24-6004    Version: 1
Type: Administrative Memorandum Status: Agenda Ready
File created: 3/12/2024 In control: Board of Directors
On agenda: 3/28/2024 Final action:
Title: North McKinney Parallel Interceptor Mitigation Projects; Project No. 501-0504-18; Tabulation of Bids and Award of Contract, and Inspection Services
Sponsors: Wastewater Committee - Committee Discussion
Indexes: .UEFIS - Upper East Fork Interceptor System, Tabulation of Bids - Award of Contract and Inspection Services
Code sections: 501-0504-18 - N McKinney Parallel Interceptor
Attachments: 1. Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Upper East Fork Interceptor System

 

title

North McKinney Parallel Interceptor Mitigation Projects;

Project No. 501-0504-18; 

Tabulation of Bids and Award of Contract, and Inspection Services

 

end

SUBJECT

 

recommendation

Authorize award of a construction contract and internal inspection services

end

 

PURPOSE

 

Complete mitigation as required by the United States Army Corps of Engineers easement agreement for the North McKinney Parallel Interceptor.

 

RECOMMENDATION

 

The Executive Director, NTMWD staff and Teague Nall and Perkins, Inc. recommend the Board of Directors authorize the award of a contract as follows:

 

Consultant:

HGS, LLC dba RES Environmental Operating Company, LLC

 

 

Scope: 

Construction Contract and Internal Inspection Services

 

 

Project:

No. 501-0504-18 North McKinney Parallel Interceptor Mitigation Projects

 

 

Amount:

$886,922.73 for construction contract and $110,400 for NTMWD inspection services

 

 

Strategic Objective:

Objective 1.2 Successfully Deliver Capital Program

 

 

Committee:

This item was discussed at the February 21, 2024, Wastewater Committee meeting. 

 

 

 

 

 

DRIVER(S) FOR THIS PROJECT

 

Regulatory Compliance

Asset Condition

Capacity

Redundancy/Resiliency

Relocation or External Requests

Operational Efficiency

Safety

Administrative

Policy

Other _____________

BACKGROUND

 

PROJECT PURPOSE 

                     The United States Army Corps of Engineers (USACE) granted NTMWD a nationwide permit and mandated mitigation for an easement and construction of NTMWD Project No. 501-0504-18, the North McKinney Parallel Interceptor and a fiber optic line. The first part of the required mitigation was performed with the pipeline construction contract. This project will complete and satisfy the balance of USACE mitigation requirements. 

                     The mitigation value to satisfy is approximately $948,500. The cost of mitigation is to be based on actual contractor bid and construction costs. Approximately $110,300 was expended under Project No. 501-0504-18 for new fencing. The balance of obligation remaining is approximately $838,200.  

 

PROJECT COMPONENTS 

                     Plant native trees within the temporary construction easement and ensure 85% survivability (estimated to be a minimum 379 1-inch trees) after 3 years.  

                     Clear and remove a portion of USACE Lavon Lake property of invasive/undesirable Chinese Privet, Chin Berry, and Eastern Red Cedar trees and re-seed with a mix of native prairie grasses and water to create a perennial seed bank on USACE Lavon Lake property.

                     The Engineer’s OPCC of $689,331 was based on an amount of acreage to be cleared of invasive/undesirable tree species that would be closest to the remaining obligation value with alternative bid items specified to fulfil the remaining obligation.

 

TABULATION OF BIDS

 

Sealed bids for construction were received at 2:00 p.m. on Thursday, February 15th, 2024, as tabulated below. Only 1 responsible bidder submitted a bid.

 

Bidder                                                                                                          Total Base Bid                      Recommendation

HGS, LLC dba RES Environmental                      $1,765,813.49                     Lowest responsible bid

Operating Company, LLC                                                                                                                               Recommended for Award

 

ENGINEER’S OPINION OF                                           $689,331

PROBABLE COST FOR BASE BID

 

 

 

 

 

The original base bid price received was greater than the amount that NTMWD is required to compensate for the total mitigation cost. From the prioritization criteria set by the USACE, NTMWD staff negotiated with the bidder and reached an agreement to reduce the quantity and scope of work to align with the remaining obligation. 

 

NTMWD staff, Teague Nall and Perkins, Inc., and HGS, LLC dba RES Environmental Operating Company, LLC, negotiated a reduced quantity and scope of work for the revised amount of $886,922.73.

 

LOWEST RESPONSIBLE BIDDER HISTORY

 

RES Environmental Operating Company, LLC, is currently working on a similar project for the NTMWD:

                     101-0366-14 Bois d’Arc Lake Mitigation Property

 

RES Environmental Operating Company, LLC, has successfully completed several similar projects outside of NTMWD:

                     Lake Ralph Hall clearing for Upper Trinity Regional Water District

                     Native Prairie Restoration for the University of Houston Coastal Center

 

 

Based on their standing as lowest responsible bidder, the information provided, and reports by the supplied references, the NTMWD staff and Teague Nall and Perkins, Inc. recommend award of the contract to HGS, LLC dba RES Environmental Operating Company, LLC.

 

INTERNAL INSPECTION SERVICES

 

NTMWD will use internal inspection staff to cover all inspection disciplines. The costs to the NTMWD related to this internal inspection coverage are approximately $110,400.

 

FUNDING

 

Funding in the amount of $886,922.73 to HGS, LLC dba RES Environmental Operating Company, LLC, and $110,400 for NTMWD Internal Inspection Services is to be made available utilizing the Upper East Fork Interceptor System Extendable Commercial Paper (ECP) Program as the appropriation source; actual issuance of ECP notes will occur as cash needs arise.