File #: 25-6216    Version: 1
Type: Administrative Memorandum Status: Agenda Ready
File created: 12/5/2025 In control: Board of Directors
On agenda: 12/18/2025 Final action:
Title: Floyd Branch Regional Wastewater Treatment Plant (RWWTP) Peak Flow and Ultraviolet (UV) Improvements, Project No. 301-0610-22; Tabulation of Bids, Award of Contract, Engineering Services Agreement, and Authorize Inspection Services
Indexes: .RWWS - Floyd Branch WWTP, Engineering Services Agreement, Tabulation of Bids - Award of Contract and Authorize Inspection Services
Code sections: 301-0610-22 - Floyd Branch WWTP Flow & UV Improvements
Attachments: 1. Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Regional Wastewater System

 

title

Floyd Branch Regional Wastewater Treatment Plant (RWWTP) Peak Flow and Ultraviolet (UV) Improvements, Project No. 301-0610-22; Tabulation of Bids, Award of Contract, Engineering Services Agreement, and Authorize Inspection Services

end

 

SUBJECT

 

recommendation

Authorize award of a construction contract in the amount of $36,981,000 to Felix Construction Company, authorize an engineering services agreement with CDM Smith, Inc., in the amount of $761,868 for construction phase engineering services and authorize internal inspection services in the amount of $720,540.

end

 

PURPOSE

 

The purpose of this project is to address wet weather flows and limitations of the existing facilities to ensure meeting the discharge permit during a peak flow event.

 

RECOMMENDATION

 

The Executive Director and NTMWD staff recommend the Board of Directors authorize the award of a contract and services as follows:

 

Contractor:

Felix Construction Company

 

 

Consultant:

CDM Smith, Inc.

 

 

Scope: 

Construction Contract, Engineering Services During Construction, and Internal Inspection Services

 

 

Project:

No. 301-0610-22; Floyd Branch RWWTP Peak Flow and UV Improvements

 

 

Amount:

Construction Contract: $36,981,000                                                                                                Engineering Services During Construction: $761,868                                                                                               Internal Inspection Services: $720,540

 

 

Committee:

This will be an item on the December 17, 2025, Wastewater Committee meeting agenda 

 

 

DRIVER(S) FOR THIS PROJECT

 

Strategic Objective:

1.1 High Quality Services                                                                                              1.4 Reliable and Resilient Systems

 

 

Regulatory Compliance

Asset Condition

Capacity

Redundancy/Resiliency

Relocation or External Requests

Operational Efficiency

Safety

Administrative

Policy

Other _____________

 

 

BACKGROUND

 

PROJECT PURPOSE

                     The Floyd Branch RWWTP serves the City of Richardson and was originally built in 1952. The RWWTP currently has Texas Commission on Environmental Quality (TCEQ) permit limits of 4.75 million gallons per day (MGD) for annual average daily flow (AADF) and 10 MGD for peak two-hour flow (P2HF).

                     The Master Plan for the Floyd Branch RWWTP performed by Plummer Associates, Inc. (NTMWD Project No. 301-0546-19) indicates the AADF is not expected to increase.

                     This project consists of two phases.  The construction contract for phase I, which included improvements to the Ultraviolet disinfection system, was awarded in May 2023 by Administrative Memorandum No. 5915.  Phase I is on schedule to be completed in January 2026.  The construction contract for phase II, which includes improvements to the peak flow system, is now being presented for the Board’s consideration under this Administrative Memorandum.  

                     Increases in peak flows will be handled by a peak flow storage system, which will be sized based upon historical wet weather events.

 

PROJECT COMPONENTS

                     Construct process-related improvements, including:

o                     Headworks

o                     Influent Pump Station

o                     Wastewater Treatment Screens

o                     Peak Flow Storage Tank

                     Demolition of abandoned facilities

 

TABULATION OF BIDS

 

Sealed bids were received at 2:00 p.m. on Thursday, November 6, 2025, as tabulated below:

 

Bidder                     Total Bid                                          Recommendation

Felix Construction Company                     $36,981,000                                          Lowest responsible bid                                                                                     Recommended for Award

Harper Brothers Construction, LLC                     $57,589,000                     

ENGINEER’S OPINION OF                      $38,100,000

PROBABLE COST                                          

 

LOWEST RESPONSIBLE BIDDER HISTORY

 

Felix Construction Company has successfully completed or is currently constructing several similar projects for the NTMWD:

 

                     Project No. 101-0572-20, North Garland Ground Storage Tank (currently in construction)

                     Project No. 101-0338-13, Meter Vault Standardization, Set Point Control, Phase III; completed in May 2025

                     Project No. 309-0609-22, Stewart Creek West Wastewater Treatment Plant Primary Clarifier and Blower Improvements; completed in May 2025

 

Based on their standing as the lowest responsible bidder, the information provided, and reports by the supplied references, the NTMWD staff and CDM Smith, Inc., recommend award of the contract to Felix Construction Company.

 

ENGINEERING SERVICES AGREEMENT

 

Engineering services during construction for the Floyd Branch RWWTP Peak Flow Improvements are based on a planned 25-month construction duration in the amount of $761,868. These services include:

 

                     Monthly project management and coordination

                     Review of shop drawing submittals, request for information, proposed change orders, and operation and maintenance (O&M) manuals

                     Review the contractor’s monthly progress payment requests

                     Site visits and construction meetings

                     Startup assistance and substantial and final completion observations

                     Development of record drawings and updated equipment list

                     Participate in factory acceptance testing and functional demonstration testing

 

 

 

INSPECTION SERVICES

 

NTMWD will utilize its own inspection staff to cover all inspection tasks.  The cost to NTMWD related to this internal inspection coverage is estimated at $720,540.

 

FUNDING

 

Funding in the amount of $36,981,000 to Felix Construction Company, $761,868 to CDM Smith, Inc., and $720,540 for NTMWD Internal Inspection Services will be made available utilizing the Regional Wastewater System Extendable Commercial Paper (ECP) Program as the appropriation source; issuance of ECP notes will occur as cash needs arise.