Skip to main content
NTMWD Logo
File #: 25-6150    Version: 1
Type: Administrative Memorandum Status: Agenda Ready
File created: 6/9/2025 In control: Board of Directors
On agenda: 6/26/2025 Final action:
Title: Wylie Water Treatment Plant SCADA System Upgrades; Project No. 101-0630-23; Tabulation of Bids, Award of Contract, Engineering Services Agreement, and Inspection Services
Sponsors: Water Committee - Committee Action
Indexes: .RWS - Regional Water System, Engineering Services Agreement, Internal Inspection Services, Tabulation of Bids and Award of Contract
Code sections: 101-0630-23 - Wylie WTP SCADA System Upgrades
Attachments: 1. Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Regional Water System

 

title

Wylie Water Treatment Plant SCADA System Upgrades; Project No. 101-0630-23; Tabulation of Bids, Award of Contract, Engineering Services Agreement, and Inspection Services

 

end

SUBJECT

 

recommendation

Authorize award of a construction contract to Prime Controls, LP in the amount of $7,416,899; authorize internal inspection services in the amount of $577,200, and authorize an Engineering Services Agreement with Gupta and Associates, Inc. in the amount of $287,778 for construction phase engineering services for the Wylie Water Treatment Plant (WTP) Supervisory Control and Data Acquisition (SCADA) System Upgrades project.

 

end

PURPOSE

 

The programmable logic controller (PLC) equipment used to monitor and control the Wylie WTP ozone process has been deemed obsolete by NTMWD staff and the equipment manufacturer. The District has been moving towards high-performance graphics for improved human-machine interface (HMI) monitoring and control of the SCADA system. This project replaces the obsolete equipment and upgrades the interface programming, as documented in the 2021 Water System SCADA Roadmap Report.

 

RECOMMENDATION

 

The Executive Director and NTMWD staff recommend the Board of Directors authorize the award of a contract as follows:

 

Contractor:

Prime Controls, LP

 

 

Consultant:

Gupta and Associates, Inc.

 

 

Scope: 

Construction Contract, Internal Inspection Services, and Engineering Services During Construction

 

 

Project:

No. 101-0630-23; Wylie Water Treatment Plant SCADA System Upgrades

 

 

Amount:

Construction Contract: $7,416,899 Internal Inspection Services: $577,200 Engineering Services during Construction: $287,778    

 

 

Committee:

This will be an item on the June 25, 2025, Water Committee meeting agenda

 

DRIVER(S) FOR THIS PROJECT

 

Strategic Objective:

1.4 Reliable and  Resilient Systems

 

Regulatory Compliance

Asset Condition

Capacity

Redundancy/Resiliency

Relocation or External Requests

Operational Efficiency

Safety

Administrative

Policy

Other _____________

 

BACKGROUND

 

                     Wylie WTP’s I-IV uses ozone to disinfect water as well as improve taste and odor in the water treatment process. Two ozone production facilities are located at the Wylie WTP Complex, the North Ozone Operations Building (NOPS) and the South Ozone Operations Building (SOPS). Generated ozone flows from NOPS to contactors located at Water Treatment Plants III and IV, and from SOPS to contactors located at Water Treatment Plants I and II.

 

                     A Human Machine Interface (HMI) system is used to operate the Ozone SCADA System. Client Workstations are primarily used at NOPS and SOPS for production, and Client Workstations are located at each plant.

 

                     A Programmable Logic Controller (PLC) system is used to control the Ozone process. The Ozone PLC system is a vendor package from the ozone equipment manufacturer. The District has additional PLCs for monitoring and process control.

 

PROJECT PURPOSE

                     Per the 2021 Water System SCADA Roadmap Report, it is recommended to upgrade the aging and obsolete PLC and Network Switch infrastructure of the Wylie WTP Ozone System.

                     The 2021 Water System SCADA Roadmap Report recommends the human machine interface (HMI) graphics that are used by Operations to monitor and control the Ozone System be upgraded to the high-performance graphics detailed by the NTMWD HMI Configuration Standards and utilized on Wylie campus for other systems already.

 

PROJECT COMPONENTS

                     High-performance HMI graphics for Wylie WTP Ozone System.

                     Upgraded PLC and Network Switch Hardware for Wylie WTP Ozone System.

 

 

 

TABULATION OF BIDS

 

Sealed bids for construction were received at 2:00 p.m. on Thursday, May 29th, 2025, as tabulated below:

 

Bidder                     Total Bid                                          Recommendation

Prime Controls, LP                                                                                    $ 7,416,899.00                     Lowest responsible bid

                                                               Recommended for Award

RLC Controls, Inc.                     $ 10,093,101.25                     

                                          

ENGINEER’S OPINION OF

PROBABLE COST                     $7,010,000.00                     

 

Due to the technical nature and security sensitivity of facilities that are directly integrated with the NTMWD Global SCADA System, specific knowledge of the system is required in order to develop a competitive bid for this type of work.  Apart from Prime Controls, LP and RLC Controls, Inc., most prospective bidders have opted not to pursue these projects for NTMWD.  For this reason, it is not unusual to see only two bidders for this type of work.

 

LOWEST RESPONSIBLE BIDDER HISTORY

 

Prime Controls, LP has successfully completed or is currently in construction on several similar projects for the NTMWD:

 

                     Project No. 101-0556-20, North Water Transmission System SCADA Network Split, currently in construction

                     Project No. 101-0515-18, Wylie WTP’s Human-Machine-Interface (HMI) and Data Server Upgrades, currently under construction

                     Project No. 101-0534-19, Wylie WTP’s III and IV Filter Performance Improvements, completed February 2021

                     Project No. 101-0329-13, Water Transmission System SCADA Upgrade, completed October 2019

 

Based on their standing as the lowest responsible bidder, the information provided, and reports by the supplied references, the NTMWD staff and Gupta & Associates, Inc. recommend award of the contract to Prime Controls, LP.

 

ENGINEERING SERVICES AGREEMENT

 

Engineering services during construction for the Wylie Water Treatment Plant (WTP) Supervisory Control and Data Acquisition (SCADA) System Upgrades project are based on a planned 33-month construction duration in the amount of $287,778.00. These services include:

                     Monthly project management and coordination

 

 

                     Review of shop drawing submittals, request for information, proposed change orders, and operation and maintenance (O&M) manuals

                     Review the contractor’s monthly progress payment requests

                     Site visits and construction meetings

                     Workshop meetings

                     Startup assistance and substantial and final completion inspection

                     Development of record drawings and updated equipment list

                     Participate in factory witness testing

                     Participate in functional demonstration witness testing

 

INTERNAL INSPECTION SERVICES

 

NTMWD will utilize its own inspection staff to cover all inspection tasks.  The costs to the NTMWD related to this internal inspection coverage are approximately $577,200.

 

FUNDING

 

Funding in the amount of $7,416,899 to Prime Controls, LP, $287,778 to Gupta and Associates, Inc., and $577,200 to NTMWD Internal Inspection Services is to be made available utilizing the Regional Water System Extendable Commercial Paper (ECP) Program as the appropriation source; issuance of ECP notes will occur as cash needs arise.