Skip to main content
NTMWD Logo
File #: 26-6242    Version: 1
Type: Administrative Memorandum Status: Agenda Ready
File created: 3/17/2026 In control: Board of Directors
On agenda: 3/26/2026 Final action:
Title: Beck Branch Parallel Interceptor Improvements, Beck Branch Parallel Interceptor Phase II, and Plano Spring Creek Force Main Parallel; Final Settlement Agreement; Project No. 501-0439-16
Indexes: Settlement Agreement
Code sections: 501-0439-16 - Beck Branch Interceptor Improvements
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Upper East Fork Interceptor System

 

title

Beck Branch Parallel Interceptor Improvements, Beck Branch Parallel Interceptor Phase II, and Plano Spring Creek Force Main Parallel; Final Settlement Agreement; Project No. 501-0439-16

end

 

 

SUBJECT

 

recommendation

Authorize final global settlement agreement of lawsuit styled Ark Contracting Services, LLC v. North Texas Municipal Water District, Lockwood, Andrews & Newnam, Inc., Freese & Nichols, Inc., and Garver, LLC.; Cause No. 471-02694-2023; In the 471st Judicial District Court, Collin County, Texas.

end

 

 

PURPOSE

 

Authorize execution of final global settlement agreement resolving lawsuit.

 

 

RECOMMENDATION

 

The Executive Director, NTMWD staff, and Saunders | Walsh recommend the Board of Directors authorize execution of a global settlement agreement securing resolution of all claims in the lawsuit.

 

 

 

Scope: 

Global settlement related to ongoing litigation

 

 

Project:

No. 501-0439-16, Beck Branch Parallel Interceptor Improvements; Beck Branch Parallel Interceptor Phase II and Plano Spring Creek Force Main Parallel

 

 

Amount:

Confidential (to be discussed in Executive Session)

 

 

Committee:

This will be a Champion Update at the March 25, 2026 Wastewater Committee meeting

 

 

 

 

 

 

DRIVER(S) FOR THIS PROJECT

 

 

 

Regulatory Compliance

Asset Condition

Capacity

Redundancy/Resiliency

Relocation or External Requests

Operational Efficiency

Safety

Administrative

Policy

Other Legal Services

 

 

BACKGROUND

 

                     On May 26, 2023, Ark Contracting Services, LLC (ARK) filed suit against NTMWD, Lockwood, Andrews & Newnam (LAN - Engineer of Record), Garver (Leased Employee - Project Management), and Freese & Nichols (FNI - Inspection Services).

                     ARK’s current live pleading seeks recovery of $15,000,000 from NTMWD, plus attorneys’ fees and interest. ARK also sued LAN, Garver, and FNI in contract and tort, seeking similar actual damages, plus punitive damages of $25,000,000.

                     Trial is preferentially set on March 30, 2026.

                     Lawsuit arises out of a construction contract for the Beck Branch Parallel Interceptor Improvements, Beck Branch Parallel Interceptor Phase II and Plano Spring Creek Force Main Parallel (Project)(reference Administrative Memorandum No. 5557).

                     On May 28, 2020, NTMWD entered into the construction contract for Project. ARK’s bid was $20,869,584.

                     Open cut trenching began in early 2021. ARK’s primary claim is that NTMWD and the other defendants interfered with ARK’s means and methods of construction. ARK claims that the other defendants tortiously interfered with the contract, as well as committed acts of negligence, fraud, and conspiracy. NTMWD and the other defendants have at all times vigorously disputed these allegations.

                     On July 21, 2023, ARK sent a notice of contract termination and abandoned the Project. NTMWD contends that this was a material breach of the contract.

                     Upon ARK’s termination and abandonment, NTMWD made prompt demand upon ARK’s performance bond surety to satisfy its obligations under the bond and to complete ARK’s scope of work (or pay the District to do it). It refused.

                     NTMWD performed emergency work to remedy life/health/safety risks to the public caused by open trenches. NTMWD then re-packaged and re-bid the remaining scope of work and awarded the bid for completion work to Wilson Contractor Services, Inc. Original contract with Wilson: $16,757,742. Wilson’s work is nearing completion.

                     NTMWD filed counterclaims against ARK and the surety, seeking recovery of the amount spent by NTMWD in excess of ARK’s contract amount to correct and complete ARK’s abandoned scope of work. NTMWD’s principal claim is for $13,580,788.81.

                     Litigation has been ongoing since 2023.

                     Mediation took place on Saturday, February 28, 2026. It did not settle during the formal mediation, but negotiations have continued since that time.

                     On March 16, all other parties agreed to a global settlement agreement that would result in resolution of all claims in the case. All other parties to the litigation agreed to and signed this global settlement agreement.

 

 

 

FUNDING

 

Confidential (to be discussed in Executive Session). Funds will be credited back to the Upper East Fork Interceptor System Capital Program.