Skip to main content
NTMWD Logo
File #: 24-6012    Version: 1
Type: Administrative Memorandum Status: Agenda Ready
File created: 4/15/2024 In control: Board of Directors
On agenda: 4/25/2024 Final action:
Title: Shiloh Pump Station Improvements Phase I; Engineering Services Agreement; 101-0648-24
Sponsors: Water Committee - Committee Action
Indexes: .RWS, Engineering Services Agreement
Code sections: 101-0648-24 - Shiloh Pump Station Improvements Phase I
Attachments: 1. Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Regional Water System

 

title

Shiloh Pump Station Improvements Phase I; Engineering Services Agreement; 101-0648-24

end

 

SUBJECT

 

recommendation

Authorize funding for an engineering services agreement for the design of the Shiloh Pump Station Improvements, Phase I Project.

end

 

PURPOSE

 

The proposed improvements will replace aging infrastructure and upgrade certain systems to current NTMWD’s standards, including the addition of a new emergency backup power. Increased service demands for this facility and condition related replacements of critical elements of this facility necessitate these improvements to maintain NTMWDs ability to serve the Shiloh System.

 

RECOMMENDATION

 

The Executive Director and NTMWD staff recommend the Board of Directors authorize the Executive Director to execute an engineering services agreement (ESA) as follows:

 

Consultant:

Brown and Caldwell, Inc.

 

 

Scope:

Final Engineering Design

 

 

Project:

No. 101-0648-24, Shiloh Pump Station Improvements Phase I

 

 

Amount:

$1,888,427

 

 

Strategic Objective:

Strategic Objective: 1.2: Successfully Deliver Capital Program 1.4: Reliable and Resilient Systems

 

 

Committee:

This will be an item on the April 24, 2024, Water Committee meeting agenda

 

 

 

 

 

 

DRIVER(S) FOR THIS PROJECT

 

Regulatory Compliance (Pre-emptive)

Asset Condition

Capacity

Redundancy/Resiliency

Relocation or External Requests

Operational Efficiency

Safety

Administrative

Policy

Other _____________

 

BACKGROUND

 

The existing 3-million-gallon (MG) ground storage tank (GST) was constructed in 1969 and a subsequent project (No. 101-0306-12) was completed in 2017 to perform pump station improvements and minor leak repairs to the tank. The tank is considered to have reached the end of its service life and is recommended for removal.

 

PROJECT PURPOSE

                     Define and implement infrastructure improvements to the pump station and meter vaults to meet increased consumer water demands to the Richardson and Plano delivery points from the Shiloh Pump Station.

                     Evaluate items that may be in poor or failing condition and develop appropriate rehabilitation or replacement plans.

                     Provide improvements to fulfill operational capabilities defined in the NTMWD Emergency Preparedness Plan submitted to the Texas Commission on Environmental Quality (TCEQ).

                     The planning level estimated cost is $19,286,000.00.

 

PROJECT COMPONENTS 

                     Design flow control vault including, isolation and flow control valves.

                     Demolition and bypass pumping plan for the existing 3-MG ground storage tank

                     Update physical security capabilities at the site

                     Provide a new emergency backup generator

                     Improvements to the Richardson delivery vault radio and panel

                     Replace Pump Nos. 203 and 204 due to advanced deterioration

 

BASIC SERVICES

                     Preliminary design

                     Transient hydraulic model

                     Final design

                     30%, 60% 90% plans

                     100% bid documents

                     Bid phase services

 

 

 

 

 

 

SPECIAL SERVICES

                     Site survey

                     Geotechnical investigation and engineering report

                     Subsurface utility investigation

                     Regulatory coordination

 

CONSULTANT SELECTION PROCESS

 

                     Four engineering firms were interviewed and Brown and Caldwell, Inc. was deemed as the most highly qualified firm for this project.

 

 

ENGINEERING SERVICES FEE

 

Description                                                               Amount

 

Basic Services                                           $1,651,179

Special Services                                           $237,248

Requested Amount                      $1,888,427

 

 

 

FUNDING

 

Funding to Brown and Caldwell Inc in the amount of $1,888,427 is to be made available in the Regional Water System Capital Improvement Fund.