Legislation Details

File #: 26-6272    Version: 1
Type: Administrative Memorandum Status: Agenda Ready
File created: 6/9/2026 In control: Board of Directors
On agenda: 6/25/2026 Final action:
Title: Stover Creek Force Main Segment B, Project No. 501-0624-23; Tabulation of Bids, Award of Contract for Segment B, Engineering Services Agreement, and Authorize Inspection Services
Indexes: Authorize Inspection Services, Engineering Services Agreement
Code sections: 501-0624-23 - Stover Ck Force Main
Attachments: 1. Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Upper East Fork Interceptor System

 

title

Stover Creek Force Main Segment B, Project No. 501-0624-23; Tabulation of Bids, Award of Contract for Segment B, Engineering Services Agreement, and Authorize Inspection Services

end

 

SUBJECT

 

recommendation

Authorize award of a construction contract for Segment B in the amount of $12,939,441 to McKee Utility Contractors, LLC, authorize funding in the amount of $1,131,457 for an engineering services agreement with Lockwood Andrews & Newnam, Inc. for engineering services during construction, and authorize funding in the amount of $1,606,176 for internal inspection services for the Stover Creek Force Main project.

end

 

PURPOSE

 

The purpose of this project is to increase wastewater conveyance capacity of the Upper East Fork Interceptor System (UEFIS) by constructing a new lift station and force main to serve projected growth in McKinney and Prosper north of US Highway 380 (US 380), return capacity to the McKinney-owned sewers, and reduce the risk of sanitary sewer overflows in the UEFIS. All flows entering the Stover Creek Lift Station and Force Main are to be conveyed and treated at the Sister Grove Regional Water Resource Recovery Facility (RWRRF) via either direct conveyance or, on an interim basis, through existing NTMWD-owned conveyance systems.

 

RECOMMENDATION

 

The Executive Director and NTMWD staff recommend the Board of Directors authorize the award of a contract and services as follows:

 

Contractor:

McKee Utility Contractors, LLC

 

 

Consultant:

Lockwood Andrews & Newnam, Inc. (LAN)

 

 

 

 

Scope: 

Construction Contract, Engineering Services During Construction, and Internal Inspection Services

 

 

Project:

No. 501-624-23, Stover Creek Force Main Segment B

 

 

Amount:

Construction Contract: $12,939,441                                                                                           Engineering Services During Construction: $1,131,457                                                                                              Internal Inspection Services: $1,606,176

 

 

Committee:

This was an item on the May 27, 2026, Wastewater Committee meeting agenda

 

DRIVER(S) FOR THIS PROJECT

 

Strategic Objective:

1.2 Successfully Deliver Capital Program

 

Regulatory Compliance

Asset Condition

Capacity

Redundancy/Resiliency

Relocation or External Requests

Operational Efficiency

Safety

Administrative

Policy

Other _____________

 

BACKGROUND

 

PROJECT PURPOSE

                     The UEFIS Regional Capacity Assessment and Assurance study identified the need for a new lift station and force main to serve projected growth in McKinney and Prosper north of U.S. 380 and reduce the risk of surcharge and potential sanitary sewer overflows in the Upper East Fork Interceptor System.

                     Administrative Memorandum No. 6092 awarded final design to LAN in December 2024.  Final design is complete and recommends the following items, which have been reviewed with NTMWD staff:

o                     The Stover Creek Force Main will be four separate construction bid segments based upon the preliminary design recommendations.

o                     Segments A, B, and C, to be prioritized and connected to the newly upsized McKinney East Side Extension (NTMWD Project No. 501-0551-19) on an interim basis.

o                     Segment D completes conveyance of flow to the Sister Grove Regional Water Resource Recovery Facility (SGRWRRF).

 

PROJECT COMPONENTS

                     The proposed Stover Creek Force Main is approximately 69,000 linear feet (LF) of 48-inch force main, generally located from the proposed Stover Creek Lift Station near the intersection of U.S. 380 and Ridge Road to the Sister Grove RWRRF.

                     The force main will be procured in four separate construction bid packages. Segments A-C are scheduled to bid in 2026, and Segment D will be a future project.

                     Junction Structure to tie-in segments A-C to the McKinney East Side Extension.

                     Segment B is approximately 13,340 linear feet (LF) of the total 69,000 LF of 48-inch force main.

 

TABULATION OF BIDS

 

Sealed bids for Segment B were received at 2:00 p.m. on Thursday, May 14, 2026, as tabulated below:

 

Bidder

Total Bid

Recommendation

Pate Garver, LP

$10,637,224.00

 

Mountain Cascade of Texas, LLC

$12,027,410.00

 

McKee Utility Contractors, LLC

$12,939,441.00

Lowest responsible bid Recommended for Award

Belt Construction of Texas, LLC

$13,279,730.00

 

Wilson Contractor Services, LLC

$13,330,700.00

 

S.J. Louis Construction of Texas, Ltd.

$13,673,280.00

 

J&L Construction, LLC

$14,375,068.09

 

Blue Star Utilities, LLC

$15,081,874.50

 

Thalle Construction Co. LLC

$16,436,210.00

 

ENGINEER’S OPINION OF PROBABLE COST

$16,909,000.00

 

 

LOWEST RESPONSIBLE BIDDER HISTORY

 

Pate Garver, LP and Mountain Cascade of Texas, LLC, were found to be non- responsive bidders per the requirements in the instructions to bidders.

 

McKee Utility Contractors, LLC has successfully completed or is currently constructing several similar projects for the NTMWD:

 

                     Project No. 501-0551-19, McKinney East Side Extension Improvements (completed September 2025)

                     Project No. 101-0544-19, Plano McKinney Water Transmission System Phase I, Relocation of 60-inch Rowlett Cottonwood Transfer Sewer Parallel (completed October 2025)

                     Project No. 101-0526-18, Wylie to Rockwall Pipeline Relocation Phase I (completed February 2026)

                     Project No. 501-0514-18, North McKinney Transfer Force Main (Project is in service)

                     Project No. 501-0561-20, Forney Mustang Creek Parallel Force Main (currently under construction)

                     Project No. 501-0495-18, Wilson Creek Transfer Force Mains (currently under construction)

 

Based on their standing as lowest responsible bidder, the information provided, and reports by the supplied references, the NTMWD staff and Lockwood Andrews & Newnam, Inc., recommend award of the contract to McKee Utility Contractors, LLC.

 

 

 

 

ENGINEERING SERVICES AGREEMENT

 

Engineering services during construction for Segments A, B, and C of the Stover Creek Force Main are based on a 28-month construction duration in the amount of $1,131,457.00.  These services include:

 

                     Monthly project management and coordination

                     Review of shop drawings submittals, requests for information, proposed change orders and operation and maintenance manuals

                     Review the contractor’s monthly progress payment requests

                     Site visits and construction meetings

                     Substantial completion and final completion observations

                     Development of record drawings

 

INTERNAL INSPECTION SERVICES

 

NTMWD will utilize its own inspection staff to cover all inspection tasks for Segments A, B, and C of the Stover Creek Force Main.  The costs to the NTMWD related to this internal inspection coverage is estimated at $1,606,176.

 

FUNDING

 

Funding in the amount of $12,939,441 to McKee Utility Contractors, LLC, $1,131,457 to Lockwood Andrews & Newnam, Inc., and $1,606,176 for NTMWD internal inspection services is to be made available from the Upper East Fork Interceptor System Construction Funds.