Regional Water System
title
Leonard Treated Water Pipeline No. 2, Segment E; Project No. 101-0685-26; Engineering Services Agreement - Final Engineering Design
end
SUBJECT
recommendation
Authorize funding in the amount of $4,890,150 to HDR Engineering, Inc. for an engineering services agreement for final engineering design of the proposed Leonard Treated Water Pipeline No. 2, Segment E.
end
PURPOSE
This project will support the delivery of additional treated water from the Leonard Water Treatment Plant (WTP) to the north and east regions of the District's service area. Leonard Treated Water Pipeline No. 2 (TWPL2) will consist of approximately 130,400 linear feet (LF) of 84-inch diameter pipe from Leonard WTP High Service Pump Station (HSPS) to McKinney area. Design will be performed in two segments (Segment D and Segment E) by two engineering firms.
Segment E is approximately 58,000 LF is between Collin County Road 500 (in the vicinity of Blue Ridge) to the NTMWD's McKinney No. 3 to McKinney No. 4 Pipeline where it will connect to Segment D (separate Board action on this agenda).
RECOMMENDATION
The Executive Director and NTMWD staff recommend the Board of Directors authorize the Executive Director to execute an engineering services agreement (ESA) as follows:
Consultant:
HDR Engineering, Inc.
Scope:
Final Engineering Design
Project:
No. 101-0685-26, Leonard Treated Water Pipeline No. 2, Segment E
Amount:
$4,890,150
Committee:
This will be an item on the February 25, 2026, Water Committee agenda.
DRIVER(S) FOR THIS PROJECT
Strategic Objective:
1.2 Successfully Deliver Capital Program
1.4 Reliable and Resilient Systems
? Regulatory Compliance
? Asset Condition
? Capacity
? Redundancy/Resiliency
? Relocation or External Requests
? Operational Efficiency
? Safety
? Administrative
? Policy
? Other _____________
BACKGROUND
This project has b...
Click here for full text