Regional Water System
title
Plano West Side Pipeline, Plano Delivery Point No. 3 to Richardson Delivery Point No. 2, Project No. 101-0566-20, Water Line B, Change Order No. 5
end
SUBJECT
recommendation
Authorize funding in the amount of $849,457 to S.J. Louis Construction of Texas, Ltd. for a construction change order for the Plano West Side Pipeline, Plano Delivery Point No. 3 to Richardson Delivery Point No. 2 project.
end
PURPOSE
Authorize Change Order No. 5 increase in construction cost, which incorporates restoration of permanent paving along the construction site of the pipeline.
RECOMMENDATION
The Executive Director, NTMWD staff and Lockwood, Andrews, and Newnam, Inc. (LAN), recommend the Board of Directors authorize a construction change order as follows:
Contractor:
S.J. Louis Construction of Texas, Ltd. Scope:
Construction Change Order Project:
No. 101-0566-20, Plano West Side Pipeline, Plano Delivery Point No. 3 to Richardson Delivery Point No. 2, Water Line B
Amount:
$849,457
Committee: This will be an item on the October 21, 2026 Water Committee meeting agenda
DRIVER(S) FOR THIS PROJECT
Strategic Objective: 1.4 Reliable and resilient Systems
? Regulatory Compliance ? Asset Condition ? Capacity ? Redundancy/Resiliency ? Relocation or External Requests ? Operational Efficiency ? Safety ? Administrative
? Policy ? Other _____________
BACKGROUND
The existing 48-inch Plano West Side Pipeline Branches into two pipe segments to deliver water to the cities of Plano and Richardson from the Shiloh Pump Station, which is part of NTMWD’s south water transmission system.
The first pipe segment, built in 1974, is the existing 30-inch pipeline along Renner Road and Point North Parkway between Custer Road and Richardson Delivery Point No. 2 (Water Line A).
The second pipe segment built in 1975 is the existing 30-inch along Custer Road between Renner Road and Plano Delivery Point No. 3 (Water Line B).
...