Title: Tickey Creek Force Main; Project No. 501-0637-24; Tickey Creek Lift Station; Project No. 501-0638-24; Engineering Services Agreement, Final Engineering
Indexes: Engineering Services Agreement - Final Engineering
Code sections: 501-0637-24 - Tickey Creek Force Main, 501-0638-24 - Tickey Creek Lift Station
Attachments: 1. Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Upper East Fork Interceptor System

title
Tickey Creek Force Main; Project No. 501-0637-24; Tickey Creek Lift Station; Project No. 501-0638-24; Engineering Services Agreement, Final Engineering
end

SUBJECT

recommendation
Authorize funding in the amount of $7,038,900 to AECOM Technical Services, Inc. for an engineering services agreement for final design of the Tickey Creek Force Main and Tickey Creek Lift Station projects.
end

PURPOSE

The purpose of this project is to increase wastewater conveyance capacity serving growth in Princeton.

RECOMMENDATION

The Executive Director and NTMWD staff recommend the Board of Directors authorize the Executive Director to execute an engineering services agreement (ESA) as follows:

Consultant:
AECOM Technical Services, Inc.


Scope:
Final Engineering Design


Project:

No. 501-0637-24, Tickey Creek Force Main
No. 501-0638-24, Tickey Creek Lift Station


Amount:

$3,537,800.00, Tickey Creek Force Main
$3,501,100.00, Tickey Creek Lift Station


Committee:
This will be an item on the December 17, 2025, Wastewater Committee meeting agenda







DRIVER(S) FOR THIS PROJECT

Strategic Objective:
1.2: Successfully Deliver Capital Program
1.4: Reliable and Resilient Systems

? Regulatory Compliance
? Asset Condition
? Capacity
? Redundancy/Resiliency
? Relocation or External Requests
? Operational Efficiency
? Safety
? Administrative
? Policy
? Other _____________

BACKGROUND

PROJECT PURPOSE

* The Upper East Fork Interceptor System (UEFIS) Regional Capacity Assurance Phase 3 Report, dated November 1, 2023, recommended increased wastewater conveyance to meet the accelerated growth and increased flow projections serving Princeton.
* The Capacity A...

Click here for full text