Title: Rowlett Creek Trunk Sewer Extension Rehabilitation and Improvements; Project No. 501-0594-24; Resolution No. 24-34; Right of Way Acquisition Program
Sponsors: Real Estate Committee - Committee Action
Indexes: Right-of-Way Acquisition Program
Attachments: 1. Resolution, 2. Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Regional Wastewater System

title
Rowlett Creek Trunk Sewer Extension Rehabilitation and Improvements; Project No. 501-0594-24; Resolution No. 24-34; Right of Way Acquisition Program
end


SUBJECT

recommendation
Adoption of Resolution No. 24-34 authorizing funding in the amount of $650,000, to acquire temporary easements and enter necessary landowner agreements, and project name change.
end


PURPOSE

Easements and agreements are needed in order to rehabilitate manholes and pipeline segments within the Rowlett Creek Trunk Sewer Extension.


RECOMMENDATION

The Executive Director and NTMWD staff recommend the Board of Directors:

1) Authorize the Executive Director to execute a right-of-way acquisition program for the Rowlett Creek Trunk Sewer Extension Rehabilitation and Improvements, Project No. 501-0594-24, with a budget of $650,000; and,

2) Authorize a project name change from 508-0594-21 McKinney IS Rehabilitation and Improvements to 501-0594-24 Rowlett Creek Trunk Sewer Extension Rehabilitation and Improvements; and,

3) Adopt Resolution No. 24-34, "A Resolution Authorizing the Acquistion of Right-of-Way for the Rowlett Creek Trunk Sewer Extension Rehabilitation and Improvements, Project No. 501-0594-24.

Consultant:
N/A


Scope:

Right-of-way acquisition and support services necessary to facilitate the purchasing of easements


Project:

No. 501-0594-24, Rowlett Creek Trunk Sewer Extension Rehabilitation and Improvements


Amount:
$650,000


Committee:
This will be an item on the September 25, 2024, Real Estate Committee agenda


DRIVER(S) FOR THIS PROJECT

Strategic Objective:
1.2 - Successfully Deliver Capital Program


? Regulatory Compliance
? Asset Condition
? Capacity
? Redundancy/Resiliency
? Relocation or External Requests
? Operational Efficiency
? Safety
? Administrative
? Policy
? Other _____________


BACKGROUND

PROJECT PURPOSE
* NTMWD and the City of McKinney accepted the transfer of ownership of the McKinney-owned Rowlett Creek Trunk ...