Skip to main content
NTMWD Logo
File #: 24-6065    Version: 1
Type: Administrative Memorandum Status: Agenda Ready
File created: 9/12/2024 In control: Board of Directors
On agenda: 9/26/2024 Final action:
Title: Preston Road Lift Station Expansion; Project No. 501-0559-20; Resolution No. 24-35; Land Acquisition Program
Sponsors: Real Estate Committee - Committee Action
Indexes: Land Acquisition Program
Code sections: 501-0559-20 - Preston Rd Lift Station Expansion
Attachments: 1. Resolution, 2. Map, 3. Line List
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Upper East Fork Interceptor System

title
Preston Road Lift Station Expansion; Project No. 501-0559-20;
Resolution No. 24-35; Land Acquisition Program
end

SUBJECT

recommendation
Adoption of Resolution No. 24-35 authorizing an amendment to a previously existing land acquisition program to acquire additional property and provide additional funding in the amount of $2,100,000.
end

PURPOSE

Additional funding and acreage are needed for a new Peak Flow Storage Tank.

RECOMMENDATION

The Executive Director and NTMWD staff recommend the Board of Directors:

1) Authorize the Executive Director to amend a previously executed land acquisition program for the Preston Road Lift Station Expansion, Project No. 501-0559-20, by increasing the acreage to be purchased, and by providing additional funding in the amount of $2,100,000, resulting in the total authorization of $3,600,000; and,

2) Adopt Resolution No. 24-35, "A Resolution Authorizing the NTMWD Executive Director to Acquire Property for the Preston Road Lift Station Expansion, Project No. 501-0559-20"

Consultant:
N/A


Scope:

Land acquisition and the necessary support services to facilitate purchasing fee simple property and easements for the project


Project:
No. 501-0559-20, Preston Road Lift Station Expansion


Amount:
$2,100,000 additional funding


Committee:
This will be an item on the September 25, 2024, Real Estate Committee agenda



DRIVER(S) FOR THIS PROJECT

Strategic Objective:
1.2 - Successfully Deliver Capital Program

? Regulatory Compliance
? Asset Condition
? Capacity
? Redundancy/Resiliency
? Relocation or External Requests
? Operational Efficiency
? Safety
? Administrative
? Policy
? Other _____________


BACKGROUND

PROJECT PURPOSE
* Ad Memo 5855 and Resolution 22-38, August 2022, approved a Land Acquisition program with a budget of $1,500,000.
* The original design of the Preston Road Lift Station (PRLS) Expansion called for a parallel lift station to be constructed in conjunction wit...

Click here for full text