Regional Water System
title
Leonard Treated Water Pipeline to Farmersville
Delivery Point; Project No. 101-0632-23;
Engineering Services Agreement Final Engineering
end
SUBJECT
recommendation
Authorize an engineering services agreement (ESA) to HDR Engineering, Inc. in the amount of $5,199,428 for final engineering design for the Leonard Treated Water Pipeline to Farmersville Delivery Point project.
end
PURPOSE
The projected growth in NTMWD's East Water Transmission System will surpass the available capacity to that system from the Wylie Water Treatment Plant (WTP) within a few years. This project will supplement the needs of the East System from the new Leonard WTP through the year 2050.
RECOMMENDATION
The Executive Director and NTMWD staff recommend the Board of Directors authorize the Executive Director to execute additional engineering as follows:
Consultant:
HDR Engineering, Inc.
Scope:
Final Engineering Design, Real Estate Services
Project:
No. 101-0632-23, Leonard Treated Water Pipeline to Farmersville Delivery Point
Amount:
$5,199,428
Committee:
This will be an item on the November 20, 2024, Water Committee Agenda.
DRIVER(S) FOR THIS PROJECT
Strategic Objective:
Objective 1.1 - High Quality Services
Objective 1.4 - Reliable and Resilient Systems
? Regulatory Compliance
? Asset Condition
? Capacity
? Redundancy/Resiliency
? Relocation or External Requests
? Operational Efficiency
? Safety
? Administrative
? Policy
? Other _____________
BACKGROUND
This project is to provide a 48-inch diameter treated water pipeline to convey water from the existing Leonard treated water pipeline in the vicinity of Farm-to-Market Road 981 south to the existing Farmersville delivery point. The alignment selected during the initial phase of design is approximately 11.5 miles long. This scope is a continuation of the project design stage, advancing from 30% Preliminary design to the completion of bid documents and procurement of the pr...