Title: Wylie Water Treatment Plants I, II, III, and IV (I-IV) Filter Media Improvements - Request for Authorization to allow use of Alternate Project Delivery Method; Project No. 101-0615-22; Resolution No. 24-47
Sponsors: Water Committee - Committee Action
Indexes: .RWS, .RWS - Wylie Plant Complex, Authorization to use CMAR Delivery Method
Code sections: 101-0615-22 - Wylie WTP I, II, III and IV Filter Improvements
Attachments: 1. Resolution, 2. Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Regional Water System

title
Wylie Water Treatment Plants I, II, III, and IV (I-IV) Filter Media Improvements - Request for Authorization to allow use of Alternate Project Delivery Method; Project No. 101-0615-22; Resolution No. 24-47
end

SUBJECT

recommendation
Authorize the use of Construction Manager At-Risk (CMAR) project delivery method for the Wylie Water Treatment Plants (WTPs) I-IV Filter Improvements project.
end

PURPOSE

CMAR project delivery provides a distinct advantage of early identification and procurement of major construction materials and equipment that have traditional long lead times for configuration approvals, fabrication, and delivery to the project site.?Such items specific to this project includes filter underdrain blocks and replacement media for the filters.?The CMAR delivery approach allows the procurement process to progress concurrently with the detailed design, which helps compress the project's schedule.?Use of CMAR minimizes impact on operational requirements by right sizing planned work to limit impact on production at different times of the year. The CMAR delivery method provides the best value to the NTMWD.

RECOMMENDATION

??The Executive Director and NTMWD staff recommend the Board of Directors adopt Resolution No. 24-47, A Resolution authorizing the use of this alternative delivery approach in accordance with Texas Government Code Chapter 2269, Contracting and Delivery Procedures for Construction Projects. The Construction Manager at Risk delivery method will provide the best value to NTMWD.??

Consultant:

N/A


Scope:

N/A


Project:

No. 101-0615-22, Wylie Water Treatment Plants (WTPs) I, II, III, and IV (I-IV) Filter Media Improvements


Amount:

N/A


Committee:
This will be an item on the November 20, 2024, Water Committee meeting agenda


DRIVER(S) FOR THIS PROJECT

Strategic Objective:
?1.1 High Quality Services?

? Regulatory Compliance
? Asset Condition
? Capacity
? Redundancy/Resiliency
? Relocation o...