File #: 26C-5    Version: 1
Type: Consent Agenda Item Status: Agenda Ready
File created: 2/3/2026 In control: Board of Directors
On agenda: 2/26/2026 Final action:
Title: Princeton Lift Station Expansion - Pump Impeller Replacement; Project No. 501-0617-22; Award of Seller Services Agreement
Indexes: Tabulation of Proposals and Award of Agreement
Code sections: 501-0617-22 - Princeton Lift Station Improvements
Attachments: 1. Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Upper East Fork Interceptor System

title
Princeton Lift Station Expansion - Pump Impeller Replacement; Project No. 501-0617-22; Award of Seller Services Agreement
end

SUBJECT

recommendation
Authorize award of a seller services agreement in the amount of $262,892 to FCX Performance Inc. dba Pierce Pump Company.
end

PURPOSE

The purpose of this project is to increase wastewater conveyance capacity at a lift station providing service to the City of Princeton.

RECOMMENDATION

The Executive Director and NTMWD staff recommend the Board of Directors authorize the award of a contract as follows:

Contractor:

FCX Performance Inc. dba Pierce Pump Company


Scope:

Seller Services Agreement


Project:

No. 501-617-22, Princeton Lift Station Expansion -
Pump Impeller Replacement


Amount:

$262,892


Committee:

This will be an update at the February 11, 2026, Executive Committee meeting









DRIVER(S) FOR THIS PROJECT

Strategic Objective:
1.2 Successfully Deliver Capital Program
1.4 Reliable and Resilient System


? Regulatory Compliance
? Asset Condition
? Capacity
? Redundancy/Resiliency
? Relocation or External Requests
? Operational Efficiency
? Safety
? Administrative
? Policy
? Other _____________


BACKGROUND

PROJECT PURPOSE

* Due to continued growth at the City of Princeton, the capacity of the Princeton Lift Station No. 2 is being increased from 12 million gallons per day (MGD) to approximately 14.7 MGD by increasing the size of the pump impellers as recommended in the Princeton Conceptual Design Report, by AECOM Technical Services, Inc. (AECOM) dated February 2024.

PROJECT COMPONENTS

* Replace and upsize pump impellers.

TABULATION OF PROPOSALS

A proposal was received at 4:00 p.m. on Friday, December 19, 2025, as tabulated below:

Proposer
Total Cost
Recommendation
FCX Performance Inc. dba Pierce Pump Company
$262,892
Recommended for Award
EN...

Click here for full text