File #: 26-6234    Version: 1
Type: Administrative Memorandum Status: Agenda Ready
File created: 2/9/2026 In control: Board of Directors
On agenda: 2/26/2026 Final action:
Title: Leonard Treated Water Pipeline No. 2 Segment D; Project No. 101-0684-26; Engineering Services Agreement - Final Engineering Design
Indexes: Engineering Services Agreement - Final Design
Code sections: 101-0684-26 - Leonard Treated Water Pipeline No. 2, Segment D
Attachments: 1. Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Regional Water System

title
Leonard Treated Water Pipeline No. 2 Segment D; Project No. 101-0684-26; Engineering Services Agreement - Final Engineering Design
end

SUBJECT

recommendation
Authorize funding in the amount of $4,583,900 to Freese and Nichols, Inc. for an engineering services agreement for final engineering design of the proposed Leonard Treated Water Pipeline No. 2, Segment D.
end

PURPOSE

This project will support the delivery of additional treated water from the Leonard Water Treatment Plant (WTP) to the north and east regions of the District's service area. Leonard Treated Water Pipeline No. 2 (TWPL2) will consist of approximately 130,400 linear feet (LF) of 84-inch diameter pipe from the Leonard WTP High Service Pump Station (HSPS) to the McKinney area. Design will be performed in two segments (Segment D and Segment E) by two engineering firms.

Segment D is approximately 72,340 LF is between the Leonard WTP HSPS-South to Collin County Road 500, in the vicinity of Blue Ridge where it will connect to Segment E (separate Board action on this agenda).

RECOMMENDATION

The Executive Director and NTMWD staff recommend the Board of Directors authorize the Executive Director to execute an engineering services agreement (ESA) as follows:

Consultant:
Freese and Nichols, Inc. (FNI)


Scope:
Final Engineering Design


Project:

No. 101-0684-26, Leonard Treated Water Pipeline No. 2, Segment D


Amount:
$4,583,900


Committee:
This will be an item on the February 25, 2026, Water Committee agenda


DRIVER(S) FOR THIS PROJECT

Strategic Objective:
1.2 Successfully Deliver Capital Program
1.4 Reliable and Resilient Systems


? Regulatory Compliance
? Asset Condition
? Capacity
? Redundancy/Resiliency
? Relocation or External Requests
? Operational Efficiency
? Safety
? Administrative
? Policy
? Other _____________


BACKGROUND

This project has been under cons...