File #: 26-6236    Version: 1
Type: Administrative Memorandum Status: Agenda Ready
File created: 2/3/2026 In control: Board of Directors
On agenda: 2/26/2026 Final action:
Title: Leonard to Princeton Pipeline; Project No. 101-0686-26; Preliminary Engineering Services Agreement
Indexes: .RWS - Regional Water System, Preliminary Engineering - Engineering Services Agreement
Code sections: 101-0686-26 - Leonard to Princeton Pipeline
Attachments: 1. Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Regional Water System

title
Leonard to Princeton Pipeline; Project No. 101-0686-26; Preliminary Engineering Services Agreement

end
SUBJECT

recommendation
Authorize funding in the amount of $2,737,600 to AECOM Technical Services, Inc. for an engineering services agreement (ESA) for preliminary design of the Leonard to Princeton Pipeline project.

end
PURPOSE

Projected growth in the North System is expected to challenge the current capacity to deliver water efficiently and reliably from the Wylie Water Treatment Plant to the City of Princeton. The purpose of this project is to provide a reliable second source of treated water into the North System from the Leonard Water Treatment Plant to meet the projected demands.

RECOMMENDATION

The Executive Director and NTMWD staff recommend the Board of Directors authorize the Executive Director to execute an engineering services agreement (ESA) as follows:

Consultant:

AECOM Technical Services, Inc.


Scope:

Preliminary Engineering Services Agreement


Project:

No. 101-0686-26, Leonard to Princeton Pipeline


Amount:

$2,737,600


Committee:
This will be an item on the February 25, 2026, Water Committee meeting agenda










DRIVER(S) FOR THIS PROJECT

Strategic Objective:
1.1 High Quality Services
1.4 Reliable and Resilient Systems

? Regulatory Compliance
? Asset Condition
? Capacity
? Redundancy/Resiliency
? Relocation or External Requests
? Operational Efficiency
? Safety
? Administrative
? Policy
? Other _____________

BACKGROUND

The current and forecasted growth within the North and East Systems increases the demand and necessitates additional capacity be supplied by the Leonard Water Treatment Plant (WTP) to supplement Wylie WTP in the near-term demands.

PROJECT PURPOSE

* This project was identified in the 2021 Water Transmission System CIP Update as demand projections for the City of Princeton (City) ar...