Regional Water System
title
Texoma Raw Water Pipeline No. 2 and Texoma Raw Water Pipeline to Leonard Water Treatment Plant (WTP) Pipeline; Construction Manager-at-Risk Award Construction Management Services Agreement; Project No. 101-0633-23 and No. 101-0642-24
end
SUBJECT
recommendation
Authorize funding in the amount of $4,163,774 to Garney Companies, Inc. for the CMAR services during preconstruction and procurement process to the Construction Manager-at-Risk (CMAR) for the Texoma Raw Water Pipeline No. 2 and Texoma Raw Water Pipeline to Leonard Water Treatment Plant (WTP) Pipeline projects.
end
PURPOSE
The use of Construction Manager at-Risk (CMAR) project delivery method will provide the best value to NTMWD and in this case the opportunity to combine these two similar capital projects to leverage the advantages of early procurement of certain long lead time materials and equipment. This allows the procurement process to progress concurrently with the detailed design, helping to compress the project schedule.
RECOMMENDATION
The Executive Director and NTMWD staff recommend the Board of Directors authorize a CMAR agreement as follows:
CMAR:
Garney Companies, Inc.
Scope:
CMAR Services
Project:
No. 101-0633-23 Texoma Raw Water Pipeline No. 2, and
No. 101-0642-24 Texoma Raw Water Pipeline to Leonard WTP Pipeline
Amount:
Project No. 101-0633-23 (PN 633) - $3,131,830.50
Project No. 101-0642-24 (PN 642) - $1,031,943.50
Total - $4,163,774
Committee:
This will be an item on the October 22, 2025, Water Committee meeting agenda
DRIVER(S) FOR THIS PROJECT
Strategic Objective:
1.1 High Quality Services
1.4 Reliable and Resilient System Capacity
? Regulatory Compliance
? Asset Condition
? Capacity
? Redundancy/Resiliency
? Relocation or External Requests
? Operational Efficiency
? Safety
? Administrative
? Policy
? Other _____________
BACKGROUND
The u...
Click here for full text