Buffalo Creek Interceptor System
title
Buffalo Creek Lift Station No. 2; Project No. 507-0639-24; Tabulation of Bids, Award of Contract, and Inspection Services
end
SUBJECT
recommendation
Authorize award of a construction contract to Urban Infraconstruction, LLC in the amount of $32,219,360 and authorize internal inspection services in the amount of $805,560 for Buffalo Creek Lift Station No. 2 project.
end
PURPOSE
The purpose of this project is to increase wastewater conveyance capacity in the Buffalo Creek Interceptor System to accommodate growth in Forney, Heath, and Rockwall.
RECOMMENDATION
The Executive Director, NTMWD staff and Carollo Engineers, Inc recommend the Board of Directors authorize the award of a contract as follows:
Contractor:
Urban Infraconstruction, LLC
Scope:
Construction Contract and Internal Inspection Services
Project:
No. 507-0639-24, Buffalo Creek Lift Station No. 2
Amount:
Construction Contract: $32,219,360
Internal Inspection Services: $ 805,560
Committee:
This will be an item on the December 17, 2025, Wastewater Committee meeting agenda
DRIVER(S) FOR THIS PROJECT
Strategic Objective:
1.2 Successfully Deliver Capital Program
1.4 Reliable and Resilient Systems
? Regulatory Compliance
? Asset Condition
? Capacity
? Redundancy/Resiliency
? Relocation or External Requests
? Operational Efficiency
? Safety
? Administrative
? Policy
? Other _____________
BACKGROUND
PROJECT PURPOSE
* The 2021 Buffalo Creek Interceptor System Capacity Assessment & Assurance report identified the need for additional capacity in the Buffalo Creek System to meet projected demand growth in the cities of Forney, Heath and Rockwall.
* A 2023 Feasibility Analysis for Conveyance Alternatives Report recommends a new Buffalo Creek Lif...