File #: 26-6237    Version: 1
Type: Administrative Memorandum Status: Agenda Ready
File created: 2/9/2026 In control: Board of Directors
On agenda: 2/26/2026 Final action:
Title: Leonard Treated Water Pipeline to Farmersville Delivery Point; Project No. 101-0632-23; Tabulation of Bids and Award of Contract for Pipe Procurement
Indexes: Tabulation of Bids and Award of Contract
Code sections: 101-0632-23 - Leonard Treated Water Pipeline to Farmersville
Attachments: 1. Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Regional Water System

title
Leonard Treated Water Pipeline to Farmersville Delivery Point; Project No. 101-0632-23; Tabulation of Bids and Award of Contract for Pipe Procurement
end

SUBJECT

recommendation
Authorize award of a procurement contract in the amount of $15,257,175 to Northwest Pipe Company for pipe procurement, storage, and delivery for the Leonard Treated Water Pipeline to Farmersville Delivery Point project.
end

PURPOSE

To mitigate lead times and maintain the proposed construction schedule of the Leonard Treated Water Pipeline to Farmersville Delivery Point project, procurement of the 48-diameter pipe is required prior to awarding the project construction contract.

RECOMMENDATION

The Executive Director, NTMWD staff and HDR Engineering, Inc. recommend the Board of Directors authorize the award of a contract as follows:

Contractor:
Northwest Pipe Company


Scope:
Procurement, storage, and delivery of pipe


Project:

No. 101-0632-23, Leonard Treated Water Pipeline to Farmersville Delivery Point


Amount:
$15,257,175


Committee:
This will be an item on the February 25, 2026, Water Committee meeting agenda








DRIVER(S) FOR THIS PROJECT

Strategic Objective:
1.2 Successfully Deliver Capital Program
1.4 Reliable and Resilient Systems


? Regulatory Compliance
? Asset Condition
? Capacity
? Redundancy/Resiliency
? Relocation or External Requests
? Operational Efficiency
? Safety
? Administrative
? Policy
? Other _____________


BACKGROUND

PROJECT PURPOSE

* This project is to provide a 48-inch diameter treated water pipeline to convey water from the existing Leonard treated water pipeline in the vicinity of Farm-to-Market Road 981 south to the existing Farmersville delivery point.
* The proposed 48-inch pipeline will provide additional capacity to the East System to meet projected demands through the year 2050.
* This project was identified ...