Legislation Details

File #: 26-6269    Version: 1
Type: Administrative Memorandum Status: Agenda Ready
File created: 5/13/2026 In control: Board of Directors
On agenda: 5/28/2026 Final action:
Title: South Mesquite Creek Regional Wastewater Treatment Plant Peak Flow Management and Expansion, Project No. 301-0525-18; Amendment No. 10 to Construction Manager At-Risk; Buffalo Creek Parallel Force Main, Project No. 507-0640-24; Final GMP; Engineering Services During Construction; and Construction Management, Inspection, and Material Testing Services
Indexes: Amendment to CMAR Agreement , Construction Management Services Agreement - Inspection Services , Engineering Services During Construction
Code sections: 301-0525-18 - S Mesquite Ck WWTP Peak Flow Management, 507-0640-24 - Buffalo Ck Parallel Force Main
Attachments: 1. Attachment A-Contract Price Summary and Contract Amendment Summary, 2. Attachment B-Project Cost and Schedule Summary, 3. Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Buffalo Creek Interceptor System & Regional Wastewater System

title
South Mesquite Creek Regional Wastewater Treatment Plant Peak Flow Management and Expansion, Project No. 301-0525-18; Amendment No. 10 to Construction Manager At-Risk; Buffalo Creek Parallel Force Main, Project No. 507-0640-24; Final GMP; Engineering Services During Construction; and Construction Management, Inspection, and Material Testing Services
end

SUBJECT

recommendation
Authorize funding in the amount of $19,546,807 to Archer Western Construction, LLC for Amendment No. 10 to the Construction Manager At-Risk (CMAR) Agreement; to Carollo Engineers, Inc. in the amount of $498,200 for Engineering Services During Construction; and to AECOM Technical Services, Inc. in the amount of $961,193 for construction management, inspection, and material testing services for work related to the Buffalo Creek Parallel Force Main (BCPFM) Final Guaranteed Maximum Price (GMP).
end

PURPOSE

The purpose of this project is to improve peak flow management and increase wastewater conveyance capacity to accommodate growth in the South Mesquite Creek Regional Wastewater Treatment Plant service area. The CMAR has submitted the Final GMP for the South Mesquite Creek Regional Wastewater Treatment Plant Peak Flow Management and Expansion to 41 MGD and the Buffalo Creek Parallel Force Main projects.


RECOMMENDATION

The Executive Director and NTMWD staff recommend the Board of Directors authorize the Executive Director to execute Amendment No. 10 to the Construction Manager At-Risk, Engineering Services Agreement, and Construction Management, Inspection Services and Material Testing Agreements, and authorize the award of a contract as follows:

CMAR:

Archer Western Construction, LLC (Archer Western)


Consultant:

Carollo Engineers, Inc. (Carollo)


Construction Manager:
AECOM Technical Services, Inc. (AECOM)


Scope:

BCPFM Construction, BCPFM Final GMP;
BCPFM Engineering Services During Construction (ESDC); ...