Title: Panther Creek Wastewater Treatment Plant (WWTP) Expansion to 15 MGD; Project No. 307-0493-18; Change Order No. 4
Indexes: .Small Systems-307-Panther Crk WWTP, Change Order
Code sections: 307-0493-18 - Panther Ck WWTP Expansion to 15 MGD
Attachments: 1. Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Panther Creek Wastewater Treatment Plant System

title
Panther Creek Wastewater Treatment Plant (WWTP) Expansion to 15 MGD; Project No. 307-0493-18; Change Order No. 4
end

SUBJECT

recommendation
Authorize a reduction to the construction contract in the amount of $5,153,729 to Crossland Heavy Contractors, Inc. for the Panther Creek Wastewater Treatment Plant Expansion to 15 MGD project.
end

PURPOSE

This change order authorizes the removal of the Maintenance Building, the removal of the Administration Building Annex, the removal of a portion of paving around the Main Electrical Building area and the removal of the sidewalk along Fields Parkway from the construction contract. In addition, this change order authorizes the relocation of electrical conduits by Coserv that are in conflict with a drainage channel at the site.

RECOMMENDATION

The Executive Director, NTMWD staff and HDR Engineering, Inc. recommend the Board of Directors authorize a change order as follows:

Contractor:
Crossland Heavy Contractors, Inc.


Scope:
Change Order No. 4


Project:

No. 307-0493-18, Panther Creek Wastewater Treatment Plant Expansion to 15 MGD


Amount:
($5,153,729) credit


Committee:
This will be a Champion Update at the December 17, 2025, Wastewater Committee meeting






DRIVER(S) FOR THIS PROJECT

Strategic Objective:
1.1: High Quality Services
1.2: Successfully Deliver Capital Program


? Regulatory Compliance
? Asset Condition
? Capacity
? Redundancy/Resiliency
? Relocation or External Requests
? Operational Efficiency
? Safety
? Administrative
? Policy
? Other _____________


BACKGROUND

The Panther Creek Wastewater Treatment Plant (WWTP) serves a portion of the City of Frisco. The WWTP currently has a permitted discharge capacity of 10 million gallons per day (MGD) annual average daily flow (AADF). Population growth projections from the City of Frisco indicate that an e...

Click here for full text