Wylie Water Treatment Plant (WTP) II East System Interconnection; Project No. 101-0652-24; Tabulation of Bids and Award of Contract for Valve Procurement
end
SUBJECT
recommendation
Award valve procurement contract to Municipal Valve and Equipment Company, Inc. for the Wylie WTP II East System Interconnection project in the amount of $432,907.
end
PURPOSE
Due to the long lead times associated with manufacturing valves, this action enables the District to procure these items prior to awarding the construction contract. Having timely possession of the valves helps mitigate future construction delays.
RECOMMENDATION
The Executive Director, NTMWD staff and Kennedy Jenks recommend the Board of Directors authorize the award of a contract as follows:
Supplier:
Municipal Valve and Equipment Company, Inc.
Scope:
Procurement of two 36-inch butterfly valves and one sleeve valve with 30-inch flanges
Project:
No. 101-0652-24, Wylie WTP II East System Interconnection
Amount:
$432,907
Committee:
This will be a Champion Update at the June 25, 2025, Water Committee meeting
DRIVER(S) FOR THIS PROJECT
Strategic Objective:
1.4 Reliable and Resilient Systems
? Regulatory Compliance
? Asset Condition
? Capacity
? Redundancy/Resiliency
? Relocation or External Requests
? Operational Efficiency
? Safety
? Administrative
? Policy
? Other _____________
BACKGROUND
PROJECT PURPOSE
* The objective for the project is to provide additional capacity from Wylie WTP II to the East System by June 2026. This will be accomplished by constructing an interconnect pipeline between the High Service Pump Station (HSPS) 2-2/2-3 discharge and the 36-inch Wylie Rockwall Farmersville pipeline.
* To accomplish this task, tie-ins during the shutdown season need to be completed. Therefore, the isolation butterfly valves need to be procured to ensure they are available for installation by the contractor during the shutdown season.
* Similarly, ...