Legislation Details

File #: 26-6307    Version: 1
Type: Administrative Memorandum Status: Agenda Ready
File created: 10/7/2026 In control: Board of Directors
On agenda: 10/22/2026 Final action:
Title: Wylie Water Treatment Plant (WTP) Complex Valve Improvements; Project No. 101-0672-25; Tabulation of Proposals and Award of Contract, Authorize Additional Engineering Services, and Authorize Internal Inspection Services
Indexes: .RWS - Regional Water System, Authorize Inspection Services, Engineering Services Agreement, Tabulation of Bids and Award of Contract
Code sections: 101-0672-25 - Wylie WTP Complex Valve Improvements
Attachments: 1. Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Regional Water System


title
Wylie Water Treatment Plant (WTP) Complex Valve Improvements; Project No. 101-0672-25; Tabulation of Proposals and Award of Contract, Authorize Additional Engineering Services, and Authorize Internal Inspection Services

end
SUBJECT

recommendation
Authorize award of a Construction Contract to Felix Construction Company in the amount of $12,194,000 and authorize additional services to Pape-Dawson Consulting Engineers, LLC (PD) in the amount of $537,000 for Engineering Services During Construction (ESDC) and authorize internal inspection services in the amount of $245,250 for the Wylie WTP Complex Valve Improvements project.

end
PURPOSE

The Contractor will remove, replace, or install the six (6) identified critical valves on the North Garland 60-inch pipeline and the North Garland Pipeline No. 2 Phase I 72-inch pipeline. These valves improve the isolation capability, operational flexibility, and resilience of the two pipelines.

RECOMMENDATION

The Executive Director and NTMWD staff recommend the Board of Directors authorize the award of a contract as follows:

Contractor: Felix Construction Company (Felix)



Consultant: Pape-Dawson Consulting Engineers, LLC (PD) Scope:
Construction Contract, Engineering Services During Construction, and Internal Inspection Services Project: No. 101-0672-25, Wylie WTP Complex Valve Improvements
Amount:

Construction Contract: $12,194,000 (Felix)
Engineering Services During Construction: $537,000 (PD)
Internal Inspection Services $245,250 (NTMWD)



Committee: This will be an item on the October 21, 2026, Water Committee meeting agenda


DRIVER(S) FOR THIS PROJECT

Strategic Objective: 1.3 Proactive Asset and Maintenance Management
...