Legislation Details

File #: 26-6300    Version: 1
Type: Administrative Memorandum Status: Agenda Ready
File created: 8/18/2026 In control: Board of Directors
On agenda: 9/24/2026 Final action:
Title: Wylie Water Treatment Plant (WTP) II Process and Facilities Improvements; Project No. 101-0695-26; Engineering Services Agreement – Conceptual Study
Indexes: .RWS - Regional Water System, Engineering Services Agreement
Code sections: 101-0695-26 - Wylie Water Treatment Plant (WTP) II Process and Facilities Improvements
Attachments: 1. Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Regional Water System

title
Wylie Water Treatment Plant (WTP) II Process and Facilities Improvements; Project No. 101-0695-26; Engineering Services Agreement – Conceptual Study

end
SUBJECT

recommendation
Authorize funding in the amount of $770,100 to Jacobs Engineering Group, Inc. for an engineering services agreement for a Conceptual Study of the Wylie Water Treatment Plant (WTP) II Process and Facilities Improvements.

end
PURPOSE

The Conceptual Study will evaluate options for improving hydraulic and process performance and identifying condition-related deficiencies in the pre-treatment process equipment and structures. An additional consideration in evaluating improvement options will be sequencing of construction to limit the impact to plant production. The overall objective is to enhance the long-term reliability and resiliency of the Wylie Water Treatment Plant II and to extend the facility's service life.

RECOMMENDATION

The Executive Director and NTMWD staff recommend the Board of Directors authorize the Executive Director to execute an engineering services agreement (ESA) as follows:

Consultant:

Jacobs Engineering Group, Inc.

Scope:
Conceptual Study Project:
No. 101-0695-26 Wylie Water Treatment Plant (WTP) II Process and Facilities Improvements Amount:
$770,100 Committee: This will be an item on the September 23, 2026, Water Committee meeting agenda






DRIVER(S) FOR THIS PROJECT

Strategic Objective: 1.4 Reliable and Resilient System Capacity

? Regulatory Compliance
? Asset Condition ? Capacity ? Redundancy/Resiliency ? Relocation or External Requests ? Operational Efficiency ? Safety
? Administrative ? Policy ? Other _____________

BACKGROUND

The Wylie Water Treatment Plant (WTP) II is a 280 million gallon per day (MGD) treatment facility within the 840 MGD Wylie WTP complex. The facility, which is between 40 and 60 years old, is experiencing condition-related deficiencies, hydraulic limitations, and ...

Click here for full text