File #: 24-6062    Version: 1
Type: Administrative Memorandum Status: Agenda Ready
File created: 9/9/2024 In control: Board of Directors
On agenda: 9/26/2024 Final action:
Title: Preston Road Lift Station Expansion; Project No. 501-0559-20; Tabulation of Bids and Award of Contract, Internal Inspection Services, and Engineering Services Agreement
Sponsors: Wastewater Committee - Committee Action
Indexes: .UEFIS - Upper East Fork Interceptor System, Engineering Services Agreement, Inspection Services, Tabulation of Bids and Award of Contract
Code sections: 501-0559-20 - Preston Rd Lift Station Expansion
Attachments: 1. Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Upper East Fork Interceptor System

title
Preston Road Lift Station Expansion; Project No. 501-0559-20; Tabulation of Bids and Award of Contract, Internal Inspection Services, and Engineering Services Agreement
end

SUBJECT

recommendation
Award a construction contract to Red River Construction Co. in the amount of $17,132,500, authorize internal inspection services in the amount of $640,000, and authorize an engineering service agreement with HDR Engineering Inc in the amount of $764,712 for construction phase services for the Preston Road Lift Station Expansion project.
end

PURPOSE

This project includes pump and electrical improvements, odor control upgrades, and replacement of assets at the existing Preston Road Lift Station that have reached the end of their useful life. These improvements address needs identified in the wastewater conveyance lift station condition assessment program and Upper East Fork capacity assurance study to meet the projected long-term operating needs in the Upper East Fork Interceptor System.

RECOMMENDATION

The Executive Director and NTMWD staff recommend the Board of Directors authorize the award of contracts as follows:

Contractor:
Red River Construction Co.


Consultant:
HDR Engineering, Inc.


Scope:

Construction Contract, Engineering Services During Construction, and Internal Inspection Services


Project:
No. 501-0559-20, Preston Road Lift Station Expansion


Amount:

Construction Contract: $17,132,500
Inspection Services (Internal): $640,000
Engineering Services during Construction: $764,712


Committee:
This will be an item on the September 25, 2024, Wastewater Committee meeting agenda



DRIVER(S) FOR THIS PROJECT

Strategic Objective:
1.2 Successfully Deliver Capital Program
1.4 Reliable and Resilient System


? Regulatory Compliance
? Asset Condition
? Capacity
? Redundancy/Resiliency
? Relocation or External Requests
? Operational Efficiency
? Safety
? Administrative
? Policy
? Other _____________