Upper East Fork Interceptor System
title
North McKinney Parallel Interceptor Mitigation Projects;
Project No. 501-0504-18;
Tabulation of Bids and Award of Contract, and Inspection Services
end
SUBJECT
recommendation
Authorize award of a construction contract and internal inspection services
end
PURPOSE
Complete mitigation as required by the United States Army Corps of Engineers easement agreement for the North McKinney Parallel Interceptor.
RECOMMENDATION
The Executive Director, NTMWD staff and Teague Nall and Perkins, Inc. recommend the Board of Directors authorize the award of a contract as follows:
Consultant:
HGS, LLC dba RES Environmental Operating Company, LLC
Scope:
Construction Contract and Internal Inspection Services
Project:
No. 501-0504-18 North McKinney Parallel Interceptor Mitigation Projects
Amount:
$886,922.73 for construction contract and $110,400 for NTMWD inspection services
Strategic Objective:
Objective 1.2 Successfully Deliver Capital Program
Committee:
This item was discussed at the February 21, 2024, Wastewater Committee meeting.
DRIVER(S) FOR THIS PROJECT
? Regulatory Compliance
? Asset Condition
? Capacity
? Redundancy/Resiliency
? Relocation or External Requests
? Operational Efficiency
? Safety
? Administrative
? Policy
? Other _____________
BACKGROUND
PROJECT PURPOSE
* The United States Army Corps of Engineers (USACE) granted NTMWD a nationwide permit and mandated mitigation for an easement and construction of NTMWD Project No. 501-0504-18, the North McKinney Parallel Interceptor and a fiber optic line. The first part of the required mitigation was performed with the pipeline construction contract. This project will complete and satisfy the balance of USACE mitigation requirements.
* The mitigation value to satisfy is approximately $948,500. The cost of mitigation is to be based on actual contractor bid and construction costs. Approximately $110,300 was expended under Project No. 501-...
Click here for full text